PRE-ENGINEERED BUILDINGS DIVISION VIETNAM PEB

QUALITY SYSTEM MANUAL (QSM-PEB)


Issued by:

MANAGEMENT REPRESENTATIVE

Approved by:

GENERAL DIRECTOR

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08

Section i
Table of Contents
Sect. Ref. Revision Specification No. ISO9001No Date I 5 20.09.08 Table of contents Ii 5 20.09.08 Record of Revisions Iii 5 20.09.08 Circulation list 0.0 5 20.09.08 Introduction 0.1 5 20.09.08 General Information 0.2 1.2 5 20.09.08 Scope and Application of this Manual. 1.0 4 5 20.09.08 Quality Management system 1.1 4.1 5 20.09.08 General 1.2 4.2 5 20.09.08 Documentation 1.2.1 4.2.1 5 20.09.08 General 1.2.2 4.2.2 5 20.09.08 Quality manual and internal documents 1.2.3 4.2.3 5 20.09.08 Control of documents 1.2.4 4.2.4 5 20.09.08 Control of records 2.0 5 5 20.09.08 Management responsibility 2.1 5.1 5 20.09.08 Management Commitment 2.2 5.2 5 20.09.08 Customer Focus 2.3 5.3 5 20.09.08 Quality Policy 2.4 5.4 5 20.09.08 Planning 2.4.1 5.4.1 5 20.09.08 Quality Objectives 2.4.2 5.4.2 5 20.09.08 Quality Management System Planning 2.5 5.5 5 20.09.08 Responsibility, Authority and Communication 2.5.1 5.5.1 5 20.09.08 Responsibility, Authority Chief Operating Officer General Director Organization 2.5.2 5.5.2 5 20.09.08 Management Representative 2.5.3 5.5.3 5 20.09.08 Communication 2.6 5.6 5 20.09.08 Management Review 2.6.1 5.6.1 5 20.09.08 General 2.6.2 5.6.2 5 20.09.08 Review Input, System Status Report 2.6.3 5.6.3 5 20.09.08 Review Output 3.0 6 5 20.09.08 Resources Management 3.1 6.1 5 20.09.08 Provision of Resources 3.2 6.2 5 20.09.08 Human Resources 3.2.1 6.2.1 5 20.09.08 General 3.2.2 6.2.2 5 20.09.08 Competence, Awareness and Training 3.3 6.3 5 20.09.08 Resources (hardware and software) 3.4 6.4 Work Environment

Page ii of v

Page ii iv v 1 1 2 3 3 4 4 4 4 5 7 7 7 7 8 8 8 10 10 10 10 10 10 11 12 12 12 12 13 13 13 13 13 14 14

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08

Section i
Sect. No. 4.0 4.1 4.2 4.2.1 4.2.2 4.2.3 4.3 4.3.1 4.3.2 4.3.3 4.3.4 4.3.5 4.3.6 4.3.7 4.3.8 4.4 4.4.1 4.4.2 4.4.3 4.4.4 4.5 4.5.1 4.5.2 4.5.3 4.5.4 4.5.5 4.6 5.0 5.1 5.2 5.2.1 5.2.2 5.2.3 5.2.4 Ref. ISO 9001 7 7.1 7.2 7.2.1 7.2.2 7.2.3 7.3 7.3.1 7.3.2 7.3.3 7.3.4 7.3.5 7.3.6 7.3.7 7.4 7.4.1 7.4.2 7.4.3 7.5 7.5.1 7.5.2 7.5.3 7.5.4 7.5.5 7.6 8 8.1 8.2 8.2.1 8.2.2 8.2.3 8.2.4 Revision 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 20.09.08 Specification

Page iii of v Page 15 15 16 16 16 17 18 18 18 18 19 19 19 19 19 20 20 20 20 21 22 22 22 23 24 24 26 28 28 28 28 28 29 30 30 30 30 32 33 33 33 33

5.3 5.4 5.5 5.5.1 5.5.2

8.3 8.4 8.5 8.5.1 8.5.2

5 5 5 5 5

20.09.08 20.09.08 20.09.08 20.09.08 20.09.08

Product realization Planning of Product Realization Customer Related Processes Determination of Product Requirements Review of Product Requirements Customer Communication Design And Development Design and Development Planning Design and Development Input Design and Development Output Design and Development Review Design and Development Verification Design and Development Validation Design and Development Changes Design and Development Manuals Purchasing Purchasing Process Purchasing Information Verification of Purchased Product Outsourcing Production and Service Provision Control of Production and Service Provision Validation of Process for Production and Service Provision Identification and Traceability Customer Property Preservation of Product Control of Monitoring and Measuring Devices Measurement, Analysis and Improvement General Monitoring and Measurement Customer Satisfaction Internal Audit Monitoring Measurement of Processes Monitoring Measurement of Product In-Process Inspection & Testing Final Inspection and Testing Inspection and Test Records Control of Nonconforming Product Analysis of Data Improvement Continual Improvement Corrective Action and Preventive Action

