Académique Documents
Professionnel Documents
Culture Documents
Here is the project report of a civil engineering student who has spent 6 months on a
training site.Due to security reasons,the project details, estimation, some portion of
design and quantity calculations have been omitted.But to help the civil engineering
students we had shown all the necessary works..
2) Demarcation of Site
5) Excavation
6) Laying of PCC
9) Concreting
11) Deshuttering
12) Brickwork
15) Plastering
17) Painting
Positioning of Central coordinate and layout- The centre point was marked with the
help of a thread and plumb bob as per the grid drawing. With respect to this center point,
all the other points of columns were to be decided so its exact position is very critical.
Excavation
Excavation was carried out both manually as well as mechanically. Normally 1-2 earth
excavators (JCB’s) were used for excavating the soil. Adequate precautions are taken to
see that the excavation operations do not damage the adjoining structures. Excavation is
carried out providing adequate side slopes and dressing of excavation bottom. The soil
present beneath the surface was too clayey so it was dumped and was not used for back
filling. The filling is done in layer not exceeding 20 cm layer and than its compacted.
Depth of excavation was 5’4” from Ground Level.
LAYING OF FOUNDATION
At our site, Raft foundations are used to spread the load from a structure over a large
area, normally the entire area of the structure. Normally raft foundation is used when
large load is to be distributed and it is not possible to provide individual footings due to
space constraints that is they would overlap on each other. Raft foundations have the
advantage of reducing differential settlements as the concrete slab resists differential
movements between loading positions. They are often needed on soft or loose soils with
low bearing capacity as they can spread the loads over a larger area.
In laying of raft foundation, special care is taken in the reinforcement and construction of
plinth beams and columns. It is the main portion on which ultimately whole of the
structure load is to come. So a slightest error can cause huge problems and therefore all
this is checked and passed by the engineer in charge of the site.
Apart from raft foundation, individual footings were used in the mess area which was
extended beyond the C and D blocks.
CEMENT
Portland cement is composed of calcium silicates and aluminate and aluminoferrite It is
obtained by blending predetermined proportions limestone clay and other minerals in
small quantities which is pulverized and heated at high temperature – around 1500 deg
centigrade to produce ‘clinker’. The clinker is then ground with small quantities of
gypsum to produce a fine powder called Ordinary Portland Cement (OPC). When mixed
with water, sand and stone, it combines slowly with the water to form a hard mass called
concrete. Cement is a hygroscopic material meaning that it absorbs moisture In presence
of moisture it undergoes chemical reaction termed as hydration. Therefore cement
remains in good condition as long as it does not come in contact with moisture. If cement
is more than three months old then it should be tested for its strength before being taken
into use.
The Bureau of Indian Standards (BIS) has classified OPC in three different grades The
classification is mainly based on the compressive strength of cement-sand mortar cubes
of face area 50 cm2 composed of 1 part of cement to 3 parts of standard sand by weight
with a water-cement ratio arrived at by a specified procedure. The grades are
(i) 33 grade
(ii) 43 grade
(iii) 53 grade
The grade number indicates the minimum compressive strength of cement sand mortar in
N/mm2 at 28 days, as tested by above mentioned procedure.
Pozzolana combines with lime and alkali in cement when water is added and forms
compounds which contribute to strength, impermeability and sulphate resistance. It also
contributes to workability, reduced bleeding and controls destructive expansion from
alkali-aggregate reaction. It reduces heat of hydration thereby controlling temperature
differentials, which causes thermal strain and resultant cracking n mass concrete
structures like dams. The colour of PPC comes from the colour of the pozzolanic material
used. PPC containing fly ash as a pozzolana will invariably be slightly different colour
than the OPC.One thing should be kept in mind that is the quality of cement depends
upon the raw materials used and the quality control measures adopted during its
manufacture, and not on the shade of the cement. The cement gets its colour from the
nature and colour of raw materials used, which will be different from factory to factory,
and may even differ in the different batches of cement produced in a factory. Further, the
colour of the finished concrete is affected also by the colour of the aggregates, and to a
lesser extent by the colour of the cement. Preference for any cement on the basis of
colour alone is technically misplaced.
