The total float of path that has activity C is (Refer above Diagram 1):
A. 6 days
B. 9 days
C. 12 days
D. 24 days
If management imposes an end time of 22 days the project float is (Refer above Diagram
1):
A. 0 days
B. 4 days
C. -4 days
D. -13 days -- right one
Set 2 (Table 2)
What is the total float of the path that has Task A? Refer Table 2)
A. 0 days
B. 3 days
C. 4 days
D. 7 days
Management has imposed an end day of time 33.What is the project float? (Refer Table 2)
A. 0 days
B. -2 days – right one
C. 7 days
D. 9 days
Assuming managements imposed end day of time 33, what is the float of Task F? (Refer Table 2)
A. 0 days --- right one
B. -2days
C. 4 days
D. 6 days
Set 3 (Table 3)
What is the Total float of the path that has Activity d?( Refer Table 3)
A. -1 days
B. 0days right one
C. 1day
D. 3days
If management imposed an end date of 18 days, what is the project float?(Refer Table 3)
A. -2 days -- right one
B. -l day
C. I day
D. 2 days
Set 4 (Table 4)
What is the total float of the path that has Activity B? (Refer Table 4)
A. 0 days --right one
B. 3 days
C. 4 days
D. 6 days
If management imposes and end date of 18 days or less, what is the float of Activity E?( Refer
Table 4)
A. -4
B. -2
C. 0 – right one
D. 7
Set 5 (Diagram 5)
If it takes the engineers 6 days and not 8 to complete Activity E, what is the project duration?( Refer above
diagram 5)
A. 16 days
B. 17 days
C. 19 days
D. 21 days
If the duration of Activity E is set back to 8 days, and management imposes an end time of 13 days, what is
the new project float?( Refer above diagram 5)
A. 2 days
B. 0 days
C. -2 days
D. -6 days