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08

Section i
5 20.09.08 Annex 1, Annex 2

Page iii of v 35

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08

Section ii
Records of Revisions

Page iv of v

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08

Section ii
# ISO S e c t i o n 1 2 3 4 5 6 00 01 02 03 04 05 First Issue Minor Changes Minor Changes Entire Quality Management System Manual Logo change Minor Changes,PIS added and Sales Territories revised. Rev. Item

Page iv of v Date

01.11.99 02.07.01 15.11.02 24.12.03 20.09.08

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08

Section iii
Circulation List
COPY 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 General Director Finance Manager Marketing Manager Production Manager HR & Administration Superintendent Purchasing Manager Engineering Supervisor Production Engineering Supervisor Production Supervisor Customer Service Manager Shipping & Logistics Supervisor Production & Material Control Supervisor Plant Maintenance Manager IT Acting Manager QC Supervisor Product Research & Development Supervisor Adminstration Supervisor I.E Supervisor HR Supervisor Production Foreman Production Foreman Production Foreman Production Foreman Production Foreman Electrical Foreman Mechanical Foreman ISSUED TO

Page v of v

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 1 of 42

Title: Introduction

Section 0.1
0.1 GENERAL INFORMATION 0.1.1 Introduction

Zamil Steel (ZS) is the largest manufacturer of Pre-Engineered Steel Buildings in the Middle East and has the most diverse product line and expertise in this industry. The Division manufactures pre-engineered steel buildings for factories, warehouses, workshops, supermarkets, automobile showrooms, sports halls, distribution centers, aircraft hangars, car parking sheds and any one, two or three storey building. Zamil Steel uses state-of-arthardware, software and machinery in the estimating, designing, shop detailing and manufacturing of all its products. 0.1.2 Brief History

ZS was founded by A.H. Al-Zamil Group of Companies in 1976 as designer and manufacturer of Pre-Engineered Steel Buildings and expanded into Structural Steel Work in 1984. The companys main operation is based at Dammams first & second industrial estates. The company has progressively expanded as a major steel fabricator in the region greatly contributing to the phenomenal growth of the Saudi Arabian industrial sector and has successfully completed numerous large and prestigious projects in the Kingdom of Saudi Arabia. 0.1.3 Marketing Presence

Zamil Steel Vietnam maintains its own sales and technical support staff in 17 sales territories. These are in Japan, Manila, Yangon, Jakarta Mandalay, Kuala Lumpur, Singapore, Bangkok, Malaysia, Cambodia, Vientiane, Johar, Pyinmana, Batam, Hanoi, Haiphong Danang and HCMC ,strategically located through out Asia and 2 Liaison Centers in Sydney and Shanghai, and offer the most superior technical and customer support in the pre-engineered buildings industry. 0.1.4 Vietnam Manpower:

The Vietnam PEB division currently employs a multinational work force of approximately 718 persons.

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 2 of 42

Title: Introduction

Section : 0.2
0.2 SCOPE AND APPLICATION

Zamil Steel Management has established the following scopes of its businesses:

Design, Detailed Engineering, Manufacture and Supply of Pre-Engineered Steel Buildings.


This manual (QSM-PEB) has been written and implemented in-line with the requirements of the International Organization for Standardization ISO 9001.

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 3 of 42

Title: Quality Management System

Section 1.1
1. QUALITY MANAGEMENT SYSTEM 1.1 GENERAL

Zamil Steel has identified the processes needed for a QMS and determined the sequence and interactions along with the method to operate and control these processes ensuring availability of information to operate, measure, monitor, control and analyze the data, taking action to achieve planned results and improvement. Outsourcing Currently Zamil Steel has some processes outsourced to outside organizations. Control of such outsourced processes is described in sections 4.1, 4.4 of this Quality Manual and related documents.

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 4 of 42

Title: Quality Management System

Section 1.2
1.2 1.2.1 DOCUMENTATION General

Design Manuals; Design Output Documents; Zamil Steel Standards

Technical Drawings; Technical standards; Customer drawings; Customer specification; ISO9001.

Internal Documents 1.2.2 Quality manual and internal documents

External Documents

Quality Manual: The Pre-Engineered Buildings (PEB) Division has documented its policies as per the recommendations of ISO 9001 in the form of a Quality System Manual bearing the title QSM (PEB), generally referred to in this manual as QSM. QSM is a document introducing Company, Companys quality policy, organization structure, responsibilities, and authorities. Quality manual refers to procedures of quality system and introduces structure of documentation.

Company and Management Procedures: An approved standard format for the structure of a typical procedure shall be followed. Refer to Procedure # ZSM 01.03. A list of all revised procedures shall be issued as and when required. Work Instruction shall also be referred to as procedures.

