Work Clearance Management Scenario

Specifications.........................................................................................................2 Maintenance Order Process....................................................................................4 Phase 1: Order creation.......................................................................................4 Phase 2: WC Application creation........................................................................5 Phase 3: WC Document creation.........................................................................5 Phase 4: Links creation.......................................................................................8 Phase 5: Prepare WCD objects for use................................................................8 Phase 6: Allow Maintenance order processing....................................................9 Customizing..........................................................................................................10 Standard/Maintain Approvals............................................................................10 Enhancements/Assign Approval........................................................................11 Enhancements/Define Hierarchy for Approvals.................................................13 Enhancements/Define Cross-Document Approval Process................................13 Enhancements/Block Issuing of Approvals/Define Dependant on System Status ..........................................................................................................................13 Enhancements/Block Issuing of Approvals/Define Dependant on Assignments 14

Specifications
Assuming PM Order is WCM relevant & all necessary WCM objects exist & linked, the following WCM objects are used: WC Application Approval is mandatory & will be copied at the time the IFS is given to the corresponding WCD WC Document: 2 distinct Approvals: o APP_01 optional approval with no influence on the approval traffic light (manually added) o IFS required approval, but cant be entered at this level: will be automatically set when Tag operation is performed The following screen can be reached by pressing management screen. while onto WCD

Simplified operation flow for tag/untag cycle (determined through use of work clearance document value)

This will lead to a simplified tag/untag flow:

Maintenance Order Process


Phase 1: Order creation
Create order IW31 with WCM as a first operation

Then save. Then open the order again & proceed to the valuation process: , select line & press yes

To finally have this screen:

& save the order. This valuation step acceptance means we do agree to use WCM objects. While a No would simply come back to the standard order process.

Phase 2: WC Application creation


WCTK to create the WCA object, nothing special at this step.

Phase 3: WC Document creation


WCT6 to create the WCD. Dont forget to set 4 as a value for the use code in order to use simplified operational cycle.

Use

to enter Approval screen & add APP_01 Approval if needed.

And select

After that, the optional APP_01 Approval can be granted by accessing this screen (through the traffic light), selecting the appropriate line & using the button; or simply use the column. 7

Use then to enter maintenance screen for switching actions. Make sure it looks like this

Phase 4: Links creation


Modify the order, & use Application, and then save the order. button to select relevant WC

Modify the WC Application, & use button to select relevant Operational WCD, and then save the WC Application.

Phase 5: Prepare WCD objects for use


Modify your WC Document & use in Operational WCD menu

Modify your WC Application & use in WC Application menu

Phase 6: Allow Maintenance order processing


Now that order is WCM-relevant, the completions steps will be impossible without a Release for Execution step. This step is only allowed when traffic light in associated WC Application is green in our case, it means that maintenance items in our operational WCD have been tagged (lift & switch are off). So, we can now enter the Operational WCD in change mode

The red traffic light means that at least one approval is missing. You anyway can use to manually issue an option al approval for APP_01 permit. In the same way the WC Application has its light red

& the approval cant be manually granted. To go further in the process we now need to tag our maintenance items. On the switching screen accessible with , select lines, & make sure all have gone through Tagged step. The following screen capture shows how to proceed.

Select relevant lines, & use button. At this step, because the WCD items are in ETG status, IFS approval is automatically granted to the Operational WCD, and then copied to corresponding WC Application. WC Application having its traffic light green, the appears in the change maintenance order screen. button now

Customizing
Besides the APP_01 permit creation, customizing lies in SAP Customizing Implementation Guide / Plant Maintenance and Customer Service / Work Clearance Management / Approvals.

Standard/Maintain Approvals

10

Enhancements/Assign Approval

11

IFS approvals are required, automatically copied & set up when possible, influence traffic light.

Please note all boxes are cleared, but as it is a new permit, we need to declare it as available for Operational WCD note also we dont want this approval to influence the traffic light.

12

Enhancements/Define Hierarchy for Approvals

The APP_01 could probably better be defined with a real hierarchy level (here its meant to be the most important), & use a hierarchical mechanism of approval revocation

Enhancements/Define Cross-Document Approval Process

Here we define IFS for WCA will come from lower level that is Operational WCD. The ticked box ensure that the approval for the WCM object is only issued if approvals have already been granted in higher-/lower-level WCM objects

Enhancements/Block Issuing of Approvals/Define Dependant on System Status

13

IFS approval can only be granted for Operational WCD when its items have been tagged

Enhancements/Block Issuing of Approvals/Define Dependant on Assignments

Here we forbid any WC Application IFS Approval without related WCM object (that is, to grant an IFS approval to a WC Application, you must have a WCD associated to this WC Application).