Vous êtes sur la page 1sur 5

NEW OSHA ERECTION RULES

HOW THEY AFFECT


R ICATOR
B

S
ERS FA

CONRACT
N E OR
S ENG
I

Barry L. Barger and Michael A. West

Introduction www.osha.gov. It is suggested that posites, are included when they re-
Since 1994, representatives of the you download both the informa- semble structural steel in their usage.
steel industry have worked with the tion as it was printed in the Federal
Department of Labor to establish Register and the Final Regulatory Definitions [.751]
new rules for the safe erection of Text and Joist Tables A and B. The The following definitions are
structural steel. The recommenda- of particular interest:
Final Regulatory Text is in a format
tions of SENRAC (Steel Erection Ne- • Bridging Terminus Point
that is far easier to follow but is
gotiated Rulemaking Advisory • Column
Committee) were largely followed by without the illustrations that are in • Competent Person
OSHA and the product of this effort, the Federal Register version. • Constructibility
29 CFR Part 1926 Subpart R – Steel Should you use the Federal Regis- • Controlled Decking Zone
Erection, was published in the Fed- ter download only, skip to the mid- • Controlling Contractor
eral Register on January 18, 2001 dle of page 5265 where the subpart • Decking Hole
• Double Connection
with the guidance that they would actually begins. The information • Double Connection Seat
become effective 180 days later. The from page 5196 that precedes it is • Erection Bridging (for joists)
Bush Administration imposed a 60- informative background material, • Final Interior Perimeter
day delay on the implementation of but will not be easy to follow with- • Multiple Lift Rigging
this and other regulations. The White • Opening (in a decked area)
out a basic understanding of the
House has not given OSHA clear • Post (as opposed to a column)
regulations. • Project Structural Engineer of
guidance as to whether the 60-day
29 CFR Part 1926 is the OSHA reg- Record
delay adds to the implementation pe-
ulation for the construction industry. • Qualified Person
riod or runs concurrent with it.
Subpart R is specific to steel erection • Shear Connector
Therefore, the regulation may be-
and is a series of articles to the sub- • Systems–Engineered Metal Build-
come effective on July 18 or Septem-
part starting with 1926.750. As much ing
ber 18 of this year.
as possible, the relevant article will
This review is not intended to
be referenced, but in the text that fol-
list every aspect of the OSHA pro- lows 1926 will be omitted, as it is Contractor Responsibilities
visions, as they are far too numer- repetitive. [.752]
ous and detailed. Instead, it will The controlling Contractor (see
highlight the changes from the cur- def.) for the construction site and ac-
rent standard with emphasis on Scope of the Standard [.750] tivities now has specific responsibili-
those of particular interest to engi- The scope is extremely broad and ties as outlined below. The
encompasses virtually all activities of Controlling Contractor must:
neers, fabricators and contractors. • Provide notification that by testing,
It will be more meaningful if used steel erection. It applies to new con-
foundation and supporting walls
with a copy of the OSHA Regula- struction and the alteration or repair
have attained sufficient strength
of structures where steel erection oc- to support the steel to be erected.
tions, which can be downloaded
curs. Interestingly, other structural
from the OSHA website at
materials, such as plastics and com-

Modern Steel Construction / May 2001


Code of Standard Practice, Section 1.8
and 7.10.

Tripping Hazards [.754 (c) (1)]


The shop placement of shear con-
nectors, weldable reinforcing bars,
deformed anchors or threaded studs
is prohibited where they would ob-
struct the walking surfaces of beams
Figure 1. Tripping hazards. or joists (Figure 1). The shop place-
ment of threaded studs on column
cap plates to receive strut joists, de-
formed bars on column webs or
shear studs on beam or column webs
is not prohibited since these are not
walking/ working surfaces (Figure
2).