SETTLING OF CEMENT
When water is mixed with cement, the paste so formed remains pliable and plastic for a
short time. During this period it is possible to disturb the paste and remit it without any
deleterious effects. As the reaction between water and cement continues, the paste loses
its plasticity. This early period in the hardening of cement is referred to as ‘setting’ of
cement.
Initial set is when the cement paste loses its plasticity and stiffens considerably. Final set
is the point when the paste hardens and can sustain some minor load. Both are arbitrary
points and these are determined by Vicat needle penetration resistance
Slow or fast setting normally depends on the nature of cement. It could also be due to
extraneous factors not related to the cement. The ambient conditions play an important
role. In hot weather, the setting is faster, in cold weather, setting is delayed Some types of
salts, chemicals, clay, etc if inadvertently get mixed with the sand, aggregate and water
could accelerate or delay the setting of concrete.
STORAGE OF CEMENT
It needs extra care or else can lead to loss not only in terms of financial loss but also in
terms of loss in the quality. Following are the don’t that should be followed -
(i) Do not store bags in a building or a godown in which the walls, roof and floor are not
completely weatherproof.
(ii) Do not store bags in a new warehouse until the interior has thoroughly dried out.
(iii) Do not be content with badly fitting windows and doors, make sure they fit properly
and ensure that they are kept shut.
(iv) Do not stack bags against the wall. Similarly, don’t pile them on the floor unless it is
a dry concrete floor. If not, bags should be stacked on wooden planks or sleepers.
(vi) Do not pile more than 15 bags high and arrange the bags in a header-and-stretcher
fashion.
(vii) Do not disturb the stored cement until it is to be taken out for use.
(viii) Do not take out bags from one tier only. Step back two or three tiers.
(ix) Do not keep dead storage. The principle of first-in first-out should be followed in
removing bags.
(x) Do not stack bags on the ground for temporary storage at work site. Pile them on a
raised, dry platform and cover with tarpaulin or polythene sheet.
COARSE AGGREGATE
Coarse aggregate for the works should be river gravel or crushed stone .It should be hard,
strong, dense, durable, clean, and free from clay or loamy admixtures or quarry refuse or
vegetable matter. The pieces of aggregates should be cubical, or rounded shaped and
should have granular or crystalline or smooth (but not glossy) non-powdery
surfaces.Aggregates should be properly screened and if necessary washed clean before
use.
Coarse aggregates containing flat, elongated or flaky pieces or mica should be rejected.
The grading of coarse aggregates should be as per specifications of IS-383.
After 24-hrs immersion in water, a previously dried sample of the coarse aggregate should not
gain in weight more than 5%.
Aggregates should be stored in such a way as to prevent segregation of sizes and avoid
contamination with fines.
Depending upon the coarse aggregate color, there quality can be determined as:
FINE AGGREGATE
Aggregate which is passed through 4.75 IS Sieve is termed as fine aggregate. Fine
aggregate is added to concrete to assist workability and to bring uniformity in mixture.
Usually, the natural river sand is used as fine aggregate. Important thing to be considered
is that fine aggregates should be free from coagulated lumps.
Grading of natural sand or crushed stone i.e. fine aggregates shall be such that not more
than 5 percent shall exceed 5 mm in size, not more than 10% shall IS sieve No. 150 not
less than 45% or more than 85% shall pass IS sieve No. 1.18 mm and not less than 25%
or more than 60% shall pass IS sieve No. 600 micron.
BRICKWORK
Brickwork is masonry done with bricks and mortar and is generally used to build
partition walls. In our site, all the external walls were of concrete and most of the internal
walls were made of bricks. English bond was used and a ration of 1:4 (1 cement: 4 coarse
sand) and 1:6 were used depending upon whether the wall is 4.5 inches or 9 inches. The
reinforcement shall be 2 nos. M.S. round bars or as indicated. The diameter of bars was
8mm. The first layer of reinforcement was used at second course and then at every fourth
course of brick work. The bars were properly anchored at their ends where the portions
and or where these walls join with other walls. The in laid steel reinforcement was
completely embedded in mortar.
2) Modular Bricks- Indian standard institution has established a standard size of bricks
such a brick is known as a modular brick. The normal size of brick is taken as 20*10*10
cm whereas its actual dimensions are 19*9*9 cm masonry with modular bricks workout
to be cheaper there is saving in the consumption of bricks, mortar and labour as compared
with masonry with traditional bricks.
