ID Task Name Duration Start Finish Predecessors 05 Dec '10 12 Dec '10 19 Dec '10 26 Dec '10 02 Jan

05 Dec '10 12 Dec '10 19 Dec '10 26 Dec '10 02 Jan '11 09 Jan '11
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 Hotel Project @ Tirupur 1 day? Fri 03-12-10 Fri 03-12-10
2 Civil works 240 days Fri 03-12-10 Thu 20-10-11
3 Release of GFC drawings 1 day? Thu 14-04-11 Thu 14-04-11
4 Basemnet & Ground floor 1 day? Mon 18-04-11 Mon 18-04-11
5 Basemnet slab casting 1 day? Tue 28-06-11 Tue 28-06-11 75
6 Ground floor slab-Lobby 14 days? Wed 29-06-11 Fri 15-07-11 5
7 First floor slab 14 days? Mon 18-07-11 Thu 04-08-11 6
8 Second floor slab 14 days Fri 05-08-11 Wed 24-08-11 7
9 Service floor slab 14 days Thu 25-08-11 Tue 13-09-11 8
10 Third floor slab 14 days Wed 14-09-11 Fri 30-09-11 9
11 Fourth floor slab 14 days Mon 03-10-11 Thu 20-10-11 10
12 Fifth floor slab 14 days Fri 21-10-11 Wed 09-11-11 11
13 Sixth floor slab 14 days Thu 10-11-11 Tue 29-11-11 12
14 Seventh floor slab 14 days Wed 30-11-11 Mon 19-12-11 13
15 ELECTRICAL WORKS 1 day? Thu 01-12-11 Thu 01-12-11
16 Preparation of tender drawings & tender 171 days? Wed 20-04-11 Thu 01-12-11
17 Float enquiries 5 days Mon 25-04-11 Fri 29-04-11
18 Receiving the quotes 3 days Mon 02-05-11 Wed 04-05-11 17
19 Consultants review 5 days? Fri 06-05-11 Tue 10-05-11
20 Final negotiation 2 days? Wed 11-05-11 Thu 12-05-11 19
21 Award contract 2 days Fri 13-05-11 Mon 16-05-11 20
22 Shop drawing submissions 5 days? Tue 17-05-11 Mon 23-05-11 21
23 Review and release of GFC drawings 2 days? Tue 24-05-11 Wed 25-05-11 22
24 Mobilise comments & complete works 141 days? Thu 26-05-11 Thu 01-12-11 23
25 DG set works 77 days? Thu 01-09-11 Thu 15-12-11
26 Preparation of tender document 6 days? Thu 01-09-11 Thu 08-09-11 89
27 Float enquiries 5 days? Fri 09-09-11 Thu 15-09-11 26
28 Receive quotes 6 days? Fri 16-09-11 Thu 22-09-11 27
29 Consultants review 7 days? Fri 23-09-11 Mon 03-10-11
30 Final negotiation 5 days? Tue 04-10-11 Mon 10-10-11 29
31 Award contract 1 day? Tue 11-10-11 Tue 11-10-11 30
32 Supply 38 days? Tue 11-10-11 Thu 01-12-11
33 Erection & Comissioning 10 days Thu 01-12-11 Wed 14-12-11
34 FA/PA/CCTV & ACCESS CONTROL 159 days? Wed 20-04-11 Tue 15-11-11
35 Preparation of tender document 8 days? Wed 20-04-11 Wed 27-04-11
36 Float enquiries 3 days? Thu 28-04-11 Mon 02-05-11 35
37 Receive quotes 7 days? Tue 03-05-11 Mon 09-05-11 36
38 Consultants review 3 days? Tue 10-05-11 Thu 12-05-11 37
39 Final negotiation 4 days? Fri 13-05-11 Wed 18-05-11 38
40 Award contract 4 days Thu 19-05-11 Tue 24-05-11 39
41 Supply 48 days? Wed 25-05-11 Mon 25-07-11 40
42 Erection & Comissioning 81 days? Wed 27-07-11 Tue 15-11-11
43 FIREFIGHTING 162 days? Mon 25-04-11 Fri 25-11-11
44 Preparation of tender document 5 days? Mon 25-04-11 Fri 29-04-11
45 Float enquiries 5 days? Mon 02-05-11 Fri 06-05-11 44
46 Receive quotes 5 days Sat 07-05-11 Wed 11-05-11 45
47 Consultants review 3 days Thu 12-05-11 Mon 16-05-11 46
