Académique Documents
Professionnel Documents
Culture Documents
S
ERS FA
CONRACT
N E OR
S ENG
I
Introduction www.osha.gov. It is suggested that posites, are included when they re-
Since 1994, representatives of the you download both the informa- semble structural steel in their usage.
steel industry have worked with the tion as it was printed in the Federal
Department of Labor to establish Register and the Final Regulatory Definitions [.751]
new rules for the safe erection of Text and Joist Tables A and B. The The following definitions are
structural steel. The recommenda- of particular interest:
Final Regulatory Text is in a format
tions of SENRAC (Steel Erection Ne- • Bridging Terminus Point
that is far easier to follow but is
gotiated Rulemaking Advisory • Column
Committee) were largely followed by without the illustrations that are in • Competent Person
OSHA and the product of this effort, the Federal Register version. • Constructibility
29 CFR Part 1926 Subpart R – Steel Should you use the Federal Regis- • Controlled Decking Zone
Erection, was published in the Fed- ter download only, skip to the mid- • Controlling Contractor
eral Register on January 18, 2001 dle of page 5265 where the subpart • Decking Hole
• Double Connection
with the guidance that they would actually begins. The information • Double Connection Seat
become effective 180 days later. The from page 5196 that precedes it is • Erection Bridging (for joists)
Bush Administration imposed a 60- informative background material, • Final Interior Perimeter
day delay on the implementation of but will not be easy to follow with- • Multiple Lift Rigging
this and other regulations. The White • Opening (in a decked area)
out a basic understanding of the
House has not given OSHA clear • Post (as opposed to a column)
regulations. • Project Structural Engineer of
guidance as to whether the 60-day
29 CFR Part 1926 is the OSHA reg- Record
delay adds to the implementation pe-
ulation for the construction industry. • Qualified Person
riod or runs concurrent with it.
Subpart R is specific to steel erection • Shear Connector
Therefore, the regulation may be-
and is a series of articles to the sub- • Systems–Engineered Metal Build-
come effective on July 18 or Septem-
part starting with 1926.750. As much ing
ber 18 of this year.
as possible, the relevant article will
This review is not intended to
be referenced, but in the text that fol-
list every aspect of the OSHA pro- lows 1926 will be omitted, as it is Contractor Responsibilities
visions, as they are far too numer- repetitive. [.752]
ous and detailed. Instead, it will The controlling Contractor (see
highlight the changes from the cur- def.) for the construction site and ac-
rent standard with emphasis on Scope of the Standard [.750] tivities now has specific responsibili-
those of particular interest to engi- The scope is extremely broad and ties as outlined below. The
encompasses virtually all activities of Controlling Contractor must:
neers, fabricators and contractors. • Provide notification that by testing,
It will be more meaningful if used steel erection. It applies to new con-
foundation and supporting walls
with a copy of the OSHA Regula- struction and the alteration or repair
have attained sufficient strength
of structures where steel erection oc- to support the steel to be erected.
tions, which can be downloaded
curs. Interestingly, other structural
from the OSHA website at
materials, such as plastics and com-
Joists [.757]
Regulations regarding joists are:
• Strut joists at or near columns must
be bolted [.757 (a) (1) and (2)]
• Increased strength of strut joists up
to 60 foot span [.757 (a) (3)]
Figure 6. Two-rod base. Figure 7. Inter-flange distance. • Strut joists over 60-foot span to be
set in tandem [.757 (a)(4)]
ments to • Joists may not be modified without
support the top and middle lines of the approval of the project struc-
the safety cables. This is not required tural engineer of record [.757
at openings such as stairwells, eleva- (a)(7)]
tor shafts, etc. • Unless panelized, joists of 40 foot
It is best left to the fabricator to de- or greater span must be bolted to
termine the most economical way to their supports unless con-
support the safety cables. Perimeter structibility does not allow [.757
(a) (8)]
safety cables must meet the require-
• Joists require erection bridging (see
ments for guardrail systems in def.) as specified in Tables A and
1926.502 (Appendix G) [.760 (d)(3)]. B[.757 (d)]
The fabricator and erector should • Erection bridging must be shown
contractually address the issue of the on the joist erection plans
custody of fall protection [.760 (e)]. [.757(d)(6)]
This topic is also addressed in the Figure 8. Single staggered • A bridging terminus point (see
Code of Standard Practice, Section 7.11. double connection. def.) must be established before
bridging is installed [.757 (a) (10)
and Appendix C]
• Bridging attachments must not
Joist Stabilizer Plates at protrude above the top chord.
