Vous êtes sur la page 1sur 8

BUILDING ECONOMICS

TASK 4
T

Description and price build-up

Length
24212
5500
Wall 4 / 100
Wall 2 / 100
29.91
16.80

502.49

200
29912

Qty

Rate

Amount

Width
12000
4400
400
16800

150 mm top soil excavation for


preservations. Include Disposal of
excavated material.
503m2 140

70,420.00

Pit excavation
60/ 0.90
0.90
0.90

43.74

Pit excavation in hard soil average


depth
1.0 m, (60 Nrs) commencing
from existing level & including
preservation for excavated surface, E.
44m3
W. Support.
Back Filling
Pit excn. 0.90x0.90x0.90
Ddt
Footing 0.90x0.90x0.15
Column 0.18x0.18x0.75

32168.7
2

1,415,424.68

= 0.729
= 0.122
= 0.024
0.583

Price Build Up
Pit excn. 0.729 @ 680
=
495.72
EWS 4x0.9x0.9 @ 650 = 2106.00
L & C 0.9x0.9 @ 25
= 2025.00
Back filling 0.583 @ 470 = 27542.00
Total cost per m3
32168.72
Trench excavation
2 / 12200
2 / 30112

24400
60224
84624

Ddt
4 / 2 / / 100

BTEC HND IN QUANTITY SURVEYING

400
84 224
Page 1

BUILDING ECONOMICS
TASK 4
T

Description and price build-up


Addition
2 / 2200
4400
2850
7250
Add
2 / 2 / / 100
200
(T) 2 / / 100
100
2 / 7550
15100
2200
3025
5225
Add
2 / / 100
/ 100

Qty

Rate

Amount

100
50
2 / 5375
10750
84 224
15 100
10 750
110 074

110m 1885.75

207,432.50

Adjustment for pit;


110 074
Ddt
Pit - 38

110.04

110.04

0.90

34.20
110 040

Trench excavation in hard soil average


width
300 mm, maximum depth
1.0
m, commencing from existing level &
including the labor charges.
Price Build Up
Trench excn.@ 720 per 1m
EWS. 2x1.0x1 @ 580
L&C 0.23x1 @ 25
Total cost per m

BTEC HND IN QUANTITY SURVEYING

= 720.00
= 1160.00
=
5.75
= 1885.75

Page 2

BUILDING ECONOMICS
TASK 4
T

D
60

60/

6/

7.2

110

735/ 1.64

S
60

432

660

1205.4
0

Description and price build-up


Qty
Footing
Precast Column Footing 0.90
0.90
fixed by manually & labor charges 60nr
including

Column
Precast column 7200 mm height 175 mm 432m
wide, fixed by Crain & column will be
connected with the footing using by mass
concrete (1:2:4) , 0.90 m 0.90 m 0.30
m of column base should used.

Tie Beam
Adjustment for tie beam
Center line
110 074
Ddt
Column - 38 0.175
7
110 067
Reinforcement for tie beam
Y 16 bar reinforcement in tie beam

Rate

805

48,300.00

5710

342,600.00

1.036t 13500
0
0.27t

= 1.036 t
R links in tie beam base

Amount

139,860.00

30,240.00
11200
0

= 0.27 t
110
0.25
0.60
16.50

Concrete
1:2:4 C 20 of reinforced concrete in tie 17m3
beams, including Form Work, placing,
compacting, curing, labor charges etc.
Price Build Up
1m3 concrete
4250
3
8m Form wk. @ 250
2000
Labor charges 15 %
937
Cost per m3

BTEC HND IN QUANTITY SURVEYING

122,179.00
7187

7187

Page 3

BUILDING ECONOMICS
TASK 4
T

42/ 2.05

S
86.10

2/
24.00
2.40
16.8
3.00
12.00
3.00

115.20

Description and price build-up


Qty
Beam
175
175 P. C. C beam, length 2050
fixed by Crain. Beam connected to the
86m
column by Bolt & Nut.

Rate

Amount

5710

491,060.00

Slab
1200 1200 P. C. C slab, 150 mm thick
202m2 4304
fixed by Crain.