Slippery Paint [.754 (c) (3)]


The implementation of a require-
ment that shop paints meet a mini-
Figure 2. Permitted shop attachments. mum slip resistance on walking
surfaces has been postponed for im-
• Provide notification of any repairs, the erector may only deviate from plementation until five years after
replacements or modifications to regulations in three
• Anchor bolts [see .755 (b) for instances:
further requirements]. • Modifications to
• Obtain approval from the Pro- crane hook
ject Structural Engineer of Record safety latches
for any repairs, replacements or [.753 (c) (5)]
modifications to Anchor bolts. • Setting strut joists
• Ensure that access roads and of over a 60 feet
conditions are suitable for steel span in tandem
erection. [.757 (a) (4)]
Bar other construction processes • Placing deck bun-
below steel erection unless overhead dles on joists
protection from falling objects is pro- that are not fully Figure 3. Opening frame.
vided [.759 (b)]. bridged [.757 (e)
The provisions regarding access (4)]
roads and site conditions are consis- Guidelines for
tent with the AISC Code of Standard developing a site-
the effective date of the rule so as to
Practice, Section 7.2. Fabricators and specific erection plan are contained
allow the technology of paint formu-
erectors may want to be cautious that in Appendix A to subpart R.
lation and means of measurement to
these requirements are not contractu- develop.
ally passed to them. Obviously, ac- Multiple-Lift Rigging Procedure
cess roads and reasonable site
[.753 (e)] Deck Openings [.754 (e) (2)]
conditions are required by and uti-
The regulations provide for multi- Where design constraints and
lized by all subcontractors. Note that
ple lifts providing certain procedures constructibility allow, the structural
subpart R uses the term “anchor
are used and training is documented. supports for deck openings are to be
bolt” where as AISC has adopted the
However, the fabricator and/or erec- fabricated so that decking runs con-
term “anchor rod” for embedded
tor may be contractually obligated to tinuously over the openings (Figure
materials to distinguish them from
observe more restrictive require- 3). This does not apply to major
steel-to-steel connectors.
ments in owner or contractor safety openings such as elevator shafts or
plans. stairwells. Other deck openings are
Site-Specific Erection Plan not to be cut until the opening is
[.752 (e)] needed. Contractual scopes should
Many erectors have indicated that Structural Stability [.754(a)] make clear who is responsible for the
they believe that a site-specific erec- Structural stability shall be main- cutting of these holes since the erec-
tion plan describing their actions will tained at all times during the erection tor may no longer be on the job or
allow them to deviate from those re- process. This is consistent with both erection activities may be located
quirements that do not suit them and the AISC Specifications and the AISC quite removed from the openings to
act in some alternative form. In fact, be cut.
quirements of the AISC Code of Stan-
dard Practice, dated March 7, 2000,
Sections 1.8 and 7.10.