Departmental procedures and Work Instructions: the documents describing in details how a particular work is performed at a particular stage, application scope of which is determined by scope of related Procedures or Instruction.

Records: documents that provide objective evidence of activities performed or result achieved. Control of forms: forms are enclosed within procedures and work Instructions and are referenced in respective procedures and work Instructions. The issuance, amendment, revision and distribution of QSM and other procedures are controlled as per Procedure # ZSM 05.01.

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 5 of 42

Title: Quality Management System

Section 1.2
1.2.3 Control Of Documents General

The Project Information System (PIS) Contract Information Form (CIF), design input, engineering output drawings and approved working procedures are considered as Controlled Documents. Refer to Procedures # ZSM 05.01. Document Approval and Issue Controlled Documents shall be reviewed and approved by the concerned Manager/Supervisor and shall be distributed and made available to all relevant recipients. A Master List of all Controlled Documents shall be established and be readily available for reference showing the latest revision number of the drawings for a particular job or working procedures. Document Changes All Controlled Documents are subject to revisions, improvements and amendments and are issued by the originally designated issuing authority bearing the latest revision number. Superseded and obsolete documents shall be removed from use. The issuer may retain a copy of the old document for reference purposes, which shall be marked Void or Old for reference only or Delete. Related documents ZSM 05.01- Document and Data Control PR 05.13- Document and Data Control in Purchasing CSD 05.01- Document Control PC 05.01- Document control Production SD 05.01- Documentation SD 05.02- Control of Documents in Shipping QCP 05.01- Document and Data control in QC Department 1.2.4 Control Of Records General Records shall remain legible, readily identifiable and retrievable. A documented procedure is established to define the methods of identification, storage, protection, retrieval and retention time, disposition of records.

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 6 of 42

Title: Quality Management System

Section 1.2

All documents and data specified in Section # 01 of this manual shall be treated as records with the exception of approved procedures. When required as per contract, the Quality Dossier containing Mill Certificates, Welding Procedures and Inspection Test Reports shall be treated as a quality record. Record Retention Cartons and bundles shall be marked with the date of disposal or destroy and shall be maintained for a period of minimum one year. The Administration Department shall check and confirm the safe and accurate storage of records. Related Documents ZSM 16.01- Quality Records Of Various Depts. PR 16.08 - Maintaining Quality Record in Purchasing. QCP 05.03- E-mail Query Procedure CSD 05.01 Control of Computerized Documents MN 05.01 Document & Data Records Keeping at PM Department

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 7 of 42

Title: Management Responsibility

Section 2.1 2.4


2. MANAGEMENT RESPONSIBILITY 2.1 MANAGEMENT COMMITMENT

Top management commits to the development and implementation of the quality management system and continually improving its effectiveness by a) Communicating to all staff the importance of meeting customer as well as statutory and regulatory requirements;
b) Establishing the quality policy;

c) Ensuring that quality objectives are established at all relevant functions and levels; d) Conducting management reviews; and e) Ensuring the availability of resources. It is the objective of Zamil Steel Buildings Company Limited to provide quality products conforming to the agreed upon specifications of contracted jobs, in order to satisfy our valued customers. To achieve these goals, the company is vigorously implementing the International Quality Management System ISO 9001 . 2.2 CUSTOMER FOCUS Zamil Steel top management ensures that customer requirements are determined and are met with the aim of enhancing customer satisfaction. 2.3 QUALITY POLICY It is the Objective of Zamil Steel (Pre-Engineered Building Division) to remain a renowned supplier of Quality Products by: Identifying Customers needs and expectations and ensuring their satisfaction. Ensuring controlled processes are fully implemented and developed. Complying with the requirements of the Quality Management System and continually improving its effectiveness. Establishing and communicating meaningful Quality objectives and performance targets. Ensuring the Quality Policy is well communicated and clearly understood by every employee.

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 8 of 42

Title: Management Responsibility

Section 2.1 2.4

Ensuring that non-conformities in the product and system are identified, investigated, analyzed and improved. Providing healthy and safe working environment. Developing employee skills and increasing their contributions through effective training. Developing supplier relationships to obtain defect free material. KHALID AL-ZAMIL President Plan DoCheckAct 2.4 PLANNING 2.4.1 Quality Objectives Zamil Steel top management ensures that quality objectives, including those needed to meet requirements for product, are established at relevant functions and levels within the Company. The quality objectives are measurable and consistent with the quality policy. 2.4.2 Quality Management System Planning

Date: January 2004

Zamil Steel top management ensures that a) the planning of the quality management system is carried out by taking into account the requirements of ISO 9001 , Companys management culture and processes, as well as the quality objectives; b) Plans are established in advance to ensure the integrity of quality management system when changes are implemented. c) Zamil Steel has identified the processes needed for the quality management system and applied them. The sequence and interaction of those processes are presented on the annex No 2 of this Quality System Manual. Besides, the interaction between processes is described by the reference between different documents and their layers and by defining communication channel between different departments and positions in their duties and responsibilities. d) Criteria and methods needed to ensure effective operation and control of these processes are identified in respective chapters of this Quality System Manual and related Management Procedures, departmental documents. e) Zamil Steel makes resources and information available to support the operation and monitoring of these processes. f) Monitoring, measurement and analysis of these processes are made through Plan-Do-Check steps of PDCA cycle and in case of needs, actions are made to

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 9 of 42

Title: Management Responsibility

Section 2.1 2.4

ensure achievement of planned results and continual improvement of these processes.

