Vous êtes sur la page 1sur 6

SIT Faculty Academic Profile Monitoring System Progect Gantt Chart ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Task Task Name Mode

SIT Faculty Academic Profile Monitoring System Letter of Approval Project Gantt Chart System Profile System Flowchart (Existing System) System Requirements Specification Introduction Purpose and Scope Definitions, Acronyms and Abbreviations References and Overview Business Description Business Description Objectives Stakeholder Profile

DurationStart

Finish

June W-2 W-1 W1 W2

July W3

W4

85 days Wed 6/15/11 Mon 10/3/11 5 days? 9 days? 5 days? 4 days? Wed 6/15/11 Mon 6/20/11 Wed 6/15/11 Fri 6/24/11 Tue 6/21/11 Mon 6/27/11 Wed 6/22/11 Mon 6/27/11

41 days Thu 6/16/11 Fri 8/5/11 13 days Thu 6/16/11 Fri 7/1/11 9 days 9 days? 4 days? 7 days? 4 days 4 days? Thu 6/16/11 Mon 6/27/11 Thu 6/16/11 Mon 6/27/11 Wed 6/22/11 Mon 6/27/11 Sat 6/18/11 Mon 6/27/11 Wed 6/22/11 Mon 6/27/11 Wed 6/22/11 Mon 6/27/11

11 days Sat 6/18/11 Fri 7/1/11

Task Split Milestone Summary Project: Project Gantt Chart Date: Wed 6/29/11 Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Page 1

Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Progress

SIT Faculty Academic Profile Monitoring System Progect Gantt Chart ID 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Task Task Name Mode
Presentation of Subject of Study 1st Defense Document Revisions The Overall Description Product Perspective Product Function User Characteristics Constraints Assumptions and Dependencis Apportioning of Requirements Tasks for Midterms Functional Requirements File Maintenance Report Generation Use Cases GUIs and Table of Fields

DurationStart
0 days 9 days 9 days 9 days

Finish

June W-2 W-1 W1 W2

Mon 7/4/11 Mon 7/4/11 Mon 7/4/11 Thu 7/14/11 Fri 8/5/11 Mon 8/1/11 Mon 8/1/11 Wed 8/3/11 Tue 8/2/11 Tue 8/2/11 Tue 8/2/11 Fri 8/5/11 Fri 7/29/11 Fri 7/29/11 Fri 7/22/11 Fri 7/22/11

July W3 7/4

W4

13 days Fri 7/22/11

11 days Fri 7/22/11 10 days Fri 7/22/11 10 days Fri 7/22/11 10 days Fri 7/22/11 13 days Fri 7/22/11 7 days 7 days 6 days 7 days Fri 7/22/11 Fri 7/22/11

Sat 7/23/11 Fri 7/29/11 Sat 7/23/11 Sat 7/30/11

Task Split Milestone Summary Project: Project Gantt Chart Date: Wed 6/29/11 Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Page 2

Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Progress

SIT Faculty Academic Profile Monitoring System Progect Gantt Chart ID 29 30 31 32 33 34 35 36 37 38 39 40 Task Task Name Mode
Use Case Diagram of the Whole System Midterm Defense Tasks for Final Defense Revised Functional Requirements File Maintenance (Finals) Report Generation Use Cases (Finals) GUIs and Table of Fields (Finals) Group Testimonial Curriculum Vitae Pictures Final Defense (Proposal System Walkthrough) Revised and Approved Final SRS

DurationStart
7 days 0 days

Finish

June W-2 W-1 W1 W2

July W3

W4

Sat 7/23/11 Sat 7/30/11 Mon 8/8/11 Mon 8/8/11 Fri 9/16/11 Wed 9/14/11

27 days Fri 8/12/11 25 days Fri 8/12/11

19 days Sat 8/20/11 Wed 9/14/11 19 days Sat 8/20/11 Wed 9/14/11 19 days Sat 8/20/11 Wed 9/14/11 19 days Sat 8/20/11 Wed 9/14/11 19 days Sat 8/20/11 Wed 9/14/11 19 days Sat 8/20/11 Wed 9/14/11 0 days Mon 9/19/11 Mon 9/19/11 10 days Wed 9/21/11 Mon 10/3/11

Task Split Milestone Summary Project: Project Gantt Chart Date: Wed 6/29/11 Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Page 3

Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Progress

SIT Faculty Academic Profile Monitoring System Progect Gantt Chart July W4 W5 W6 August W7 W8 W9 W10 W11 September W12 W13 W14 W15 October W16 W17 W18

Task Split Milestone Summary Project: Project Gantt Chart Date: Wed 6/29/11 Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Page 4

Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Progress

SIT Faculty Academic Profile Monitoring System Progect Gantt Chart July W4 7/4 W5 W6 August W7 W8 W9 W10 W11 September W12 W13 W14 W15 October W16 W17 W18

Task Split Milestone Summary Project: Project Gantt Chart Date: Wed 6/29/11 Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Page 5

Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Progress

SIT Faculty Academic Profile Monitoring System Progect Gantt Chart July W4 W5 W6 August W7 W8 8/8 W9 W10 W11 September W12 W13 W14 W15 October W16 W17 W18

9/19

Task Split Milestone Summary Project: Project Gantt Chart Date: Wed 6/29/11 Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Page 6

Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Progress

Vous aimerez peut-être aussi