Minimum Erection Bolts [.756


(a) and (b)]
The requirements given in the reg-
ulation are for the minimum number
Figure 4. Four-rod base. of bolts to be used during erection to
support a member until the crane’s Figure 5. 300 lb. load.
load line is released. Two bolts in
Column Anchor bolts (rods) 9. When seats (Figures 10-12) are
each connection are the minimum to
[.755] used, the beam must have a positive
connect solid web members and one
Columns are required to have a connection to the seat, while the sec-
bolt is the minimum for solid web
minimum of 4 anchor bolts (rods) ond member is erected. The figure in
bracing members or the equivalent
[.755 (a) (1)] (Figure 4) and those an- the Standard’s Appendix H shows
as specified by the project structural
chor bolts (rods) as well as the col- clipped plates where end plates are
engineer of record. The initial mini-
umn foundation are to capable of used as shear connections.
mum bolts are to be the same size
supporting a 300 lbs. (the weight of
and strength as shown in the erection
an erector and his tools) at the col-
drawings. The erector is required to Column Splice Strength [.756
umn top located at both 18 inches
maintain structural stability at all (b)]
from the face of the column flange
times during the erection process Column splices have the same
and from a plane at the tips of the
[.754 (a)] and the determination of 300-lb. loading requirement at the
column flanges (Figure 5) [.755 (a)
the number of bolts required to tem- top of the upper shaft as anchor bolts
(2)]. Posts (see def.) are not required
porarily support members is a re- (rods) (Figure 5). Again, the erector
to have 4 anchor bolts (rods) (Figure
sponsibility of the erector. Project must consider other factors, such as
6).
structural engineers of record should wind, and guy the column accord-
Engineers must design a column’s
to be cautious in involving them- ingly, if necessary.
base plate and supporting founda-
selves in the means and methods of
tion to accept the 4 anchor bolts
erection.
(rods). The clear distance between
Column Splice Locations [Ap-
column flanges (Figure 7) will not
allow for a significant spread be- Double Connections [.756 (c)] pendix F]
tween anchor bolts (rods) when Only double connections of beams Since connectors are required to
placed inside the flanges of W8 and to column webs or to the webs of tie off when the fall distance exceeds
W10 columns. It is recommended girders over columns in the case of 30 feet, placing column splices every
that they be placed outside the col- cantilevered construction are regu- three floors is a bad choice for the
umn at the base plate corners. Mini- lated, i. e., not at locations away from purposes of erection. The erector will
mum embedment lengths for anchor the columns. This boxes the bay with erect two floors, deck the second
bolts (rods) are given in the AISC strut beams. The rule is based on the level, and then erect and deck the
LRFD Manual of Steel Construction, fact that an erector commonly sits on third level before starting the process
2nd Edition in Table 8-26 on page the beam on the first side of the dou- again. It would be better for the de-
8–90. The designer may give consid- ble connection while the beam on the signer to place column splices either
eration to the fact that base plates fre- opposite side is connected in these every 2 floors or, in some cases, every
quently require slotting in the field to regulated instances. If the connection 4 floors so as to optimize the erection
accommodate misplaced anchor gets away from the erector, beam and process.
bolts. column collapse can occur and the
As noted above, anchor bolts erector may fall. Typical beam-to- Column Splice Height at
(rods) may not be repaired, replaced beam double connections (other than Perimeter Columns/ Perimeter
or modified in the field without the at a cantilever over a column) require
Safety Cable Attachments
approval of the project structural en- no special consideration since the
[.756 (e)]
gineer of record and the Controlling erector can instead sit on the girder
Except where constructability
Contractor must give the erector no- that receives both beams. At column
does not permit, perimeter columns
tification of any such alteration [.755 conditions, there are many ways to
must extend a minimum of 48”
(b)]. In the erection of all columns, facilitate safe double connections
above the finished floor so as to
the erector must evaluate the jobsite (Figures 8-12). The staggering of end
allow the attachment of safety cables.
erection conditions and factors such angles on each side of the column
Per [.760 (a) (2)], perimeter safety ca-
as wind, when the column will be web as shown in Figure 8 may not
bles are required at the final interior
tied in, etc. and determine the neces- stabilize the beam’s top flange unless
(see def) and exterior perimeters. The
sity for guying or bracing [.755 (a) metal deck is present and the angles
columns must be provided to the
(4)]. This is consistent with the re- may be better staggered on each side
erector with either holes or attach-
of the beam web as shown in Figure

May 2001 / Modern Steel Construction / 3


ments reported. For example, the ef-
fects of loads applied prior to weld-
ing need not be included in the
continuity moments.