48 Final negotiation 3 days Tue 17-05-11 Thu 19-05-11 47
49 Award contract 2 days Fri 20-05-11 Mon 23-05-11 48
50 Supply 93 days? Wed 25-05-11 Fri 23-09-11
51 Erection & Comissioning 121 days? Wed 15-06-11 Fri 25-11-11
52 HVAC 207 days? Tue 26-04-11 Mon 30-01-12

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 1
ID Task Name Duration Start Finish Predecessors 05 Dec '10 12 Dec '10 19 Dec '10 26 Dec '10 02 Jan '11 09 Jan '11
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
53 Preparation of tender document 4 days? Tue 26-04-11 Fri 29-04-11 96
54 Float enquiries 4 days Mon 02-05-11 Thu 05-05-11 53
55 Receive quotes 4 days Fri 06-05-11 Mon 09-05-11 54
56 Consultants review 2 days Tue 10-05-11 Wed 11-05-11 55
57 Final negotiation 2 days Thu 12-05-11 Fri 13-05-11 56
58 Award contract 2 days Mon 16-05-11 Tue 17-05-11 57
59 Supply 1 day? Wed 25-05-11 Wed 25-05-11
60 Double skin FCU with valve package , AHU &
93Chiller
days? Wed 25-05-11 Sun 25-09-11
61 Low side Works 56 days? Mon 26-09-11 Mon 12-12-11 50
62 Erection & Comissioning 91 days? Mon 26-09-11 Mon 30-01-12 60
63 PLUMBING 200 days? Mon 18-04-11 Mon 09-01-12
64 Preparation of tender document 1 day Mon 18-04-11 Mon 18-04-11
65 Float enquiries 7 days Wed 20-04-11 Tue 26-04-11
66 Receive quotes 4 days Wed 27-04-11 Mon 02-05-11 65
67 Consultants review 3 days Tue 03-05-11 Thu 05-05-11 66
68 Final negotiation 3 days Fri 06-05-11 Sun 08-05-11 67
69 Award contract 2 days Mon 09-05-11 Tue 10-05-11 68
70 Supply 104 days? Tue 17-05-11 Fri 30-09-11
71 Erection & Comissioning 81 days? Mon 19-09-11 Mon 09-01-12
72 SEWAGE TREATMENT PLANT 54 days? Mon 18-04-11 Wed 22-06-11
73 Preparation of tender document 1 day Mon 18-04-11 Mon 18-04-11
74 Float enquiries 1 day Tue 19-04-11 Tue 19-04-11 73
75 Receive quotes 4 days? Thu 23-06-11 Mon 27-06-11 72
76 Consultants review 3 days? Mon 25-04-11 Wed 27-04-11
77 Final negotiation 3 days Thu 28-04-11 Mon 02-05-11 76
78 Award contract 4 days? Tue 03-05-11 Fri 06-05-11 77
79 Supply 30 days? Wed 18-05-11 Fri 24-06-11 103
80 Erection & Comissioning 23 days? Wed 25-05-11 Wed 22-06-11
81 WATER TREATMENT PLANT 202 days? Mon 25-04-11 Fri 20-01-12
82 Preparation of tender document 3 days? Mon 25-04-11 Wed 27-04-11
83 Float enquiries 3 days Thu 28-04-11 Mon 02-05-11 82
84 Receive quotes 7 days? Tue 03-05-11 Mon 09-05-11 83
85 Consultants review 3 days? Tue 10-05-11 Thu 12-05-11 84
86 Final negotiation 3 days? Fri 13-05-11 Tue 17-05-11 85
87 Award contract 3 days? Wed 18-05-11 Fri 20-05-11 86
88 Supply 45 days? Thu 02-06-11 Fri 29-07-11 132
89 Erection 23 days? Mon 01-08-11 Wed 31-08-11 88
90 comissioning 15 days? Tue 10-01-12 Mon 30-01-12 115
91 MOCKUP ROOM INTERIORS 1 day? Mon 18-04-11 Mon 18-04-11
92 Procurement items 5 days? Thu 21-04-11 Mon 25-04-11 74
93 Plumbing 2 days? Thu 21-04-11 Fri 22-04-11
94 Firefighting Sprinkler 1 day Mon 25-04-11 Mon 25-04-11
95 Electrical 7 days? Fri 22-04-11 Thu 28-04-11
96 Windows 1 day Mon 25-04-11 Mon 25-04-11