2. Mix of motor.
The strength of brick masonry depends upon the strength of bricks used in the masonry
construction. The strength of bricks depends upon the nature of soil used for making and
the method adopted for molding and burning of bricks .since the nature of soil varies
from region to region ,the average strength of bricks varies from as low as 30kg/sq cm to
150 kg /sq cm the basic compressive stress are different crushing strength.
Continue Reading »
1) Fresh Concrete
2) Hardened Concrete
Fresh Concrete should be stable and should not segregate or bleed during transportation
and placing when it is subjected to forces during handling operations of limited nature.
The mix should be cohesive and mobile enough to be placed in the form around the
reinforcement and should be able to cast into the required shape without loosing
continuity or homogeneity under the available techniques of placing the concrete at a
particular job. The mix should be amenable to proper and through compaction into a
dense, compact concrete with minimum voids under the existing facilities of compaction
at the site. A best mix from the point of view of campactibility should achieve a 99
percent elimination of the original voids present.
SEGREGATION
The stability of a concrete mix requires that it should not segregate and bleed during the
transportation and placing. Segregation can be defined as separating out of the
ingredients of a concrete mix, so that the mix is no longer in a homogeneous condition.
Only the stable homogeneous mix can be fully compacted
The segregation depends upon the handling and placing operations. The tendency to
segregate, amount of coarse aggregate, and with the increased slump. The tendency to
segregate can be minimized by:
b. Not using the vibration as a means of spreading a heap of of concrete into a level mass
over a large area.
c. Reducing the continued vibration over a longer time, as the coarse aggregate tends to settle
to the bottom and the scum would rise to the surface.
BLEEDING
Bleeding is due to the rise of water in the mix to the surface because of the inability of
the solid particles in the mix to hold all the mixing water during settling of particles under
the effect of compaction. The bleeding causes formation of a porous, weak and non
durable concrete layer at the top of placed concrete. In case of lean mixes bleeding may
create capillary channels increasing the permeability of the concrete. When the concrete
is placed in different layers and each layer is compacted after allowing certain time to
lapse before the next layer is laid, the bleeding may cause a plane of weakness between
two layers. Any laitance formed should be removed by brushing and washing before a
new layer is added. Over compacting the surface should be avoided.
HARDENED CONCRETE
One of the most important properties of the hardened concrete is its strength which
represents the ability if concrete to resist forces. If the nature of the force is to produce
compression, the strength is termed compressive strength. The compressive strength of
hardened concrete is generally considered to be the most important property and is often
taken as the index of the overall quality of concrete. The strength can indirectly give an
idea of the most of the other properties of concrete which are related directly to the
structure of hardened cement paste. A stronger concrete is dense, compact, impermeable
and resistant to weathering and to some chemicals. However, a stronger concrete may
exhibit higher drying shrinkage with consequent cracking, due to the presence of higher
cement content.
Some of the other desirable properties like shear and tensile strengths, modulus of
elasticity, bond, impact and durability etc. are generally related to compressive strength.
As the compressive strength can be measured easily on standard sized cube or cylindrical
specimens, it can be specified as a criterion for studying the effect of any variable on the
quality of concrete. However, the concrete gives different values of any property under
different testing conditions. Hence method of testing, size of specimen and the rate of
loading etc. are stipulated while testing the concrete to minimize the variations in test
results. The statistical methods are commonly used for specifying the quantitative value
of any particular property of hardened concrete.
COMPRESSIVE STRENGTH
The compressive strength of concrete is defined as the load which causes the failure of
specimen, per unit area of cross-section in uniaxial compression under given rate of
loading. The strength of concrete is expressed as N/mm2. The compressive strength at 28
days after casting is taken as a criterion for specifying the quality of concrete. This is
termed as grade of concrete. IS 456 – 2000 stipulates the use of 150 mm cubes.
TENSILE STRENGTH
The concrete has low tensile strength; it ranges from 8-12 per cent of its compressive
strength. An average value of 10 per cent is generally adopted.
SHEAR STRENGTH
The concrete subjected to bending and shear stress is accompanied by tensile and
compressive stresses. The shear failures are due to resulting diagonal tension. The shear
strength is generally 12-13 per cent of its compressive strength.
