Abstract: The project in the paper included design and construction of a permanent 120m long RC box culvert and
sewer diversion at North Buona Vista Road (NBV) Singapore. The pipe roof method was selected by the design
and build contractor in fulfilment of the contract requirement for the 53 m box section undercrossing NBV Road. The
adopted methodology comprised the installation by pipe jacking of numbers of interlocking steel pipes followed by
traverse series of steel frames for safe mining of the tunnel. This served to maintain uninterrupted service conditions for the
road, subways tunnel and other services. There are many challenges in the construction of pipe roof and mined tunnel. This
paper deals with the consideration in the design and construction of such works. It also highlighted the
problems encountered during the construction, subsequent solution adopted and protection of existing utilities as well as
monitoring of settlement of the surrounding areas of the project.
4. CONSTRUCTION
The West End line viaduct and the MRT (CCL 4& 5 )
Tunnel, which was laid some 4.4 m below the propsed
outlet drain were checked for the effect of the excaation
of the shafts, mined tunnel and found to have maximum
settlement of 6 mm, much less than the allwoable 15mm
according to LTA Civil Design Criteria ( LTA 2009 c) Fig 7a MRT tunnel underneath of mined tunnel
and LTA Code of practice for RailWay Protecvtion.
(LTA.2009 d). Fig Fig 7b,and 7 c shows the cross sections of the major
services( MRT /Sewer lines and MRT viaduct ) .
Fig 8 shows the general summary of utilities The mandatory requirements for the maintenance of
encountered and the protection measures adopted. uninterrupted service for the services offered many
challenges to the project. At rare occasions when
settlements occasionally exceeded the suspension levels,
the pipe jacking and tunnel mining works were stopped
to enable lifting of the services to adjust the base
condition to normal to avoid damages to the utilities.
This is done in compliance of the approved( by the
authorities) stringent method. The laborious monitoring
process, with daily /weekly instrumentation meeting in
the presence of LTA, PUB and other agencies helped to
ensure that all such measures were carefully evaluated
Fig 8 . Utilities and protection measures adopted and solutions decided upon expeditiously and promptly
carried out to prevent any further excessive settlements.
The services and utilities and their allowable settlements The requirements of Power Grid were particularly
at the influence zones of the mined tunnel are indicted in strenuous on the joint cable bay at the centre of box
Table 2. culvert along North Buona Vista Road, and cumulated
in the complex web of instrumentations installed (refer to
Table 2. Existing utilities within the area of mined tunnel
Fig 9 ).
Utilities Protection Allowable Allowable
measures different absolute
settlement settlement
The West NA(Within
allowable limit) 15 or
End line
1:1000 *
viaduct
CCL 4& NA (Within 15 or
5 Tunnel allowable limit 1:1000*
150 dia (Abandoned)
water
pipe
300 dia Re-propping NA
water 1:240
pipe
SingTel/ Re-propping
Star Hub 1:100 Fig 9 . Layout of Joint Bay & Instrumentations
cables
1650 dia Within
sewer allowable limit
(estimated less 1:300
than 1: 300)
4.2.2 Pipe Jacking 4.2.3 Settlement Control and Monitoring
REFERENCES:
Atalah, A.L. and D.T. Iseley, 1991. "Pipe Arch
Horizontal Drift Method for MARTA's Transit Extension
Under I-285," Proceedings of Rapid Excavation and
Tunneling Conference, SME, Chapter 24, June, pp. 435-
453.