Related Documents: ZSM 01.03 Standard Format For Writing /Changing Of Policy/Procedures PR 01.01 Purchasing Department Policy and Procedure PR 01.03 Goals of Purchasing Department

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 10 of 42

Title: Management Responsibility

Section 2.5

2.5 RESPONSIBILITY, AUTHORITY AND COMMUNICATION 2.5.1 Responsibility and Authority

Chief Operating Officer The Chief Operating Officer of the Company is Senior Vice President. He reports to the President of the company and is accountable to the Board of Directors. General Director The General Director has full authority over the overall performance of the Vietnam PEB Division. He is responsible for the performance of the various departments: Marketing, Sales, Operations, Engineering & Estimating (E & E), Customer Service (CSD) and Quality Control (QC) and reports directly to the Vice President. Organization Organization Charts Figures QC # 1 to 9 in annex 1 show the various department organization charts. Responsibility and Authority The responsibility and authority of employees are stated under individual department procedures. Related Documents: Different departmental documents describing Duties and Responsibilities Organization chart of different departments 2.5.2 Management Representative

The Quality Assurance & Continuous Improvement Manager (QACI Manager) is the Management Representative for the implementation and maintenance of the Quality System and reports directly to the General Director, Vietnam PEB. Responsibility of Management Representative: a) Ensuring that processes needed for the quality management system are established, implemented and maintained, b) Reporting to top management on the performance of the quality management system and any need for improvement, and

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 11 of 42

Title: Management Responsibility

Section 2.5

c) Ensuring the promotion of awareness of customer requirements throughout the organization. 2.5.3 Communication

Zamil Steel top management ensures that appropriate communication processes are established within the organization and that communication takes place regarding the effectiveness of the quality management system. Communication is taken place by means of staff meetings, reports, management meetings, information boards, memos, etc.

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 12 of 42

Title: Management Responsibility

Section 2.6
2.6 MANAGEMENT REVIEW 2.6.1 General

Top management reviews quality management system to ensure its continuing suitability, adequacy and effectiveness. This review shall include assessing opportunities for improvement and the need for changes to the quality management system, including the quality policy and quality objectives. Records from management reviews shall be maintained. 2.6.2 Review input, System Status Report The Management Representative shall report periodically on the status of the quality system to Management Committee for their review. The input to management review shall include information on a) Results of audits, b) Customer feedback, c) Process performance and product conformity, d) Status of preventive and corrective actions, e) Follow-up actions from previous management reviews, f) Changes that could affect the quality management system, and g) Recommendations for improvement. 2.6.3 Review output

The output from the management review shall include any decisions and actions related to a) Improvement of the effectiveness of the quality management system and its processes, b) Improvement of product related to customer requirements, and c) Resource needs. The Management Representative shall conduct Management Review meetings as and when needed but at least once a year. The Strategic Management Meeting held every month, where all Managers/Supervisors of the departments are usually present, shall also be treated as Management Review Meeting. Related Documents: ZSM 01.04 Management Review

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 13 of 42

Title: Resource Management

Section 3.1 - 3.2


3.1 PROVISION OF RESOURCES Zamil Steel determines and provides resources needed a)

To implement and maintain the quality management system and continually improve its effectiveness, and b) To enhance customer satisfaction by meeting customer requirements.

The needs in resources are systematically reviewed and analyzed in regular Management reviews and/or in ad-hoc reviews. Actions and decisions related to resource needs are included in management review output. 3.2 HUMAN RESOURCES 3.2.1 General All technical and office staff shall be recruited and trained to meet their respective job description and be competent on the basis of appropriate education, training, skills and experience. 3.2.2 Competence, awareness and training

Zamil Steel: a) Determines the necessary competence for personnel performing work affecting product quality, b) Provides training or take other actions to satisfy these needs, c) Evaluates the effectiveness of the actions taken, d) Ensures that its personnel are aware of the relevance and importance of their activities and contribution to the achievement of the quality objectives. Records are maintained within the Administration Department. o Training Facility Quality Policies stated in this Quality System Manual shall be conveyed to all employees through various seminars, open forum discussions and Technical Training Programs. o Hiring of Qualified Staff Candidates with appropriate experience and qualifications shall be employed. Further training, as deemed necessary, shall be the responsibility of the employees immediate Supervisor. Related Documents: ZSM 18.01 Training of Staff QCP 09.01 Qualification of New Welders ADM 01.01 Hiring Of Staff, OP 18.02 Testing of Newly Hired Welders Departmental Training procedures

