Vous êtes sur la page 1sur 5

How to Schedule, Track and Control an ERP

Project
Art Herbert III, PMP

“Setting a goal is not the main Once you complete your project scope, developing a
thing. It is deciding how you will project schedule helps you identify the necessary tasks
to reach your goal, assign a logical sequence to those
go about achieving it and staying tasks, monitor their execution, and provide progress
with that plan.” reporting to your project team and key stakeholders1.
—Tom Landry, Football Player and Coach
Developing a project schedule requires time and
How do you implement a multi-million dollar effort, but a well-developed plan positions your
Enterprise Resource Planning (ERP) project on-time implementation for completing activities on time and
and within budget? budget.
1. Set a goal.
2. Plan what you need to do to reach that goal.
How Do You Create a Project Schedule?
3. Work your plan.
A successful project schedule is built on a meaningful
While this answer may seem to be an scope of work that has been identified and approved
oversimplification, those basic steps are the most by the key project sponsors. The project schedule is
critical components for a successful ERP simply the delivery of that project scope in a task-by-
implementation. task outline.

The first decision to make is the method of


1. Develop a project 1. Set a goal. scheduling. Small projects with few tasks can be
scope document. tracked simply as a list of tasks and an estimate of
2. Identify tasks and 2. Plan what you need
how long each task will take to accomplish. ERP
create a project to do to reach that
projects have hundreds of tasks (if not more) and one
schedule. goal.
of the available commercial project management
tools, such as Microsoft Project, should be used.
3. Implement, track 3. Work your plan.
and control your
project schedule.

1 Stakeholders are those people who are affected in any way by


the project, either during the implementation or as a result of the
project implementation.

© 2006 Collegiate Project Services www.collegiateproject.com 1


Additionally, for ERP projects we recommend using We recommend that a group of project stakeholders
the critical path method (CPM) for creating the meet together to brainstorm a list of these major
schedule. The CPM requires that all tasks are linked tasks, risks and dangers, questions to be answered,
via predecessor tasks (those that must be and assumptions to help develop this list. All of these
accomplished before the task can start) and successor items become candidates to be included in the project
tasks (those that follow the completion of the task). schedule, and the involvement of the stakeholders
This linking creates one or more series of tasks that helps to create buy-in in the project schedule.
result in the longest total duration from project start Once the list of tasks is completed, they are placed
to project finish. Tasks in this series are known as into an ordered sequence to create the project
critical path tasks, and if any one is extended, the entire schedule. They can then be entered into project
project timeline is extended. Thus critical path tasks management software. When developing the final list
must receive priority attention, with every effort made of tasks, ensure all the entries are easy to understand
to prevent delays in their completion. by the project stakeholders. The Project Management
Institute, “Draft Practice Standard for Scheduling”
recommends the task descriptions start with a verb
What Do You Include in a Project and contain a unique noun. If a task meaning is not
Schedule?
intuitive or needs further explanation (maybe the user
Everything. Everything, that is, that is needed to has not learned enough about the topic or module),
successfully implement your project. The schedule you can use the notes feature of the software for a
becomes the project road map; therefore, the brief explanation.
following items should be considered for any ERP
project schedule: Each entry into the software is either a task or a
summary task. Summary tasks require no action.
ƒ Tasks – a list of activities that need to be They are updated automatically by updating the tasks
completed including: that roll up to the summary level. The tasks below
ΠFunctional tasks the summary tasks are where the tracking and
ΠTechnical tasks controlling will take place.
ΠAdministrative tasks
ΠTesting tasks Each task must:
Œ Training tasks ƒ Be clearly understood
ƒ Key Project Meetings – the key ƒ Include the duration (length of time required
communications and problem-solving for the task), preferably in days
opportunities including: ƒ Predecessor(s) and successor(s)
Œ Core Project Team Status Meetings ƒ An assigned owner, also known as a resource
ΠTechnical Team Meetings
ΠFunctional Team Meetings Figure 1 shows an excerpt from an ERP project
ΠStakeholder Meetings schedule that includes tasks, summary tasks, task
ƒ Critical Communications – the key durations, task owners and a gantt chart.
opportunities for communications to project
stakeholders including:
ΠRegular status updates
ΠInformation releases
ΠInstitution communication vehicles
ΠInstitutional training sessions