97 Tile Flooring 3 days Tue 26-04-11 Thu 28-04-11 92
98 POP on walls 2 days Fri 29-04-11 Mon 02-05-11 97
99 False ceiling 1 day Tue 03-05-11 Tue 03-05-11 98
100 Painting 3 days? Wed 04-05-11 Fri 06-05-11 99
101 Wardrobe,luggage rack,bar unit on Vestibule area
5 days? Sat 07-05-11 Wed 11-05-11 100
102 Headboard 2 days Thu 12-05-11 Fri 13-05-11 101
103 Laminated wooden flooring on Bay area 2 days? Mon 16-05-11 Tue 17-05-11 102
104 Cot,side table,working table 2 days Tue 17-05-11 Wed 18-05-11 129

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 2
ID Task Name Duration Start Finish Predecessors 05 Dec '10 12 Dec '10 19 Dec '10 26 Dec '10 02 Jan '11 09 Jan '11
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
105 Tv ledge 2 days Thu 19-05-11 Fri 20-05-11 104
106 Light fixtures 1 day Mon 23-05-11 Mon 23-05-11 105
107 Toilet fixtures,mirror 2 days Mon 23-05-11 Tue 24-05-11 130
108 ROOM INTERIORS 167 days? Wed 15-06-11 Mon 30-01-12
109 Preparation of tender document 4 days? Wed 15-06-11 Mon 20-06-11
110 Float enquiries 6 days? Tue 21-06-11 Mon 27-06-11 109
111 Receive quotes 7 days Tue 28-06-11 Tue 05-07-11 110
112 Consultants review 10 days Wed 06-07-11 Tue 19-07-11 111
113 Final negotiation 2 days Wed 20-07-11 Thu 21-07-11 112
114 Award contract 1 day Fri 22-07-11 Fri 22-07-11 113
115 Supply 97 days? Mon 29-08-11 Mon 09-01-12
116 Erection 97 days? Mon 05-09-11 Mon 16-01-12
117 Rooms comissioning 8 days? Thu 19-01-12 Mon 30-01-12
118 PUBLIC AREAS 1 day? Mon 18-04-11 Mon 18-04-11
119 Finalisation of Concept 5 days? Mon 02-05-11 Fri 06-05-11
120 Preparation of tender document 4 days? Wed 15-06-11 Mon 20-06-11 134
121 Float enquiries 6 days? Tue 21-06-11 Mon 27-06-11 120
122 Receive quotes 7 days? Tue 28-06-11 Tue 05-07-11 121
123 Consultants review 10 days? Wed 06-07-11 Tue 19-07-11 122
124 Final negotiation 2 days? Wed 20-07-11 Thu 21-07-11 123
125 Award contract 1 day Fri 22-07-11 Fri 22-07-11 124
126 Supply 117 days? Mon 29-08-11 Mon 06-02-12
127 Erection 66 days? Mon 21-11-11 Mon 20-02-12
128 KITCHEN EQUIPMENT 1 day? Mon 18-04-11 Mon 18-04-11
129 Finalisation of Concept 6 days? Mon 09-05-11 Mon 16-05-11
130 Preparation of tender document-Imported 4 days? Tue 17-05-11 Fri 20-05-11
131 Indian 3 days? Mon 23-05-11 Wed 25-05-11 87
132 Float enquiries 6 days? Thu 26-05-11 Wed 01-06-11 131
133 Receive quotes 5 days? Thu 02-06-11 Wed 08-06-11
134 Consultants review 5 days? Thu 09-06-11 Tue 14-06-11 133
135 Final negotiation 7 days? Wed 15-06-11 Thu 23-06-11
136 Award contract 1 day Fri 24-06-11 Fri 24-06-11
137 Supply 31 days? Mon 03-10-11 Mon 14-11-11 70
138 Erection 35 days? Mon 14-11-11 Fri 30-12-11
139 Comissioning 7 days? Mon 16-01-12 Tue 24-01-12

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 3
16 Jan '11 23 Jan '11 30 Jan '11 06 Feb '11 13 Feb '11 20 Feb '11 27 Feb '11 06 Mar '11 13 Mar '11 20
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 4