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 14 of 42

Title: Resource Management

Section 3.3 3.4

3.3 Resources (Hardware and Software) Zamil Steel determines, provides and maintains the infrastructure needed to achieve conformity to product requirements. Buildings, workspace and associated utilities, all hardware and software (where applicable) shall be reviewed periodically to ensure its adequacy and suitability to serve the intended functions (refer to Engineering computer aids manual). Related Documents: MN 01.04 New and Obsolete Equipment; MN 09.01 Planned preventive and corrective maintenance CSD 05.01 Control of Computerized Documents MN 05.01 Document & Data Records Keeping at PM Department 3.4 WORK ENVIRONMENT Zamil Steel has determined production and servicing processes having critical impact from work environment and their conditions/parameters are controlled to achieve conformity to product requirements. Related Documents: Production and Material departmental procedures;

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 15 of 42

Title: Product Realization

Section 4.1
4.1 PLANNING OF PRODUCT REALIZATION

Zamil Steel has planed and developed the processes needed for product realization. Planning of product realization is consistent with the requirements of the other processes of the quality management system. Zamil Steel has determined: o Quality objectives and requirements for the product set forth in inspection procedure and instructions of Quality Control department and respective design and development output documents. o Processes, documents are established and resources specific to the product are identified and established/provided; o Verification, validation, monitoring, inspection and test activities specific to the product and criteria for product acceptance are established and implemented; o Records needed to provide evidence that the realization processes and resulting product meet requirements are identified in respective departmental procedures/instructions and are maintained. A standard Quality Plan (QP), also referred to as the Inspection and Test Program (ITP), shall be adopted for each PEB jobs. A standard ITP shown in Appendix A. The standard ITP shall be superseded if required by a Customers Approved ITP. o Identification and Acquisition of Resources

All departments within the Vietnam PEB division shall utilize the proper mix of skilled human resources and equipment. o Updating Quality Control Techniques

The Vietnam PEB Division shall customize its existing procedures and techniques to suit the requirements of a particular Project/Job. QC Department shall modify and re-issue the procedures in the revised ITP in the light of special requirements of a customer. o Sp.Painting. QC may sub-contract a part or all testing requirements for a certain job to an Independent Testing Agencies, if required necessary as per customers approved Quality Plan.

Sub-Contracting

of

Special

Testing.

HDG

and

QC shall monitor and maintain the record of all such tests.

HDG and some Special Paint jobs are sub-contracted as per the Quality Plan and the QC monitor and maintain the records of the results.

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 16 of 42

Title: Product Realization

Section 4.2
4.2 CUSTOMER RELATED PROCESSES 4.2.1 Determination of Product Requirements

Three types of jobs are normally processed, which can be described as follows: Simple Inquires (with no specifications from the Customer & Zamil Steel standard supplies): Most of times, estimation for such buildings are done by the Representative Offices without the involvement of the Head Office. In case of higher complexity of such standard buildings, Vietnam CSD and E & E shall provide assistance to Representative Office. Simple Inquires (with no specifications from the Customer but with non-standard supplies): this includes; Special Paint Non-standard/Inventory Special Delivery/Discount Or other Validation of Process for Production and Service Provision

In such a case, consultation with the Head Office is required. After approval, estimates shall be prepared by the Representative Office or by the E & E Department depending upon the complexity of the building. Inquires with Customers specification Estimates shall only be prepared at the Head Office. CSD shall thoroughly review Customers specification. Representative Offices are responsible for the Project Information System ( PIS) Contract Information Form (CIF) once a job is finalized. This PIS/CIF shall include all the information of the Clients requirement. All assumptions, exclusions and deviations from Zamil Steels Standard Practices and Procedures shall be clearly mentioned in the PIS/CIF. 4.2.2 Review of Product Requirements

The comments on those specifications shall be sent to the Representative Office by the CSD. The Sales Engineers shall clearly mention all non-standard specifications in the PIS/CIF for CSD to prepare additional necessary action that may require. Review Procedures: when special requirements are received by the CSD after job entry, review shall be performed as follows:

By the CSD Engineers, in consultation with the CSD Supervisor or by the Estimating Engineers in consultation with Engineering Supervisor, comments and observation shall be sent to the Representative Offices directly.

If, in the opinion of the Engineering Supervisors, further approval or clarifications are required, the matter shall be presented to General Director for his advice through CSD Supervisor.

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 17 of 42

Title: Product Realization

Section 4.2

CSD Supervisor may review on behalf of the General Director or partial involvement of some members through phone or emails. The summary of the comments shall be conveyed to the Representative Offices, for necessary action. The Management shall only be convened upon the request of the CSD Supervisor to discuss a particular project, if he feels necessary.