BOND STRENGTH
3) The mortar / concrete should be consumed as early as possible after addition of water
to it. The hydration of cement starts the moment water is added to it. As the hydration
progresses the cement paste starts stiffening and loses its plasticity. The concrete should
not be disturbed after this. Normally, this is about 45 – 50 minutes.
(viii)Air entertainment
Use of minimum quantity of mixing water, consistent with the degree of workability
required to enable easy placing and compaction of concrete, is advisable.
Low water to cement ratio is essential for good performance of the structure in the
long run.
Use of too much or too little water for mixing, or water carelessly added during
mixing
Incomplete mixing of aggregate with cement
Leaving the finished concrete surface exposed to sun and wind during the first ten
days after placing without protecting it and keeping it damp by proper methods of
curing.
Construction joints are the joints provided between successive pours of concrete that have
been carried out after a time lag. As far as possible the construction joints should be
avoided and every care should be taken to keep their numbers minimal. Since, presence
of these joints creates a plane of weakness within the concrete body, these joints should
be preplanned and their location should be such that they are at places where they are
subjected to minimum bending moment and minimum shear force.
Concrete (M20) was used for all works in column, beams and slabs. It was well
consolidated by vibrating using portable mechanical vibrators. Care was taken to ensure
that concrete is not over vibrated so as to cause segregation. The layers of concrete are so
placed that the bottom layer does not finally set before the top layer is placed. The
vibrators maintain the whole of concrete under treatment in an adequate state of agitation,
such that deaeration and effective compaction is attained at a state commensurate with
the supply of concrete from the mixers. The vibrator continue during the whole period
occupied by placing of concrete, the vibrators being adjusted so that the centre vibrations
approximate to the centre of the mass being compacted at the time of placing. Shaking of
reinforcement for the purpose of compaction should be avoided. Compaction shall be
completed before initial setting starts i.e. within thirty minute of addition of water to the
dry mixture.
The concrete was deposited in its final position in a manner to preclude segregation of
ingredients. In case of column and walls, the shuttering was so adjusted that the vertical
drop of concrete is not more than 1.5 m at a time. In case of concreting of slabs and
beams, the pipe from the batching plant wasmix leads to the formation of Reinforced
Cement Concrete popularly known as RCC.
Concrete has two main stages
1) Fresh Concrete
2) Hardened Concrete
Fresh Concrete should be stable and should not segregate or bleed during transportation
and placing when it is subjected to forces during handling operations of limited nature.
The mix should be cohesive and mobile enough to be placed in the form around the
reinforcement and should be able to cast into the required shape without loosing
continuity or homogeneity under the available techniques of placing the concrete at a
particular job. The mix should be amenable to proper and through compaction into a
dense, compact concrete with minimum voids under the existing facilities of compaction
at the site. A best mix from the point of view of campactibility should achieve a 99
percent elimination of the original voids present.
SEGREGATION
The stability of a concrete mix requires that it should not segregate and bleed during the
transportation and placing. Segregation can be defined as separating out of the
ingredients of a concrete mix, so that the mix is no longer in a homogeneous condition.
Only the stable homogeneous mix can be fully compacted
The segregation depends upon the handling and placing operations. The tendency to
segregate, amount of coarse aggregate, and with the increased slump. The tendency to
segregate can be minimized by:
c. Reducing the continued vibration over a longer time, as the coarse aggregate tends to settle
to the bottom and the scum would rise to the surface.
BLEEDING
Bleeding is due to the rise of water in the mix to the surface because of the inability of
the solid particles in the mix to hold all the mixing water during settling of particles under
the effect of compaction. The bleeding causes formation of a porous, weak and non
durable concrete layer at the top of placed concrete. In case of lean mixes bleeding may
create capillary channels increasing the permeability of the concrete. When the concrete
is placed in different layers and each layer is compacted after allowing certain time to
lapse before the next layer is laid, the bleeding may cause a plane of weakness between
two layers. Any laitance formed should be removed by brushing and washing before a
new layer is added. Over compacting the surface should be avoided.
