VAT (+) TRIPODE VAD (-) COTA

1 37.985 36.5 PENDIENTE=


2 1.463 36.522
3 1.495 38.017 36.528
4 1.478 36.539
5 1.516 38.055 36.545
6 1.508 36.547
7 1.497 38.044 36.519
8 1.385 36.659
9 2.297 38.956 37.446
0.62 38.336

0 10 20 30 40 50
PENDIENTE 2.04 0.204
COTA TERRENO 36.5 36.522 36.528 36.539 36.545 36.547
COTA ROJA 36.5 36.704 36.908 37.112 37.316 37.52
CORTE
RELLENO 0 -0.182 -0.38 -0.573 -0.771 -0.973

0,36.5
10,36.522
20,36.528
30,36.539
40,36.545
50,36.547
60,36.519
70,36.659
80,37.446
90,38.336
2.04 %

60 70 80 90

36.519 36.659 37.446 38.336


37.724 37.928 38.132 38.336

-1.205 -1.269 -0.686 0


CALCULOS MOVIMIENTO TIERRAS AREA(m2)
TRAMO DIST.HORIZ DIST.ACUM CORTE RELLENO SEMIDISTACIA
1 0 0 10 5 0
1-2 10 10 4 8 5
2-3 10 20 2 7 5
3-4 10 30 3 8 5
4-5 10 40 9 4 5
5-6 10 50 7 6 5
6-7 10 60 8 4 5
7-8 10 70 5 3 5
8-9 10 80 4 4 5
9-10 10 90 5 6 5
A1+A2 VOLUMENES
CORTE RELLENO CORTE RELLENO F.E. CORTE RELLENO

14 13 70 65 1.5 105 65
6 15 30 75 1.5 45 75
5 15 25 75 1.5 37.5 75
12 12 60 60 1.5 90 60
16 10 80 50 1.5 120 50
15 10 75 50 1.5 112.5 50
13 7 65 35 1.5 97.5 35
9 7 45 35 1.5 67.5 35
9 10 45 50 1.5 67.5 50
742.5 495

MATERIAL EXCEDENTE= 247.5 M3


EL FACTOR SE LE MULTIPLICA AL CORTE