Académique Documents
Professionnel Documents
Culture Documents
Description
Unit
Unit = sqm Taking output = 3500 sqm a) Labour day day hour hour hour tonne Machinery Mate Mazdoor b) Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm Emulsion pressure distributor @ 1750 sqm per hour c) d) e) Material Overhead charges @ 10 % on (a+b+c) Contractor's profit @ 10 % on (a+b+c+d) Bitumen emulsion @ 0.20 kg per sqm
Cost for 3500 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/3500 Add 1% labour cess
5.3
504
Bituminous Macadam Providing and laying bituminous macadam with 100120 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder, transported to site, laid over a previously prepared su Unit = cum Taking output = 205 cum (450 tonnes) a) Labour day day day Mate Mazdoor working with HMP, mechanical broom, paver, roller, asphalt cutter and assistance for setting out lines, levels and layout of construction Skilled mazdoor for checking line & levels b) Machinery hour hour hour hour hour hour tonne.km Batch mix HMP 100-120 TPH @ 75 tonne per hour actual output Mechanical broom hydraulic @ 1250 sqm per hour Air compressor 250 cfm Paver finisher hydrostatic with sensor control @ 75 cum per hour Generator 250 KVA Front end loader 1 cum bucket capacity Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading and unloading Smooth wheeled roller 8-10 tonnes for initial break down rolling. Vibratory roller 8 tonnes for intermediate rolling. Finish rolling with 6-8 tonnes smooth wheeled tandem roller. c) Material i) Bitumen@ 3.3 per cent of mix weight of mix = 205 x 2.2 = 450 tonne ii) Aggregate Total weight of mix = 450 tonnes Weight of bitumen = 14.85 tonnes Weight of aggregate = 450 -14.85 = 435.15 tonnes Taking density of aggregate = 1.5 ton/cum Volume of aggregate = 290.1 cum *Grading I ( 40 mm nominal size ) 37.5 - 25 mm 15 per cent 25 - 10 mm 45 per cent 10 - 5 mm 25 per cent 5 mm and below15 per cent (i) for Grading I ( 40 mm nominal size ) d) e) Overhead charges @ 10 % on (a+b+c) Contractor's profit @ 10 % on (a+b+c+d)
tonne
Cost for 205 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/205 (For Grading I) Add 1% labour cess
5.8
509
Bituminous Concrete Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509 complete in all respects Unit = cum Taking output = 191 cum (450 tonnes) a) Labour Mate Mazdoor working with HMP, mechanical broom, paver, roller, asphalt cutter and assistance for setting out lines, levels and layout of construction Skilled mazdoor for checking line & b) levels Machinery
day day
day
Batch mix HMP @ 75 tonne per hour Paver finisher hydrostatic with sensor control @ 75 cum per hour Generator 250 KVA Front end loader 1 cum bucket capacity tonne capacity Tipper 10 Add 10 per cent of cost of carriage to cover cost of loading and unloading Smooth wheeled roller 8-10 tonnes for initial break down rolling. Vibratory roller 8 tonnes for intermediate with 6-8 tonnes Finish rolling rolling. smooth wheeled tandem roller. c) Material i) Bitumen@ 5 per cent of weight of ii) Aggregate mix Total weight of mix = 450 tonnes Weight of bitumen = 22.5 tonnes Weight of aggregate = 450 -22.50 = 427.50 tonnes Taking density of aggregate = 1.5 ton/cum aggregate = 285 cum Volume of * Grading - I-19 mm (Nominal Size) 20 - 10 mm 35 per cent 10 - 5 mm 23 per cent 5 mm