869,408.00

50.40
36.00
201.60

First floor center line


Ext. wall
16800
29912
2 / 46 712
93 424
Ddt
4 / 2 / / 100
Int. wall
Ddt
2 / 175

400
93 024
2 /3000

Ddt
2 / 175
Int.wall

110.00
3.00
93.02
3.00
30.80
3.00

330
279.06
92.40
701.46

6000
350
4 / 5650
22 600
2400
350
4 / 2050
8200
30 800

Wall
100 mm thick concrete facing block
702m2 1280.50
masonry work with 1:5 Cement mortar.
Price Build Up
Facing block 1m
= 862.50
Mortar 1m
= 270
Labors 13%
= 148
1280.50

BTEC HND IN QUANTITY SURVEYING

898,911.00

Page 4

BUILDING ECONOMICS
TASK 4
T

2/

110
3.00
2/
93.02
3.00
2/
30.80
3.00
2/60/ 0.18
6.15

660.00
558.18
184.80

Description and price build-up


Painting

Qty

Rate

Amount

Internal & external area emulsion


painting
Price Build Up
Painting material = 40per m2
Labour cost wit tools = 12 per m2
Total cost
= 52 per m2

1536m2 52

79,872.00

132.84
1535.8
2

BTEC HND IN QUANTITY SURVEYING

Page 5

BUILDING ECONOMICS
TASK 4
T

07

07

Description and price build-up


Doors (D)

Qty

Plywood door with timber framed size


07nr
1800 x 2100

Rate

Amount

6678.73

46,751.11

6192.47

24,769.88

Composite rate build-up per door


Plywood door with framed = 9700.00
Lintel 2.40 m @ 450 per m = 1080.00
10780.00
Ddt
Block work 3.78 @ 1280.50 = 4840.29
5939.71
Ddt
Block work 0.36 @ 1280.50 = 460.98
5478.73
Add
Finishing with varnish
= 1200.00
Total cost per door

04

04

6678.73

Doors (D1)
Plywood door with timber framed size 04
1050 x 2100
Composite rate build-up per door
Plywood door with framed = 7400.00
Lintel 1.65 m @ 450 per m = 742.50
8142.50
Ddt
Block work 2.21 @ 1280.50 = 2829.90
5312.59
Ddt
Block work 0.25 @ 1280.50 = 320.12
4992.47
Add
Finishing with varnish
= 1200.00
Total cost per door

BTEC HND IN QUANTITY SURVEYING

6192.47

Page 6

BUILDING ECONOMICS
TASK 4
T

04

04

Description and price build-up


Doors (D2)

Qty

PVC door with PVC framed size 1050 x


2100
04

Rate

Amount

3142.77

12,571.08

6127.80

73,533.60

Composite rate build-up per door


PVC door with framed
= 5550.00
Lintel 1.65 m @ 450 per m = 742.50
6292.50
Ddt
Block work 2.21 @ 1280.50 = 2829.90
3462.90
Ddt
Block work 0.25 @ 1280.50 = 320.13
Total cost per door

3142.77

Window (W)
Extra over brick wall for aluminum
window, including glass. size
1800 x
1500
21
21

21
Composite rate build-up per window
Extra over brick wall for aluminum
window, including glass
= 12300.00
Lintel 1.65 m @ 450 per m =
742.50
13042.50
Ddt
Block work 2.7 @ 1280.50 =
3457.35
9585.15
Ddt
Block work 0.36 @ 1280.50 = 3457.35
Total cost per door
6127.80

BTEC HND IN QUANTITY SURVEYING

Page 7

BUILDING ECONOMICS
TASK 4
T

04

04

Description and price build-up


Fanlight (F)

Qty

Extra over brick wall for aluminum


window, including glass. size 300 x 04
600

Rate

Amount

1248.53

4,994.12

647m2 3836 .35

24,819,146.45

Composite rate build-up per fanlight


Extra over brick wall for aluminum
fanlight, including glass
= 2480.00
Lintel 1.20 m @ 450 per m = 540.00
1940.00
Ddt
Block work 0.18 @ 1280.50 = 230.49
1479.02
Ddt
Block work 0.18 @ 2550
= 230.49
Totalcost per door
1248.53

Roof
2/

10.2
0
31.7
1

646.8
8

Asbestos Roof covering with steel truss


Composite rate build-up
Asb/ sheet 2/3x40 @ 2600 = 624000.00
Wind tie 164 nr@ 22
= 3608.00
62708.00
Steel truss
97.185x @300 per m
= 29155.50
4/2/31.712 @850 per m = 215641.60
Gus plate 15 @ 780 per nr = 11700.00
Bold and nuts 88 @ 112 = 9856.00
Labour
= 53324.29
463511.19
Total cost of truss 1854044.76
Cost of roof 3836.35 per m2

BTEC HND IN QUANTITY SURVEYING

Page 8

Vous aimerez peut-être aussi