PRESENTATION ON

Grid Reliability Requirements, Stability and Protection


Presented by : Mr. M.Majumdar Executive Director ( Commercial) WBSEDCL 10th April, 2008

Profile and Energy Scenario of West Bengal :


West Bengal is located in the eastern region of India with an area of 87853 sq. km and 19 districts. West Bengal shares an international border with Nepal, Bhutan and Bangladesh and is surrounded by Indian States namely, Sikkim, Assam, Orissa, Jharkhand and Bihar. Main languages spoken in West Bengal are Bengali, Hindi and English. West Bengal is having a total population 80.22 million (2001 Census) with density of population of 904 per Sq.km.

WBSEDCL

Some BasicEnergy Scenario of West Bengal : Profile and Features :


West Bengal is located in the No of Population 80.22 million eastern region of India with an area of 87853 sq. km and 19 Urban West Bengal 28.03 % districts. Population shares an international border with Total no of Mouzas 37910 Nepal, Bhutan and Bangladesh No of surrounded by Indian 34184 and is Mouzas Electrified States namely, Sikkim, Assam, Orissa, Jharkhand and Bihar. Some languagesFeatures about Electricity In West Bengal Main Special spoken in (West Bengal are31, 2008) as on March Bengali, Hindi and English. West Bengal is having a total population 80.22 : Peak Load 4900 MW million (2001 Census) with Off-Peak Load 3350 MW density of population of 904 per : Sq.km. Sundarban Mangrove Forest is not connected by Grid Power
WBSDA WBSEDCL

Area

87853 SQ KM

List of Renewable &Scenario of West Bengal : power to Profile and Energy Co-generation plants selling WBSEDCL :
West Bengal is located in the eastern region of India with an area of 87853of the km and 19 Sl. Name sq. Location No. districts. Entrepreneur West Bengal shares an international border with Haldia, Nepal, Bhutan and Bangladesh Dist 1. M/s Electro Steel Purbo Medinipur and is surrounded by Indian States namely, Sikkim, Assam, Dist M/s Neora Hydro Neora, 2. Ltd. Darjeeling Orissa, Jharkhand and Bihar. Main languages spoken in M/s. Nippon Lodhama, Dist: 3. West Bengal are Bengali, Hindi Power Limited Darjeeling and English. West Bengal is having a total population Mohan Dairy, 80.22 4. WBREDA million (2001 Census) Dist: Purulia with density of population of 904 per Sq.km.

Type of project Coke Oven plant Hydel Hydel Bio-gas Plant

Capacity (MW) 12.0 3.0 3.0 0.03

WBSDA WBSEDCL

List of Renewable & Scenario of West Bengalexecuted PPA Profile and Energy Co-generation plants who : with WBSEDCL for sale of power:
West Bengal is located in the eastern region of India with an area ofName of the km and 19 87853 sq. Sl. Location districts. West Bengal shares No. Entrepreneur an international border with M/s. Kamarhatti Raina, Nepal, Bhutan and Bangladesh 1. Co. Ltd. and is surrounded by Dist: Burdwan Indian StatesM/s. Amrit Bionamely, Sikkim, Assam, Dist: Bankati, 2 Energy & Orissa, Jharkhand and Bihar. Bankura Industries Ltd. Main M/s. PCM Hydel spoken in languages West Bengal are Bengali,Chel-I, Dist Hindi 3. Power Darjeeling and English. West Bengal is Corporation Ltd. having a total population Chel-II, Dist 80.22 M/s. Shyam 4. millionEnergy Limited (2001 Census) Darjeeling with density M/s. Eastern of 904 per of population Chel-III, Dist Sq.km. Hydro Power 5.
Company Limited Darjeeling

Type of project Bio-mass Bio-mass

Capacity (MW) 6.0 10.0

Hydel Hydel Hydel

6.0 6.0 4.2

WBSDA WBSEDCL

Some salient features of State Electricity Grid Code(SEGC):


Frequency variation : Rated frequency of the system 50 HZ. and shall normally be controlled within the bandwidth of 49 to 50.5 HZ Voltage Variation : Shall not be more than Voltage range specified in IE Rules. Sub-Station Equipment :All equipment shall be designed, manufactured, tested as per IEC / BIS standard. Each Connection between an agency and STS shall be controlled by a circuit breaker capable of interrupting at the connection point.
WBSEDCL

Protection :
Protection systems are to be provided by all entities as specified by STU. Requires to isolate the faulty equipment and protect the other equipments against all types of faults internal / external within specified fault clearance time with reliability, selectivity and sensitivity. Relay Setting Coordination shall be done by STU STU shall arrange periodic meeting with the entities to discuss coordination of protection.