HARDENED CONCRETE
One of the most important properties of the hardened concrete is its strength which
represents the ability if concrete to resist forces. If the nature of the force is to produce
compression, the strength is termed compressive strength. The compressive strength of
hardened concrete is generally considered to be the most important property and is often
taken as the index of the overall quality of concrete. The strength can indirectly give an
idea of the most of the other properties of concrete which are related directly to the
structure of hardened cement paste. A stronger concrete is dense, compact, impermeable
and resistant to weathering and to some chemicals. However, a stronger concrete may
exhibit higher drying shrinkage with consequent cracking, due to the presence of higher
cement content.
Some of the other desirable properties like shear and tensile strengths, modulus of
elasticity, bond, impact and durability etc. are generally related to compressive strength.
As the compressive strength can be measured easily on standard sized cube or cylindrical
specimens, it can be specified as a criterion for studying the effect of any variable on the
quality of concrete. However, the concrete gives different values of any property under
different testing conditions. Hence method of testing, size of specimen and the rate of
loading etc. are stipulated while testing the concrete to minimize the variations in test
results. The statistical methods are commonly used for specifying the quantitative value
of any particular property of hardened concrete.
COMPRESSIVE STRENGTH
The compressive strength of concrete is defined as the load which causes the failure of
specimen, per unit area of cross-section in uniaxial compression under given rate of
loading. The strength of concrete is expressed as N/mm2. The compressive strength at 28
days after casting is taken as a criterion for specifying the quality of concrete. This is
termed as grade of concrete. IS 456 – 2000 stipulates the use of 150 mm cubes.
TENSILE STRENGTH
The concrete has low tensile strength; it ranges from 8-12 per cent of its compressive
strength. An average value of 10 per cent is generally adopted.
SHEAR STRENGTH
The concrete subjected to bending and shear stress is accompanied by tensile and
compressive stresses. The shear failures are due to resulting diagonal tension. The shear
strength is generally 12-13 per cent of its compressive strength.
BOND STRENGTH
3) The mortar / concrete should be consumed as early as possible after addition of water
to it. The hydration of cement starts the moment water is added to it. As the hydration
progresses the cement paste starts stiffening and loses its plasticity. The concrete should
not be disturbed after this. Normally, this is about 45 – 50 minutes.
(viii)Air entertainment
Use of minimum quantity of mixing water, consistent with the degree of workability
required to enable easy placing and compaction of concrete, is advisable.
Low water to cement ratio is essential for good performance of the structure in the
long run.
Use of too much or too little water for mixing, or water carelessly added during
mixing
Leaving the finished concrete surface exposed to sun and wind during the first ten
days after placing without protecting it and keeping it damp by proper methods of
curing.
Construction joints are the joints provided between successive pours of concrete that have
been carried out after a time lag. As far as possible the construction joints should be
avoided and every care should be taken to keep their numbers minimal. Since, presence
of these joints creates a plane of weakness within the concrete body, these joints should
be preplanned and their location should be such that they are at places where they are
subjected to minimum bending moment and minimum shear force.
Concrete (M20) was used for all works in column, beams and slabs. It was well
consolidated by vibrating using portable mechanical vibrators. Care was taken to ensure
that concrete is not over vibrated so as to cause segregation. The layers of concrete are so
placed that the bottom layer does not finally set before the top layer is placed. The
vibrators maintain the whole of concrete under treatment in an adequate state of agitation,
such that deaeration and effective compaction is attained at a state commensurate with
the supply of concrete from the mixers. The vibrator continue during the whole period
occupied by placing of concrete, the vibrators being adjusted so that the centre vibrations
approximate to the centre of the mass being compacted at the time of placing. Shaking of
reinforcement for the purpose of compaction should be avoided. Compaction shall be
completed before initial setting starts i.e. within thirty minute of addition of water to the
dry mixture.
The concrete was deposited in its final position in a manner to preclude segregation of
ingredients. In case of column and walls, the shuttering was so adjusted that the vertical
drop of concrete is not more than 1.5 m at a time. In case of concreting of slabs and
beams, the pipe from the batching plant was directly taken to the closest point.
COMPACTION
Green concrete has all the three phases – solids, water & air. In order to make the
concrete impervious & attain its maximum strength it is required to remove the entrapped
air from the concrete mass when it is still in plastic state. If the air is not removed
completely, the concrete loses strength considerably. It has been observed that 5% voids
reduce the strength by about 30% and 10% voids reduce the strength by over 50%.
