Académique Documents
Professionnel Documents
Culture Documents
Limitations Advantages
• Pre-selected pile • No external reaction system
• Maximum load limited by weaker • No anchor piles
of end bearing or skin friction • Little or no heavy transport
• Test results need interpretation requirements
• Only half the stresses applied
• Top of the pile is not structurally
to the concrete
tested
• Significant cost savings as
• Top load movement curve must loads increase
be calculated
(NH) 1
4
(MA) 26
2 3
6 (RI) 4
19
4 3
(CT) 7
33 10 19
4 7 (NJ) 31
13
10 1 24 (MD) 8
53 13 15 12
(DC) 7
2 12
2 11 2 23
(HI) 34 75 15 17
10 15
89 (PR) 29
2 Lateral
Total USA Tests: 677
Key
0
1-10
11-20
21-30
>30
Upcoming/In
progress
Issues Faced:
Adapting to the
Augercast
Installation
method – or
making
hockey sticks!
Allowed
cage to flex
assuring
verticality
(no hockey
sticks)
Welding
time
infringing on
installation
process
Required
a pilot hole
for stinger
Additional Modifications
• Plumbers union for TT pipe
• Taping pipe joints
• Sealing of hose joints with
plumbers putty
Applications
• 18-inch-diameter, 80-ft long piles
• 9-inch diameter O-cell (800 kip cap.)
• 24-inch-diameter, 100-ft long piles
• 16-inch diameter O-cell (2800 kip cap.)
• 30-inch-diameter, 120-ft long piles
• 21-inch diameter O-cell (4800 kip cap.)
• 36-inch-diameter, 120-ft long piles
• Multi-level assemblies
• Two 21-inch diameter O-cell
• 26-inch? (7200 kip cap.)