Specifications.........................................................................................................2 Maintenance Order Process....................................................................................4 Phase 1: Order creation.......................................................................................4 Phase 2: WC Application creation........................................................................5 Phase 3: WC Document creation.........................................................................5 Phase 4: Links creation.......................................................................................8 Phase 5: Prepare WCD objects for use................................................................8 Phase 6: Allow Maintenance order processing....................................................9 Customizing..........................................................................................................10 Standard/Maintain Approvals............................................................................10 Enhancements/Assign Approval........................................................................11 Enhancements/Define Hierarchy for Approvals.................................................13 Enhancements/Define Cross-Document Approval Process................................13 Enhancements/Block Issuing of Approvals/Define Dependant on System Status ..........................................................................................................................13 Enhancements/Block Issuing of Approvals/Define Dependant on Assignments 14
Specifications
Assuming PM Order is WCM relevant & all necessary WCM objects exist & linked, the following WCM objects are used: WC Application Approval is mandatory & will be copied at the time the IFS is given to the corresponding WCD WC Document: 2 distinct Approvals: o APP_01 optional approval with no influence on the approval traffic light (manually added) o IFS required approval, but cant be entered at this level: will be automatically set when Tag operation is performed The following screen can be reached by pressing management screen. while onto WCD
Simplified operation flow for tag/untag cycle (determined through use of work clearance document value)
Then save. Then open the order again & proceed to the valuation process: , select line & press yes
& save the order. This valuation step acceptance means we do agree to use WCM objects. While a No would simply come back to the standard order process.
Use
And select
After that, the optional APP_01 Approval can be granted by accessing this screen (through the traffic light), selecting the appropriate line & using the button; or simply use the column. 7
Use then to enter maintenance screen for switching actions. Make sure it looks like this
Modify the WC Application, & use button to select relevant Operational WCD, and then save the WC Application.
The red traffic light means that at least one approval is missing. You anyway can use to manually issue an option al approval for APP_01 permit. In the same way the WC Application has its light red
& the approval cant be manually granted. To go further in the process we now need to tag our maintenance items. On the switching screen accessible with , select lines, & make sure all have gone through Tagged step. The following screen capture shows how to proceed.
Select relevant lines, & use button. At this step, because the WCD items are in ETG status, IFS approval is automatically granted to the Operational WCD, and then copied to corresponding WC Application. WC Application having its traffic light green, the appears in the change maintenance order screen. button now
Customizing
Besides the APP_01 permit creation, customizing lies in SAP Customizing Implementation Guide / Plant Maintenance and Customer Service / Work Clearance Management / Approvals.
Standard/Maintain Approvals
10
Enhancements/Assign Approval
11
IFS approvals are required, automatically copied & set up when possible, influence traffic light.
Please note all boxes are cleared, but as it is a new permit, we need to declare it as available for Operational WCD note also we dont want this approval to influence the traffic light.
12
The APP_01 could probably better be defined with a real hierarchy level (here its meant to be the most important), & use a hierarchical mechanism of approval revocation
Here we define IFS for WCA will come from lower level that is Operational WCD. The ticked box ensure that the approval for the WCM object is only issued if approvals have already been granted in higher-/lower-level WCM objects
13
IFS approval can only be granted for Operational WCD when its items have been tagged
Here we forbid any WC Application IFS Approval without related WCM object (that is, to grant an IFS approval to a WC Application, you must have a WCD associated to this WC Application).
14