Académique Documents
Professionnel Documents
Culture Documents
Project
Owner
Client
Consultant
LOI No. & Date
Doc. No. ACE-TK-JP-08 Rev. 0 Sheet 1 of 7
1. Scope
This Procedure describes the technique and requirement for radiography
examination of butt Welds.
2. Qualification of Personnel
Personnel performing radiography examination will be level 1.
Personnel responsible for supervision safety and interpretation of radiography will be
level – II or equivalently qualified BARC certified radiographic Site in charge.
3. Material
Material group is Group – I as classified by ASTM E142 or ASME SE 142 article – 22
(i.e. A carbon steel, low alloy steel, manganese, nickel, aluminum, bronze).
4. Thickness Range
Useful range of thickness in steel is 3mm to 60 mm.
5. Equipment
Radiography equipment will be remote operated type B tested IR.192 Isotope
camera.
6. Nature of Source
Gamma radiation from IR.192 Isotope with an average energy level of 0.4 MeV will
be used for radiography examination.
7. Techniques for
7.1 Plates - Single wall single image technique will be used. The minimum
source to film distance will be the thickness of weld meal.
Anwesha Comtech Engg. Pvt. Ltd.
Project
Owner
Client
Consultant
LOI No. & Date
Doc. No. ACE-TK-JP-08 Rev. 0 Sheet 2 of 7
7.2 Pipes / Tubes:-
7.2.1 Diameter range 1/2:” to 3.5”- Double wall double image technique will be used.
This technique is adopted for smaller size pipes of diameter upto 80mm. The source
is kept at one angle with respect to the weld, so as to avoid overlap of the top and
bottom weld. Generally, 10° - 20° offset angle is given for the exposure. Two
exposures are taken by rotating the pipe through 90°.
7.2.2 Diameter range 3.5” to 5”- Double wall single image technique will be used. This is
mostly suitable for the pipes of diameter above 80 mm. Sources can be kept on the
pipe or away from the pipe, depending on the diameter of the pipe, SFD required and
accessibility.
7.2.3 Diameter range 6” to Onwards- Single wall single image or double wall single
image technique shall be used depending upon the accessibility for positioning the
source. In this technique, several methods of exposure are possible. The ideal
position to locate the source would be the centre of the pipe or cylinder ( Panaromic
exposure). However, if the centre is not accessible or if pipe diameter is small the
source can be off the centre. The welds can be divided into several segments and
the exposures are carried out.
Project
Owner
Client
Consultant
LOI No. & Date
Doc. No. ACE-TK-JP-08 Rev. 0 Sheet 3 of 7
10. Screens
Lead screens will be used for intensification. Normal lead screen thickness will be
0.005” on front and back.
Date.
Joint No.
Welder No.
XR No.
Isometric/ Spool Number/ Dra. No.
Film segment marking.
To identify repair welds, the letter R1 will be used to identify first repair and R2 for
second repair. This identification shall be of a permanent nature by leat latter (6mm
height and 1.5 mm thick)
For re-shoot RS will be put in the film. For retake RT will be put to identify.
Radiography offering:- Once weld, visual and heat treatment (if applicable)
completed, the joint will be selected for radiography, jointly with inspectors. The
selected joints will be identified by their welder No. Spool/ Pass/ Line No. &
Radiography No (X No.). The tag or marking will be provided to the selected joints for
easy identification.
Anwesha Comtech Engg. Pvt. Ltd.
Project
Owner
Client
Consultant
LOI No. & Date
Doc. No. ACE-TK-JP-08 Rev. 0 Sheet 4 of 7
13. Film Density
The transmitted film density thought the area of interest will be 2 to 3± 0.05. A
densitometer of densitostrip will be used to measure the density.
For single wall image technique, the placement of penetrameter will be on source
side.
The wire type penetrameter will be placed 90” to the weld with the thinnest wire away
from central beam of radiation and within one inch distance from either of the end
markers.
Project
Owner
Client
Consultant
LOI No. & Date
Doc. No. ACE-TK-JP-08 Rev. 0 Sheet 5 of 7
If the total repaired weld length and the additional weld length to be covered exceeds
the total maximum coverage as mentioned earlier additional exposure will be taken.
This will be carried out prior to production radiography and at selected problem areas
thereafter. A image of the ‘B’ on a lighter background is not a cause for rejection.
Project
Owner
Client
Consultant
LOI No. & Date
Doc. No. ACE-TK-JP-08 Rev. 0 Sheet 6 of 7
Apart from the information given on radiography, the evaluation result also will be
written on the wrapper. The evaluation result includes, type of defect and acceptance
/ rejection status. Wrapper should also show density, thickness, sensitivity & IQI.
21. Processing
Processing will be manual
Developing time will be 4-8 minutes in temperature range of 18°C to 22°C. Film will
be agitated for two seconds each minute during development. This will help develop
evenly.
Film will be fixed for at least twice the clearing time with agitation for the first 10
seconds and a gain at the end of the first minute.
Washing will be for at least 10 minutes in running water.
Film will be dipped in wetting agent for 1 minute.
Film will be drained, then hung and dried.
Project
Owner
Client
Consultant
LOI No. & Date
Doc. No. ACE-TK-JP-08 Rev. 0 Sheet 7 of 7
(a) Fogging
(b) Processing defects such as water or chemical marks.
(c) Scratches, finger marks, crimps, static smudges or tears.
(d) Loss of details due to poor screen to film contact.
(e) False indication due to defective screen.
25. Reporting
Radiographic report containing required details will be submitted immediately after
completion of evaluation of radiographs.
26. Safety
Personnel performing radiography shall wear a TLD whenever in a radiation area
and survey meter will be used to measure the radiation level.
The area where radiography is being performed will be cordoned off to prevent
unauthorized entry.
The radiation level at the cordoned off distance will be such that the non radiation
workers will not receive a dose not more than 2 MR per week.
27. Documentation
Proper record shall be maintained as per format No. ACE/QA/TK/FM-10, 11 & 12
Rev.0