© 2006 Collegiate Project Services www.collegiateproject.com 2


Figure 1

Finally, project schedules need to be flexible. They are ƒ Tasks that are due during the next three
working plans, and rarely does the execution of a weeks
project take place as originally planned. Schedules ƒ All past due tasks
that are inflexible create frustration with the team
members and discourage use of the most critical tool An example of a weekly dashboard report of task
for effective project management. progress on a Student ERP implementation is shown
in Figure 2 on the next page. This is a summary
report that shows progress on task starts and task
How Do You Track a Project? completions for each of the project teams
Project Schedule Update Process (recruitment, admissions, registration, financial aid,
We recommend that you update your project etc.), plus a nineteen week history of task progress.
schedule every week to effectively track and monitor
your project. Establish a specific schedule to get Task Risk Assessment Process
updates from the tasks owners or the project team Tasks that are overdue should be addressed
members. The first update or two of the project immediately by the project manager and the task
schedule will take a little longer to accomplish, and owners to identify and mitigate any risks.
the process will become more routine as the project Stakeholders and the team leadership must
team members become familiar with the update understand they are expected to accomplish their
process. tasks on time or early. They must also understand the
impact of late tasks on the overall schedule.
When the schedule has been updated, the project
team members should receive a copy of the tasks that Regardless of the cause of overdue tasks, the project
are due to be accomplished. This task list should manager and team members must address the impact
include the following summary: of any delays in task completion. Over time, tasks
ƒ Task(s) that are in progress that continue to come in behind schedule add
ƒ New tasks that have been added significant cost to the project. Following are items
that commonly put task completion at risk:

© 2006 Collegiate Project Services www.collegiateproject.com 3


ƒ Task owners that have not bought into the ƒ Poor expectations.
project or do not have the skills to complete ƒ Lack of ownership for the task.
the task. ƒ Illness or foul weather.
ƒ Stakeholders that are hands off and not ƒ Loss of connectivity to instances/document
storage.
proactive.
ƒ Malicious virus or Trojan horse.
ƒ Back order of hardware or equipment. ƒ Poor issue tracking and resolution.
ƒ Resignation or loss of a critical resource.
ƒ Temporary reassignment of project
resources.

Figure 2

© 2006 Collegiate Project Services www.collegiateproject.com 4


How Do You Control A Project? ƒ Follow Up, Follow Up, and Follow Up
Once the project schedule is created and the project ΠRoutinely update the schedule. If a
schedule is being tracked and updated, the most participant is not available during a normally
challenging job of managing an ERP project is scheduled update session, arrangements
controlling the project. The purpose of schedule should be made to get the update earlier so
control is to take measures to eliminate schedule that information can be shared with the rest
delay and ensuring tasks are on time. Controlling the of the project team and stakeholders.
project schedule includes several components: ΠA tried and true management theory still
works -- management by walking around.
ƒ Control Changes Stakeholders, team leaders and the project
manager cannot control a project strictly
ΠControl begins by recognizing that most from their offices. To effectively control a
projects do not go as planned. To prevent project, the project manager and key team
the project from falling behind, you must leaders must get to know the task owners in
define a process for continued control and their environments and gain understanding
monitoring of needs – and begin of the effort involved in the task
implementing the process at the start of the implementation.
project.
Œ Controlling project variances begins with ƒ Develop and Implement a Reporting
keeping your project schedule accurate, Strategy:
detailed, and on task. Continuously refer to ΠDevelop a reporting strategy beyond the
the statement of work or scope document updating of the project schedule.
help eliminate scope creep (uncontrolled ΠStatus reports should include topics such as
changes in a project). issue identification, issue resolution,
ΠUse a predetermined process of change decisions, or upcoming events.
control and approval to add to or redefine ΠStatus reports should routinely be
the scope of the project. distributed to stakeholders, team leaders and
team members and other resource
ƒ Observe Performance
management. We recommend weekly
ΠOnce a control process is in place, the written status reports.
project manager and stakeholders must then ΠConsider additional updates various interest
balance between being too aggressively groups such as Steering Teams, Boards of
involved or too hands off. Task owners Trustees, Faculty Senates, or Department
need a reasonable amount of time to Heads. These updates should be customized
complete their tasks. They appreciate to the audience.
follow-up but not constant observation.
ΠDuring the control phase the project How do you implement a multi-million dollar
manager must be fully and actively engaged. Enterprise Resource Planning project on-time and
Human behavior plays a very large role in within budget? You set a clear goal through your
controlling the project schedule as it relate scope development. You plan the tasks that you need
to timely task completion. The project to accomplish to reach that goal and build a project
manager must have a keen awareness of schedule. And you implement, track, and control your
what is happening (or not happening) with project schedule.
the project and must be alert to possible
risks.
If you found this article helpful and would like to read more, please go to our
website at www.collegiateproject.com and browse our ERP Library.

© 2006 Collegiate Project Services www.collegiateproject.com 5

Vous aimerez peut-être aussi