and below 40 per cent Filler @ 2 per cent of weight of aggregates. or Grading - II-13 mm (Nominal Size) 13.2 - 10 mm30 per cent 10 - 5 mm 25 per cent 5 mm and below43 per cent Filler @ 2 per cent of weight of aggregates. *Any one of the alternative may be adopted as per approved design for Grading-I ( 13 mm nominal size ) Err:509 Err:509 Cost for 205 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/191 5.8 (ii) for Grading-II(10 mm nominal size) Err:509 Err:509 Cost for 205 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/191 (For Grading-II)
tonne
(i)
(BITUMINOUS) SOR-2008-09, R & B, A'bd Dist. Remarks/ Input ref. 5% rate increase per year. Total 10% 2010-11
Quantity
Rate Rs
Cost Rs
8.75 218.80 644.00 576.80 1384.00 19331.76 11882.29 13070.52 47116.92 13.46 0.13 13.60
say
14.96 15
P&M-021 P&M-031 P&M-001 P&M-034 P&M-081 P&M-017 Lead =15 km & P&M-058
1080.00 6.00x0.65* 6.00x0.65* 6.00x0.65* 297.00 994.00 738.00 1158.30 3876.60 2878.20 P&M-044 P&M-059 P&M-045
14.850
26144.40
388244.34
M-074
say
4548.00 say
5002.8 5003
0.840 16.000
190.40 109.40
159.94 1750.40
L-12 L-13
5.000
109.40
547.00
L-15
72360.00 7200.00
P&M-022 P&M-034
3900.00 P&M-081 3120.00 P&M-017 Err:509 Lead =3 km & P&M-058 Err:509 1251.90 4188.60 3108.30 P&M-044 P&M-059 P&M-045
22.500
22089.63 497016.68
M-074
0
Err:509 Err:509 Err:509 Err:509 say Err:509 Err:509 Err:509 Err:509 Err:509 say Err:509
5883.22 5883
4937.17 4937
Suggested Levels of Reliability For Various Functional Classifications Recommended Level of Reliability
Functional Classifications
Urban 85 - 99.9 80 - 99 80 - 95 50 - 80
Rural 80 - 99.9 75 - 95 75 - 95 50 - 80
98.00 98.00 108.00 12060.00 1863.00 900.00 562.00 2.00 321.00 1074.00 797.00 #REF!
33521.06 #REF!
say
say
Recommended Values of Drainage Coefficient, Cd Pavement Design Quality of Drainage Excellent Good Fair Poor Very Poor Percent of Time Pavement Structure is Exposed to Moisture Levels Approaching Saturation Less Than 1 % 1.25 - 1.20 1.20 - 1.15 1.15 - 1.10 1.10 - 1.00 1.00 - 0.90 1-5% 1.20 - 1.15 1.15 - 1.10 1.10 - 1.00 1.00 - 0.90 0.90 - 0.80 5 - 25 % 1.15 - 1.10 1.10 - 1.00 1.00 - 0.90 0.90 - 0.80 0.80 - 0.70 Greater Than 25 % 1.1 1 0.9 0.8 0.7
Sr. no
Unit
Quantity
day day day hour hour hour hour hour hour tonne.km
2.000 15.000 35.000 2.800 18.000 6.000 6.000 6.000 36.000 ### 0.100
sqm 3675.000 sqm 16.330 kg 875.000 sqm 46.670 liter 1850.000 kg 2070.000
Add 1 per cent of material for cost of miscellaneous materials like tarpauline, Hessian cloth, metal cap, cotton / compressible sponge and cradle for dowel bars, work bridges for men to approach concrete surface without walking over it, cutting blades and bites, minor equipments like scabbling machine, threads, ropes, guide wires and any other unforeseen items. d) overhead charges 8% of (a+b+c) e) contracter profit 10% of (a+b+c+d) Cost for 1050cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/1050
KL
216.000
Rate Rs Cost Rs
Remarks/ Input 5% rate increase per year. ref. Total 10% 2010-11
109.1 109.1 109.1 260 520 1440 650 1850 300 1.6 38640 250 200
P&M-081 P&M-006 P&M-060 Lead =60 km & 38640 P&M-058 3864 3000 2400 P&M-083 P&M-088
707.44 668530.8 228.64 ### 4400 1821600 34000 65 50 50 250 39780 238875 816.5 43750 11667.5
M-052 and M054 M-004 M-081 M-082 M-164 M-141 M-120 M-138 M-090 M-180
M-189
5691.52 5692