Records: The official job file shall be maintained at the CSD. The job file shall contain all records of the contract. Review Changes The Representative Offices in conjunction with the CSD shall maintain a record of all changes in the contract and revisions of the PIS/CIF. CSD Department shall issue a revised PIS/CIF to all concerned departments. 4.2.3 Customer Communication

Zamil Steel has determined and implemented arrangements for communicating with customers in relation to a) Product information, b) Enquiries, contracts or order handling, including amendments, and c) Customer feedback, including customer complaints. Related documents: ZSM 03.01- Procedure for Contract Review CSD- 05.01- Documents Control CSD-03.01 - Procedure For Filling-In The (PIS/CIF); ZSM 14.01 Corrective/Preventive Action Requests PDB 14.01 Processing of Customers Claim; PR 14.07 Handling Claims; QCP 14.02 Investigation of Customers Claim by Manufacturing& QC ZSM06.01 Selection and Evaluation of Raw-Material Suppliers/ Sub-contractors ( Foreign/Local)

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 18 of 42

Title: Product Realization

Section 4.3
4.3 DESIGN AND DEVELOPMENT

4.3.1 Design and Development Planning A standard plan for each design and development activity shall be followed. This plan is shown in Engineering & Estimating Procedures Manual under Section 4.3.3. This plan shall be updated, when appropriate, as design and development progresses. Organizational & Technical Interfaces The CSD shall receive input from the Representative Office via a Project Information System (PIS) or Contract Information Form (CIF). The CSD shall review the PIS/CIF in accordance with the workflow procedure contained in Section 4 of Engineering & Estimating Procedure Manual. The receipt of the PIS/CIF shall be acknowledged by sending a schedule information message from the CSD. 4.3.2 Design Input

Design Engineers shall prepare design calculations and drawings according to the information contained in the PIS/CIF and the E & E Department Manuals. The Project Information System (PIS) or Contract Information Form (CIF) received from the CSD is the only source of input accepted by the E & E Department. Some supporting documents may be attached to the PIS/CIF to explain specific customer requirements. Any clarification required by the E & E Department shall be communicated to the CSD in writing. The E & E Department shall make revisions to the released designs based on a revised PIS/CIF form received from the CSD. 4.3.3 Design Output All design output documents shall be reviewed by an E & E Group Supervisors to make sure the design has been prepared in accordance with the latest PIS/CIF and the Standard Zamil Steel Procedures. The E & E Group Supervisors shall make sure that critical or crucial requirements are properly identified and considered in the design. The output of the E & E Department consists of design calculations, erection drawings, shop drawings and bill of materials. These are prepared in accordance with the procedures contained in the following manuals. E & E Procedures Manual This manual contains the E & E Department organization chart, Job description for each position, qualification requirements for each position, work flow procedures, reports and internal forms.

Designing Manual This manual contains guidelines and procedures for design calculations, material selection, codes requirements and specific requirements of certain major customers, end-users and approving authorities.

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 19 of 42

Title: Product Realization

Section 4.3

Detailing Manual This manual contains standard Zamil Steel detailing practices, detailing aid tables, manufacturing capabilities and limitations. Computer Aids Manual This manual contains instructional information for all the computer programs that are approved for use in the E& E Department.

4.3.4 Design and Development Review All design process shall at appropriate stages be reviewed by qualified and competent engineers involved in all phases of design of a building. The E & E Group Supervisors shall confirm that all design phases have been reviewed by entering a password protected computer record. An evidence of the same shall always be available on the archived design package for a particular job. 4.3.5 Design and Development Verification The E & E Group Supervisor shall confirm that design results are verified with historical cases of similarly designed buildings and by utilizing his past experience to make sure that the design is realistic. The Group Supervisor shall record his verification on the same computer record. 4.3.6 Design and Development Validation The Engineering Supervisors shall study the validity of the design for the defined use and issue a certificate for validation of the design, if required by the customer. 4.3.7 Design and Development Changes All revisions shall go through the same process as in a new design to make sure that they have been documented, reviewed and reflected accordingly on the detailed drawings, if necessary. The resulting revisions of drawings shall be controlled. If needed as per contract, the revised design package shall be sent to the customer for his records. Records All records of Design and Development Inputs, Design and Development reviews, Design and Development verification, Design and Development validation, Design and Development changes are maintained. 4.3.8 Design and Development Manuals Related Documents E& E Procedures Manual Designing Manual Detailing Manual Computer Aids Manual

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 20 of 42

Title: Product Realization

Section 4.4
4.4 PURCHASING 4.4.1

Purchasing Process The Purchasing Department is responsible for procuring all materials and services used in the fabrication and supply of Zamil Steel fabricated and supplied products in accordance with the purchase requisition. Refer to Procedure # ZSM 06.01. The evaluation and selection of a new Supplier shall be as per Procedure # ZSM 06.01. A list of approved suppliers with assigned supplier/vendor numbers shall be available at the Purchasing Department and the performance of approved suppliers shall be maintained regularly.