Columns [.757 (a) (2) (i)] • Joist bridging bundles may not ex-
When columns are strutted with ceed 1000 lbs.. [.757 (e)(3)]
joists, the column must be provided • Decking or deck accessory bundles
with a plate to receive and stabilize may not exceed 4000 lbs. and may
the joist bottom chord. The plate be set on partially bridged joists
must be a minimum of 6 inches x 6 under controlled circumstances
inches and extended 3 inches below [.757 (e)(4)]
the joist bottom chord with a 13/16- Designers must take the bolting
Figure 9. Double staggered
inch diameter hole for attaching guy- requirements for joists of 40 foot
double connection. spans and over into consideration in
ing or plumbing cables (Figures
13-14). Figures 13 and 14 show de- beam design, particularly in can-
tails at column tops in cantilevered tilevered construction over the can-
girder construction. Figure 13 shows tilever support. Note that strut joists
stiffeners in the beam web above the require bolting and stabilizer plates
column. In this case, the stiffeners regardless of span. K-series joists
acting with a properly designed col- commonly use ½-inch diameter
umn cap will provide the necessary bolts, while LH-series and DLH-se-
continuity and stability for the col- ries joists use ¾-inch diameter bolts.
umn top. Thus, the joist bottom Fabricators must not arbitrarily in-
chord extensions need not be welded crease bolt diameters without verify-
to the stabilizer plates. In Figure 14 ing with the project structural
there is no stiffener over the column engineer of record that the additional
and stability of the column top is loss of net cross-sectional area will
provided by welding the extended Figure 10. Field-bolted temporary not affect the supporting member’s
bottom chords to the stabilizer plates. erection seat. design. Threaded studs may not be
These welded connections create used on walking/working surfaces
continuity in the joists. The resulting properly sized. The timing of the because they constitute a tripping
moments must be reported to the welding must be indicated so that it hazard [.754 (c)(1)]
joist supplier so that the joists are is consistent with the continuity mo-
Fall Protection/ Work Heights
[.760]
All erection activities where a fall
of greater that 15 feet can occur, re-
quire that the erector be protected by
guardrail systems, safety net sys-
tems, personal fall arrest systems, po-
sitioning device systems or fall
restraint systems (see Appendix G)
with the exception of connectors or
erectors working in a Controlled
Decking Zone – CDZ (see def.).
Figure 11. Shop-welded temporary
Connectors may work up to 30
erection seat. feet or two stories whichever is less
provided that they are trained re-
garding fall hazards and either be Figure 14. Girder over column
protected by the above methods or without web stiffeners and exten-
wear the equipment necessary to be sions welded to stabilizer plates.
tied off. The decision to be tied off is
solely the connectors. The connector
does not have this choice when fall
heights exceed 30 feet.
Controlled Decking Zones may be Conclusion
used to lay metal decking at fall As can be seen from the above dis-
height exposures of over 15 feet and cussion and the citation form the
up to 30 feet. Those erectors working new rules, subpart R has been sub-
Figure 12. Shop-welded temporary in CDZ areas are limited as to what stantially changed from the previous
erection seat, alternate. tasks they can perform and are re- rule. The last edition of the rules fo-
quired to be trained for this specific cused almost exclusively of the Erec-
Fabricators may want to limit joist
activity. Additional information re- tor. The new rules require the
bridging and deck bundle weights in
garding the CDZ may be found in participation of engineers, fabrica-
their purchase orders to their suppli-
Appendix D. Prior to allowing other tors and contractors. It behooves
ers.
erectors into the CDZ, it must be se- everyone involved in the design and
cured by covering or guarding deck- construction of steel building to be
Systems–Engineered Metal ing holes and openings and aware of these new rules and how
Buildings [.758] providing perimeter safety they affect their aspect of the de-
All requirements of Subpart R cable/guardrail systems where re- sign/construction process.
apply to systems–engineered metal quired. Refer to Appendix G and the
buildings (see def.) except as noted in previous discussion of safety cable/
this section. Additionally, there are Guardrail systems under Column
some safety requirements that are Splice Height at Perimeter Columns/
unique to this type of construction. Perimeter Safety Cable Attachments.
Erectors laying deck at fall exposure
heights exceeding 30 feet must either
be protected per [.760 (a)(1)] or under
other provisions as may be available
under Subpart M – Fall Protection.
Training [.761]
Specific training is required for
erectors and must be documented for
the following (see Appendix E):
• Fall hazard training
• Multiple lift rigging procedures
• Connector procedures
• Controlled Decking Zone proce-
dures