Compaction eliminates air bubbles and brings enough fine material both to the surface
and against the forms to produce the desired finish. One can use such hand tools as steel
rods, paddling sticks, or tampers, but mechanical vibrators are best. Any compacting
device must reach the bottom of the form and be small enough to pass between
reinforcing bars. Since the strength of the concrete member depends on proper
reinforcement location, be careful not to displace the reinforcing steel.
C Compacting reinforced concrete work is very important and is done using iron rods. In
case the thickness of concrete layers should be more than 15 cm. the most satisfactory
method for compacting concrete properly is to consolidate each layer separately so that
its top surface become level and fairy smooth before the next layer is placed. While
tamping is carried out, care should be taken that the rod should penetrate the full layer of
the last layer placed and to some extent into lying to ensure proper bond between bond
between them. Secondly the reinforcement and formwork should not be disturbed from
their positions.
MECHANICAL COMPACTION
TYPES OF VIBRATORS
1. Internal vibrators
2. External vibrators
3. Surface vibrators
4. Vibrating table
Internal vibrator consists of metal road like vibrating head which is immersed in the full
depth of concrete layer. It is also known as poker or needle vibrator and is consider to be
most effective type of vibrator as it comes into intimate contact with concrete. External
vibrators are placed against the concrete form-work and vibrating force for compaction is
conveyed to the concrete through the form work. These vibrators are also called form
vibrators. The vibrator is rigidly clamped to form work resting on a elastic spot, so that
both the form and concrete are vibrated. Incase considerable proportion of work done is
consumed in vibrating resulting in low efficiency of the system. Surface vibrators are
mounted on platform and are generally used to compact and finish bridge, road slab etc.
These are also external vibrators and are suitable for precast concrete work. It provides a
reliable means of compaction of pre-cast concrete and has the adv of offering uniform
vibration. Vibrating table is used for consolidation of pre-cast units. Surface vibrators is
used there a wide horizontal surface occurs such as dams and very thick walls .large type
of surface vibrators is there but pen type vibrator are used most. When concrete is placed
on such tables, mechanical compaction takes place which has many advantages. Each
vibrator have its own advantages and disadvantages, hence the choice between different
types should be made correctly. Concrete to be compacted by vibration, should be
designed properly. The consistency of concrete depends of conditions of placing, type of
mix, and the efficiency of vibrator. The slum of such concrete should not be more than 5
cm in any case; otherwise segregation of concrete will take place, which should never be
allowed to occur.
a) All concrete while being poured against form work was worked with vibrator
b) All exposed surface of RCC lintels, beams, columns etc. were plastered to match
with adjoining plastered face of walls after suitably hacking the concrete surface.
Concrete Plant, also known as a Batch Plant, is a device that combines various
ingredients to form concrete. Some of these inputs include sand, water, aggregate (rocks,
gravel, etc.), fly ash, potash, cement, and other ingredients to create concrete. There are
two types of concrete plants, ready mix plants and central mix plant. A concrete plant can
have a variety of parts and accessories, including but not limited to: mixers (either tilt-up
or horizontal (or in some cases, both), cement batchers, aggregate batchers, conveyors,
radial stackers, aggregate bins, cement bins, heaters, chillers, cement silos, batch plant
controls, and dust collectors (to minimize environmental pollution).
The front view of the plant from where it hauls coarse aggregate is shown below:-
CURING
The term ‘curing’ is used to include maintenance of a favorable environment for the
continuation of chemical reactions, i.e. retention of moisture within, or supplying
moisture to the concrete from an external source and protection against extremes of
temperature
Beams and columns – The beams and columns can be maintained wet by tying gunny
bags around the periphery and by maintaining it wet always.
Ponding, continuous sprinkling, covering with wet cloth, cotton mats or similar materials,
covering with specially prepared paper, polyethylene, sealing coat applied as a liquid
commonly known as ‘curing compound’ which hardens to form a thin protective
membrane, are some of the methods by which concrete is cured. Curing should be started
just after the surfaces begin to dry. Normally 7 to 14 days curing is considered adequate.