4.4.2

Purchasing Information The requisitioning departments are responsible for providing the relevant specifications in their purchase requisitions. The Purchasing Department shall process the Purchase Orders in accordance with the purchase requisitions. The Head of the Purchasing Department shall review the contents of the purchase orders before signing it. In case, there is a difference of any sort with reference to the purchase requisition, he will confirm that the purchasing staff has obtained written concurrence from the requisitioner. Verification of Purchased Product The QC Department shall inspect all incoming materials in accordance with the applicable procedures. These procedures recognizes the specifications stated in the ZS Purchase Order as the acceptance criteria and incorporates the control exercised at the vendors premises as part of the receiving inspection process, where applicable. Inspection report shall be made available to the Purchasing, Quality Control, Production & Material Control and Finance Department. Urgent Issue: In the event that incoming material is issued without a formal inspection the Production & Material Control shall keep an identification and traceability record for the positive recall of components manufactured from such materials in event that the identification of a significant non-conformance to the originally specified Purchase Order requires a recall of the material. Incoming Material QC Department shall inspect incoming raw materials in accordance with the specifications and special requirements stated in the Purchase Order. Nonconformance shall be reported as per Procedure # ZSM 13.01. The Non-

4.4.3

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 21 of 42

Title: Product Realization

Section 4.4

conforming material shall be pasted with a copy of NCR form or labeled with a sticker On Hold. Verification at Suppliers premises: When specified in the Purchase Order, Purchasing Department shall arrange for the raw material or the product to be inspected at the Vendors premises by a QC Inspector. The inspector shall confirm the quality through an Inspection Report prior to the shipment by the supplier. Customer verification of sub-contracted product: When specified in the Purchase Order, Zamil Steel shall arrange for the product to be inspected at the Vendors premises prior to shipment by a representative of the Customer. 4.4.4 Outsourcing The evaluation and selection of a sub-contractor to perform a part or the whole of design, fabrication and other services shall be arranged by the Purchasing Department in coordination with concerned department. A list of approved subcontractors shall be available at the Purchasing Department and the performance of approved sub-contractors shall be maintained regularly. Suppliers Suppliers information is one of information the analysis of data shall cover. Records Records of the results of evaluations and any necessary actions arising from the evaluation shall be maintained. Related Documents ZSM 06.01 Selection & Evaluation of Raw Material Suppliers (Foreign or Local); ZSM 10.01 Acceptance Procedure For Incoming Raw Materials; PR 06.01 Selection & Evaluation of Raw Material Suppliers; PR 06.03 Purchasing Data; PR 06.04 Expediting of Purchase Orders; PR 06.05 Shipping Documents; PR 06.06 Procurement of Equipment; PR 06.10 Local Purchasing Ordering System; MDB 06.01 Ordering Of Raw Materials; MDB 06.02 Ordering Of Buyout Items; MDB 06.03 Ordering Of Production Store Items (Paints, Reducers & Thinners); MDB06.04 Ordering Of Production Store Items; MDB06.05 Tracking Of Orders; CD 10.01 Checking of Material at Site; CD 16.02 Sub-Contracting Of Erection Work

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 22 of 42

Title: Product Realization

Section 4.5
4.5 PRODUCTION AND SERVICE PROVISION 4.5.1 Control of Production and Service Provision

The Production & Material Control Group of the Operations Department shall be responsible for the production scheduling of ZS manufacturing. The Production & Material Control Procedure defines the process whereby shop drawings and bills of materials (BOM) output from the Engineering Group within E& E Department is released to the shop, scheduled in conformance with contractual delivery requirements, and that Validation of Process for Production and Service Provision (i.e. non-standard Quality Plan requirements, special manufacturing requirements, and/or special inspection criteria) are identified and controlled. Production & Material Control shall monitor the production status of all released-for-production components and ensure that revisions to in-production Engineering output are promptly released to the affected manufacturing processes The Production & Material Control is responsible for all manufactured products. These products consist of built-up members, hot rolled members, cold-formed secondary framing members, roll formed roof, wall and liner panels, and sundry parts. These products are manufactured in accordance with the procedures (noted below) that identify the production machinery, processes, manpower skills, quality standards, tolerances and workmanship standards that are relevant to each particular product. o Built-up/Hot-rolled Main Frame Components The procedures outline the workflow, machines (with maintenance histories), in processing inspection criteria, job descriptions, and process validation inspection for all components manufactured from plates or from mill hot-rolled shapes. o Secondary Framing Members This procedure outlines the workflow, machines (with maintenance histories), in processing inspection criteria, job descriptions, and process validation inspection for all components either roll-formed or presses broken from hot rolled steel coil. o Roll-formed Sheeting and Trim This procedure outlines the workflow, machines (with maintenance histories) in processing inspection criteria, job descriptions, and process validation inspection for all components either roll-formed or press broken from hot-rolled cladding coils. Related Documents Departmental procedures and instructions;

