Académique Documents
Professionnel Documents
Culture Documents
Qu 1
a. Operations management is an area of business concerned with the production of goods and
services, and involves the responsibility of ensuring that business operations are efficient in terms
of using as little resource as needed, and effective in terms of meeting customer requirements. It is
concerned with managing the process that converts inputs (in the forms of materials, labor and
energy) into outputs (in the form of goods and services).
Operations management is needed in organizations. The decisions it makes have a major impact on
both the cost of producing products or services and how well the products and services are
produced and delivered which has a major impact on the revenue coming into the organization. So,
operations management has an important impact on both revenue and cost and therefore profits.
Effective operations management can cost effectively increase efficiency, quality and
responsivenessto customers in order to give the organization a competitive advantage.
Qu 2b
Qu2c (vi)- Project duration 18 weeks
Schedule
All activities at normal times. No need to
crash any activity
Schedule
Crash only A by 1 week
Schedule
Crash A and E by 1 week each
Schedule
Crash A, Eand Gby 1 week each
Schedule
Crash A, B,D, E and G by 1 week each
Schedule
Crash A, D, E, Fand G by 1 week each and
crash B by 2 weeks
Qu2e
(i)- Both B & F employ “Oracle”
There is no impact for activities B & F to
employ “Oracle” because activity F starts
after the completion of activity B under the
normal time.
As we can see from Diagram 2, there are only 3 activities D, F & G on the critical path and each of them can
only be crashed by 1 week max. By crashing all three of them, the duration of the remained project can only
be reduced to 16 weeks. That means the whole project will still be delayed by 1 week.
Since the project will not be able to complete on time with the impact of delay. My recommendation isto
minimize the impact as much as much possible by paying an addition cost of $150 (crash cost of A, D, F, G))
to crash activities D, F and G by 1 week each. Reduce 4 days delay to 1day only.