16 Jan '11 23 Jan '11 30 Jan '11 06 Feb '11 13 Feb '11 20 Feb '11 27 Feb '11 06 Mar '11 13 Mar '11 20
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 5
16 Jan '11 23 Jan '11 30 Jan '11 06 Feb '11 13 Feb '11 20 Feb '11 27 Feb '11 06 Mar '11 13 Mar '11 20
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 6
ar '11 27 Mar '11 03 Apr '11 10 Apr '11 17 Apr '11 24 Apr '11 01 May '11 08 May '11 15 May '11 22 May '11
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Arch/Structural

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 7
ar '11 27 Mar '11 03 Apr '11 10 Apr '11 17 Apr '11 24 Apr '11 01 May '11 08 May '11 15 May '11 22 May '11
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 8
ar '11 27 Mar '11 03 Apr '11 10 Apr '11 17 Apr '11 24 Apr '11 01 May '11 08 May '11 15 May '11 22 May '11
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 9
29 May '11 05 Jun '11 12 Jun '11 19 Jun '11 26 Jun '11 03 Jul '11 10 Jul '11 17 Jul '11 24 Jul '11 31 Jul '11
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 10
29 May '11 05 Jun '11 12 Jun '11 19 Jun '11 26 Jun '11 03 Jul '11 10 Jul '11 17 Jul '11 24 Jul '11 31 Jul '11
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 11
29 May '11 05 Jun '11 12 Jun '11 19 Jun '11 26 Jun '11 03 Jul '11 10 Jul '11 17 Jul '11 24 Jul '11 31 Jul '11
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 12
07 Aug '11 14 Aug '11 21 Aug '11 28 Aug '11 04 Sep '11 11 Sep '11 18 Sep '11 25 Sep '11 02 Oct '11 09 Oct '
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 13
07 Aug '11 14 Aug '11 21 Aug '11 28 Aug '11 04 Sep '11 11 Sep '11 18 Sep '11 25 Sep '11 02 Oct '11 09 Oct '
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 14
07 Aug '11 14 Aug '11 21 Aug '11 28 Aug '11 04 Sep '11 11 Sep '11 18 Sep '11 25 Sep '11 02 Oct '11 09 Oct '
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 15
1 16 Oct '11 23 Oct '11 30 Oct '11 06 Nov '11 13 Nov '11 20 Nov '11 27 Nov '11 04 Dec '11 11 Dec '11
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 16
1 16 Oct '11 23 Oct '11 30 Oct '11 06 Nov '11 13 Nov '11 20 Nov '11 27 Nov '11 04 Dec '11 11 Dec '11
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 17
1 16 Oct '11 23 Oct '11 30 Oct '11 06 Nov '11 13 Nov '11 20 Nov '11 27 Nov '11 04 Dec '11 11 Dec '11
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 18
18 Dec '11 25 Dec '11 01 Jan '12 08 Jan '12 15 Jan '12 22 Jan '12 29 Jan '12 05 Feb '12 12 Feb '12 19 Feb '12
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 19
18 Dec '11 25 Dec '11 01 Jan '12 08 Jan '12 15 Jan '12 22 Jan '12 29 Jan '12 05 Feb '12 12 Feb '12 19 Feb '12
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone

Page 20
18 Dec '11 25 Dec '11 01 Jan '12 08 Jan '12 15 Jan '12 22 Jan '12 29 Jan '12 05 Feb '12 12 Feb '12 19 Feb '12
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Project: Work break down structure,JG Task Progress Summary External Tasks Deadline
Date: Tue 03-05-11 Split Milestone Project Summary External Milestone