Joists [.757]
Regulations regarding joists are:
• Strut joists at or near columns must
be bolted [.757 (a) (1) and (2)]
• Increased strength of strut joists up
to 60 foot span [.757 (a) (3)]
Figure 6. Two-rod base. Figure 7. Inter-flange distance. • Strut joists over 60-foot span to be
set in tandem [.757 (a)(4)]
ments to • Joists may not be modified without
support the top and middle lines of the approval of the project struc-
the safety cables. This is not required tural engineer of record [.757
at openings such as stairwells, eleva- (a)(7)]
tor shafts, etc. • Unless panelized, joists of 40 foot
It is best left to the fabricator to de- or greater span must be bolted to
termine the most economical way to their supports unless con-
support the safety cables. Perimeter structibility does not allow [.757
(a) (8)]
safety cables must meet the require-
• Joists require erection bridging (see
ments for guardrail systems in def.) as specified in Tables A and
1926.502 (Appendix G) [.760 (d)(3)]. B[.757 (d)]
The fabricator and erector should • Erection bridging must be shown
contractually address the issue of the on the joist erection plans
custody of fall protection [.760 (e)]. [.757(d)(6)]
This topic is also addressed in the Figure 8. Single staggered • A bridging terminus point (see
Code of Standard Practice, Section 7.11. double connection. def.) must be established before
bridging is installed [.757 (a) (10)
and Appendix C]
• Bridging attachments must not
Joist Stabilizer Plates at protrude above the top chord.
Columns [.757 (a) (2) (i)] • Joist bridging bundles may not ex-
When columns are strutted with ceed 1000 lbs.. [.757 (e)(3)]
joists, the column must be provided • Decking or deck accessory bundles
with a plate to receive and stabilize may not exceed 4000 lbs. and may
the joist bottom chord. The plate be set on partially bridged joists
must be a minimum of 6 inches x 6 under controlled circumstances
inches and extended 3 inches below [.757 (e)(4)]
the joist bottom chord with a 13/16- Designers must take the bolting
Figure 9. Double staggered
inch diameter hole for attaching guy- requirements for joists of 40 foot
double connection. spans and over into consideration in
ing or plumbing cables (Figures
13-14). Figures 13 and 14 show de- beam design, particularly in can-
tails at column tops in cantilevered tilevered construction over the can-
girder construction. Figure 13 shows tilever support. Note that strut joists
stiffeners in the beam web above the require bolting and stabilizer plates
column. In this case, the stiffeners regardless of span. K-series joists
acting with a properly designed col- commonly use ½-inch diameter
umn cap will provide the necessary bolts, while LH-series and DLH-se-
continuity and stability for the col- ries joists use ¾-inch diameter bolts.
umn top. Thus, the joist bottom Fabricators must not arbitrarily in-
chord extensions need not be welded crease bolt diameters without verify-
to the stabilizer plates. In Figure 14 ing with the project structural
there is no stiffener over the column engineer of record that the additional
and stability of the column top is loss of net cross-sectional area will
provided by welding the extended Figure 10. Field-bolted temporary not affect the supporting member’s
bottom chords to the stabilizer plates. erection seat. design. Threaded studs may not be
These welded connections create used on walking/working surfaces
continuity in the joists. The resulting properly sized. The timing of the because they constitute a tripping
moments must be reported to the welding must be indicated so that it hazard [.754 (c)(1)]
joist supplier so that the joists are is consistent with the continuity mo-
Fall Protection/ Work Heights
[.760]
All erection activities where a fall
of greater that 15 feet can occur, re-
quire that the erector be protected by
guardrail systems, safety net sys-
tems, personal fall arrest systems, po-
sitioning device systems or fall
restraint systems (see Appendix G)
with the exception of connectors or
erectors working in a Controlled
Decking Zone – CDZ (see def.).
Figure 11. Shop-welded temporary
Connectors may work up to 30
erection seat. feet or two stories whichever is less
provided that they are trained re-
garding fall hazards and either be Figure 14. Girder over column
protected by the above methods or without web stiffeners and exten-
wear the equipment necessary to be sions welded to stabilizer plates.
tied off. The decision to be tied off is
solely the connectors. The connector
does not have this choice when fall
heights exceed 30 feet.
Controlled Decking Zones may be Conclusion
used to lay metal decking at fall As can be seen from the above dis-
height exposures of over 15 feet and cussion and the citation form the
up to 30 feet. Those erectors working new rules, subpart R has been sub-
Figure 12. Shop-welded temporary in CDZ areas are limited as to what stantially changed from the previous
erection seat, alternate. tasks they can perform and are re- rule. The last edition of the rules fo-
quired to be trained for this specific cused almost exclusively of the Erec-
Fabricators may want to limit joist
activity. Additional information re- tor. The new rules require the
bridging and deck bundle weights in
garding the CDZ may be found in participation of engineers, fabrica-
their purchase orders to their suppli-
Appendix D. Prior to allowing other tors and contractors. It behooves
ers.
erectors into the CDZ, it must be se- everyone involved in the design and
cured by covering or guarding deck- construction of steel building to be
Systems–Engineered Metal ing holes and openings and aware of these new rules and how
Buildings [.758] providing perimeter safety they affect their aspect of the de-
All requirements of Subpart R cable/guardrail systems where re- sign/construction process.
apply to systems–engineered metal quired. Refer to Appendix G and the
buildings (see def.) except as noted in previous discussion of safety cable/
this section. Additionally, there are Guardrail systems under Column
some safety requirements that are Splice Height at Perimeter Columns/
unique to this type of construction. Perimeter Safety Cable Attachments.
Erectors laying deck at fall exposure
heights exceeding 30 feet must either
be protected per [.760 (a)(1)] or under
other provisions as may be available
under Subpart M – Fall Protection.

Training [.761]
Specific training is required for
erectors and must be documented for
the following (see Appendix E):
• Fall hazard training
• Multiple lift rigging procedures
• Connector procedures
• Controlled Decking Zone proce-
dures

Figure 13. Girder over column with


web stiffeners and stabilizer plates.

May 2001 / Modern Steel Construction / 5

Vous aimerez peut-être aussi