Set 1 (Diagram1)

The duration of the project is (Refer above Diagram 1):


A. 20 days
B. 26 days
C. 35 days ---right one
D. 37 days

The float of Activity C is (Refer above Diagram 1):


A. 6 days
B. 9 days
C. 12 days --- right one
D. 24 days

The total float of path that has activity C is (Refer above Diagram 1):
A. 6 days
B. 9 days
C. 12 days
D. 24 days

If management imposes an end time of 22 days the project float is (Refer above Diagram
1):
A. 0 days
B. 4 days
C. -4 days
D. -13 days -- right one
Set 2 (Table 2)

Activity Predecessor Duration


A Start 3
B Start 7
C A 4
D A, B 6
E C, D 5
F B,D,E 2
G C, E 8
H F,G 9

What is the duration of the critical path? (Refer Table 2)


A. 20 days
B. 26 days
C. 35 days ---right one
D. 42 days

What is the float of Task A? ( Refer Table 2)


A. 0 days
B. 3 days
C. 4 days
D. 7 days

What is the total float of the path that has Task A? Refer Table 2)
A. 0 days
B. 3 days
C. 4 days
D. 7 days

Management has imposed an end day of time 33.What is the project float? (Refer Table 2)
A. 0 days
B. -2 days – right one
C. 7 days
D. 9 days

Assuming managements imposed end day of time 33, what is the float of Task F? (Refer Table 2)
A. 0 days --- right one
B. -2days
C. 4 days
D. 6 days
Set 3 (Table 3)

Activity Predecessor Duration


A Start 3
B Start 7
C A (start to start) 4
D A, B 1
E C, D 6
F D 5
G E, F 2
Finish G

What is the project duration? (Refer Table 3)


A. 15 days
B. 16 days --- right one
C. 17 days
D. 18 days

What activities are on the critical path? (Refer Table 3)


A. b-d-f-g
B. d-e-g
C. a-c-e-g
D. b-d-e-g ---right one

What is the float of Activity d? (Refer Table 3)


A. -1days
B. 0 days -- right one
C. I days
D. 3 days

What is the Total float of the path that has Activity d?( Refer Table 3)
A. -1 days
B. 0days right one
C. 1day
D. 3days

If management imposed an end date of 18 days, what is the project float?(Refer Table 3)
A. -2 days -- right one
B. -l day
C. I day
D. 2 days
Set 4 (Table 4)

Activity Predecessor Duration


A Start 5
B Start 3
C A+2days lag , B 7
D B 8
E C, D 6
Finish E
What is the duration of the critical path? (Refer Table 4)
A. 17 days -- right one
B. 18 days
C. 20 days
D. 24 days

What is the float of Activity B? (Refer Table 4)


A. 0 days -right one
B. 3 days
C. 4 days
D. 6 days

What is the total float of the path that has Activity B? (Refer Table 4)
A. 0 days --right one
B. 3 days
C. 4 days
D. 6 days

What activities are on the critical path? (Refer Table 4)


A. c-e
B. a-c-e
C. b-c-e
D. b-d-e --right one

If management imposes and end date of 18 days or less, what is the float of Activity E?( Refer
Table 4)
A. -4
B. -2
C. 0 – right one
D. 7
Set 5 (Diagram 5)

The project duration is:(Refer above diagram 5)


A. 16 days
B. 17 days
C. 19 days
D. 21 days

What activities are on the critical path?( Refer above diagram 5)


A. c-d-f
B. a-b-d-f
C. d-e-f
D. c-e-f

If it takes the engineers 6 days and not 8 to complete Activity E, what is the project duration?( Refer above
diagram 5)
A. 16 days
B. 17 days
C. 19 days
D. 21 days

If the duration of Activity E is set back to 8 days, and management imposes an end time of 13 days, what is
the new project float?( Refer above diagram 5)
A. 2 days
B. 0 days
C. -2 days
D. -6 days