WBSEDCL

Requirements of Generating Unit:


A generating unit shall be capable of continuously supply its normal rated active / reactive out put with specified system frequency and voltage variation. Generating Unit shall be provided with an AVR, Protective and safety devices. All Generating Units and associated Electrical Equipment connected to State Grid shall be provided with adequate protection so that State Grid does not suffer due to any disturbances. Each Generating Unit shall be fitted with a Turbine Speed Governor having an over all droop characteristic within the range of 3-6 % . Each Generating Unit shall be capable of instantaneously increasing out put by 5% limited to 105% MCR when frequency falls.
WBSEDCL

Transmission Line Requirements :


Every EHT line taking off from generating station or a substation shall have distance protection and back up protection. For 132 KV lines three-zone non-switched distance protection with suitable back-up protections to be used.

WBSEDCL

Distribution line requirements: All 33 KV and 11 KV lines at connection point shall be provided with minimum of over current and earth fall protection with or without directional features as. Transformer requirements : For transformers of HV class differential protection shall be provided for 10 KVA and above. For transformers of 2.5 MVA to less than 10 MVA time lag over current, earth fault and instantaneous REF relays. All transformers of 2.5 MVA and above shall be provided with gas operated relays, winding temperature and oil temperature protection.
WBSEDCL

Communication:
Communication system between grid sub-station and generating station shall be developed by the developer at their cost Developers of co generation and renewable energy sources shall abide by all applicable codes, rules & regulations in regard to operational and commercial practices

WBSEDCL

Metering :
Ownership and responsibility of maintaining and testing of meter shall be mutually agreed between the entities and the STU. Minimum standard of accuracy of meter shall be of class 0.2 or as specified by STU. All CTs and PTs used for metering shall confirm to the BIS or standard of IEC.

WBSEDCL

Procedure for connection to STS:


Any agency seeking connection to STS shall submit application on specified forms to STU along with the following details: A report stating the purpose of connection, connection point ,apparatus to be connected and beneficiaries of connection. Prospective users shall, require to pay STU all charges as specified by WBERC for conducting initial and any additional studies for processing the application. Construction schedule and target completion date. A confirmation to abide by the provisions of WBEGC, I.E rules and provisions of the regulation made by the CEA under the Act. The connection point shall be at licensees gantry in case of CPP
WBSEDCL

Connection Agreement:
A connection agreement shall include (but may not be limited to), as appropriate, within its terms and conditions, the following: A condition requiring both parties to comply with WBEGC and Grid Code; The details of connection, technical requirements and commercial arrangements; The details of any capital expenditure arising from necessary reinforcement or extension of the system and demarcation of the same between the concerned parties;

WBSEDCL

Connection Agreement: contd..


A Site Responsibility Schedule; The metering arrangements; The general procedure, guidelines, etc. on protection and telemetry; The procedures necessary for site access, site operational activities and maintenance standard for equipment of Licensee at the premises of the User and vice-versa;

WBSEDCL

Connectivity for Co-generation & Renewable sources as per WBERC regulation:


The Cogeneration and renewable energy sources excepting roof-top Solar PV and Bio gas sources shall be connected to state grid at a voltage of 33 KV or 11 KV subject to technical suitability Delivery point shall be the nearest grid sub station of 33/11 KV voltage level Roof top solar PV system shall be connected at LV or MV or 11 KV Bio gas plant shall be connected at MV or at 11 KV
WBSEDCL

Procedure to be followed for Co-generation & Renewable Energy Sources: After preliminary discussions with the buyer licensee, the developer shall submit full details of the projects alongwith cost data and financial charges and tariff for direct sale to the licensee. The buyer licensee shall examine the tariff proposal in the light of price reasonableness, impact on consumer tariff and the price cap specified in these regulations.

WBSEDCL

Procedure to be followed for Co-generation & Renewable Energy Sources: MOU / PPA shall be signed between developer and purchaser. In case of open access, the transmission and/orwheeling agency shall also be a party to the MOU / PPA. In the MOU / PPA with details of connectivity, completion of project and commencement of supply, periods of supply (month wise), time of supply (peak / off peak), technical & commercial obligation, security and modes of payment of each party, etc. in line with these regulations shall be suitably incorporated. The MOU / PPA, as agreed and signed, shall be submitted to the Commission.
WBSEDCL