FANTSUAM SOLAR PROJECT PROGRESS REPORT

May, 2007

PROGRESS REPORT SOLAR BACKUP

Project Information Summary

Project Title: A Solar Power Electricity Backup System for Fantsuam


Foundation’s Community Wireless Network

IDRC Grant Number: 104192- 001

Institution Name: FANTSUAM FOUNDATION, Kafanchan. Nigeria

Working currency: Naira Currency of bank Account: UK Pounds Sterling

Commencement Date: 13th February, 2007

Report No. 1

Period of Report: 13th February – 25th May, 2007

Name of Project Leader: John Dada

Name of Authorized Financial Officer: Kazanka Comfort

Project Consultant: Dr Alberto Pascual-Escudero, IT+ 46 Ltd, Sweden

Team members: Ochuko Onoberhie, Owolabi Azeez, David Tsaro, Sunday


Oladayo, Joy Duniya, Sankwai Shekari, Omolayo Samuel

1
2
Introduction
The Solar backup program started with initial design work by the IDC
Consultant in November 2006. However, critical elements of the proposal
could not be confirmed until after the consultant’s visit to Fantsuam in
February, 2007. This report therefore covers February to May, 2007. It must
however be appreciated that this is not an independent project, as it is an
integral part of the Wireless project that started in June 2006.

Design work has now been completed, introductory training provided, EOIs
accepted and a final quotation for supply of equipment is now being awaited.

Status Report

Objectives Activities Status Report


Increment the number Implement an electricity Technical assessment which started
of working hours of the backup system based on in Nov 2006, required physical visit of
ICT infrastructure deep cycle batteries consultant in Feb, 2007 during which
connected to the grid data collection was undertaken.
The Research Support Grant
Agreement for the Solar Power
Electricity Backup System for
Fantsuam Foundation's Community
Wireless Network was received on
28th February, 2007
Improve the physical Implement six At the Feb visit, tender documents
security in the premises independent street lighting were made available on 27th March,
poles and EOIs were requested for the
Include a solar-powered different energy subsystems and their
‘signal light’ in the wireless loads.
communication tower On 14th May, the quotation of Yves
was accepted, and clarifications
requested from him.
On 30th May, Yves sent in his
response
Improve the availability Implement electricity To give more space to the new NOC,
of intranet and Internet backup system based on the Fantsuam VSAT will be relocated
core services to deep cycle batteries to the top of a roof. Bricks for the
Fantsuam Foundation connected to the grid in NOC have been produced. The line
and identified partners the Network Operation items from which savings are to be
within the community Centre, NOC made to accommodate costs for the
Implement a solar panel NOC is yet to be decided. In the
subsystem to extend the meantime, to take advantage of
autonomy of the NOC available labour, excavation of
foundation is to start on 19th June
Expand the network by Establish two solar-power These activities will await next visit of
means of establishing repeaters that will enable consultant in Sept, 2007. The second
two solar powered the expansion of the supervisory visit as in the approved
repeaters backhaul network to proposal was to have taken place in
include another 5 partners May 2007.
and increase the service
area of the community

3
network
Improve the availability Implement an electricity These activities will await next visit of
of the wireless backup system based on consultant in Sept, 2007
backbone network deep cycle batteries
connected to the grid and
solar panels in the
wireless backbone nodes
that act as repeaters
Build capacity within Conduct basic general Basic training of FF staff in renewable
Fantsuam Foundation training in the energies took place during the Feb
in designing, dimensioning and visit
implementing and simulation of solar-
maintaining electricity powered autonomous and
backup systems with back-up systems
solar panels and deep Develop manuals and
cycle batteries training material
Deploy a set of backhaul
communication links and
clients installation using
electricity backup systems
jointly with Fantsuam
Foundation staff

Implementation Plan, June to Sept, 2007

June 4 – 17th Final quotation received from Yves


June 11 – 30th Construction of NOC
June 15 – Sep Socio-economic impact of CWN
June 25th Relocation of VSAT Dish
June 18 – 30th Solar Installations at FF
July 1 Installation of Pay As You Go
Jul 1 – 30th Low Power PCs
August 1- 31st Marketing, installations, in-house training
June – August Team meetings, weekly
July 15 Draft kick off program circulated
September Kick off