ADMIXTURE
Admixtures are those ingredients/materials that are added to cement, water, and
aggregate mixture during mixing in order to modify or improve the properties of concrete
for a required application.
Some of the important purposes for which the admixtures could be used are
3. Increase in strength
4. Improvement in workability
The best way to test the admixture is by making trial mixes with the concrete materials to
be used on the job and carefully observing and measuring the change in the properties.
This way the compatibility of the admixture and the materials to be used, as well the
effects of the admixture on the properties of fresh and hardened concrete can be
observed. The amount of admixture recommended by the manufacturer or the optimum
quantity determined by laboratory tests should be used
Leakages occur because of variety of reasons; some of which are mentioned below –
a) Accumulation of water, which start penetrating the surface.
b) Poor quality and improper proportioning of concrete constituents that make concrete
permeable.
d) Construction joints at two different works like concrete and brick works, and
discontinuity in concrete casting (joint at old concrete and new concrete) leading
minute cracks, which facilitate water movement.
e) Other structural cracks because of loading conditions and failure of the structure to
withstand those stresses.
Following figure shows the damp proofing material which was used at site:
a) Provide good drainage facility with correct gradient at the places where there are
chances for water to accumulate.
b) Use good quality of materials with correct proportioning in concrete. For example, use
of blended cement and use of less water in concrete can reduce permeability of the
structure. Similarly, proper proportioning of materials would help concrete becoming
uniformly packed and dense.
d) Avoid construction joints becoming a weaker point for water to travel. Some proactive
and treatment measures would be useful.
e) Proper structural design and execution of members, which results no cracks for water
to percolate.
f) Proper damp proofing course required to avoid movement of ground and other water
from bottom to top. Some useful methods are like applying bitumen, concrete
construction etc. at plinth level.
PLASTERING
Plaster protects structure from temperature variations; external attacks of sulphates,
chlorides, etc. Plaster also provides smooth & aesthetic surface on RCC & Brickwork
surface. The proportion of mortar used at site for ceiling coat is 1:4 and wall coat is 1:3.
A plaster of 10 mm is done at ceiling and a plaster of 12.5mm is done at wall. Various
precautions to be taken while the work of plastering is going on are:-
•At the junction of Brickwork & RCC, chicken mesh or fiber mesh may be used.
•Wet the surface before plastering and cure the surface for at least 10 to 12 days.
FLOORING
The purpose of a floor is to provide a horizontal sanitary surface to support the occupants
of a building, furniture and equipment. A good floor should have strength and stability,
resistance to dampness, good appearance, and freedom from maintenance etc.
Tile flooring- It consists of ceramic, vitrified, terrazzo and cement tiles. Tiles give very
pleasant appearance to floors. Also, it can be executed fast. Vitrified and Ceramic tiles
have gained popularity over mosaic tiles because it doesn’t require grinding and polishing
and the appearance is good and the tiles are quite strong.
In ground floor the cement concrete floor is to be on 7.5 cm base of lime concrete or
weak cement concrete as per standard specifications. If the bases consist of cement
concrete it shall be allowed to set for about 7 days. In case the base is of weak cement
concrete the flooring shall commence within 48 hours of laying the base. In first floor or
upper floor if c.c. floor is to be laid on R.C.C. slab, the surface shall be made rough with
brushes while concrete is green. Before laying the c.c. floor the surface shall be cleaned,
wetted and a neat cement wash shall be applied to get a good bond.A layer of brick brats
ie broken bricks are laid before the laying of mortar and there by the tiles
ELECTRICAL CONDUITS
Separate conduits are laid for following systems:
b) Power points
c) AC points
d) Internet wiring
More Entries :
Comments
Reply
The mortar for plastering to be used in 30 min after that it has less strength,so mix
adequate to avoid wastage.
Reply
I have been making pavers but getting a lot of little holes on the top i have a
vibrating table and have done lots of time trials but get the same results
Reply
In the construction of septic tank, is it necessary replacing the corners block with
column? Thanks.
Reply
Reply
pl. provide information regarding vitrified tile bond strength ,shear strength and
tensile strength fixing with tile adhesive 3 mm thin bedding against it’s fixing
with cement sand mortar (1:6) bedding about 2.5 inches thickness
Reply
Reply
• Sasi Bhushan Gupta November 23, 2010 at 12:41 am