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 23 of 42

Title: Product Realization

Section 4.5
4.5.2

Validation of Process for Production and Service Provision: Non-standard products and/or specific customer requirement may require the development of special manufacturing procedures. Zamil Steel shall develop such special process requirements and incorporate them within a job specific ITP. The special processes may include: o Non-standard Requirement: In the event that a particular joint required by design or in a specific contracted supply can not be performed using a standard Zamil Steel welding procedures, Operations and QC Departments shall develop a welding procedure which is either pre-qualified to AWS D1.1 or can be qualified under the conditions setforth by that standard. Welder qualifications relevant to such a non-standard welding procedure shall be carefully reviewed to ensure conformance with AWS guidelines. o Third Party Inspection All manufacturing procedures noted above comply with the Zamil Steel Quality System. In the event that a customer shall require third party inspection, Quality Control shall accompany the nominated inspector and coordinate, as necessary, with CSD Engineer to ensure compliance with all contractual terms.

4.5.3

Identification And Traceability o Product Identification The identification of Zamil Steel supplied products shall be clear and unambiguous to ensure that the product is used as intended. ZS always follows its own established product identification system as given in Procedure # ZSM 08.01. o Traceability The identification and maintenance of records enable Zamil Steel to maintain traceability of the material, design and test reports relating to the supplied products. Traceability shall be as per Procedure # ZSM 08.01 Zamil Steel Pre-Engineered Buildings are uniquely designed structures requiring job specific component manufacturing. No components enter production as general stock; all are entered for a specific contract. As such, All Zamil Steel work-in process is marked with and is traceable through a unique part mark/job number designation. All inspection is conducted against actual job marked components.

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 24 of 42

Title: Product Realization

Section 4.5
o

Status With Respect To Monitoring And Measurement Results.

The assigned inspector if a particular stage of manufacturing shall record his observations on an Inspection or Test Report. Additional Non-Destructive Tests Reports, if required, shall be attached. If no inspection sign or NCR appears on a component, it is considered to be conforming and released for further processing to the next stage. In case a non-conformance is observed during the manufacturing process, the defect of component will be marked and the corresponding NCR number will be mentioned on the component to highlight the need of an appropriate Corrective Action. The Inspection or Test Reports shall be reviewed by the QC Supervisor and by the Customers Representative, if contractually required. After the painting process if no NCR appears on a component, it will be considered as conforming and released for shipment. Related Documents Documents of Production Planning And Control Group; Documents of Quality Control Department; ZSM 08.01 Identification, Traceability Of Raw Materials & Finished Products; PDB 08.01 Traceability Record Of Fitters & Welders; QCP 08.01 Trace-Ability Of Plates; QCP 12.01 Inspection And Test Status 4.5.4 Customer Property Currently Zamil Steel does not receive any customer supplied materials, however received customer documents and information which are kept in confidence. In case the customer drawings, documents or specification contain ambiguous or conflicting provisions, Zamil Steel will discuss with client to resolve those provisions. Related documents: ZSM 03.01- Procedure for Contract Review CSD- 05.01- Documents Control CSD- 03.01 - Procedure For Filling-In The Project Information System (PIS) or Contract Information Form (CIF) 4.5.5 Preservation Of Product o Handling Products shall be handled by trained operators using cranes, forklifts, side loaders and trucks.

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 25 of 42

Title: Product Realization

Section 4.5
o Storage

Products shall be stored in designated stocking areas. Protection during storage shall be ensured. Steel members shall be separated by wooden sleepers and stacked according to shape and weight. Goods shall bear permanent identification marks. Care shall be taken to protect finished surfaces. Approved repair procedures shall be followed to rectify accidental handling damage. o Packaging Due to the nature of the product manufactured by Vietnam-PEB Division, materials are typically not packed prior to shipment. Zamil Steel standard practice is to loose load mainframe components; bundle cold form and sheeting; and crate trims, and buyout store materials. (Each bundle or crate shall bear a unique pack number with a detailed packing list, which clearly identifies the contents of the package traceable to BOM quantity/description). Care is taken in loading loose goods to ensure that handling and transit damage is minimized; likewise bundled and /or crated material are loaded in such a manners as to ensure that the package and contents are not subject to damage during transit. o Preservation PEB supply is protected by shop coatings, cover sheets, and/or crating to ensure that materials remain in prime condition both while in yard storage prior to shipment and for a reasonable period of time at the site prior to erection. Site storage guideline is provided to customers and end users to ensure that material are preserved in prime condition until erected/installed. These guidelines describe proper off-loading techniques, segregation of materials, storage suggestions, and advice regarding site security to guard against theft and/or accidental damage. o Delivery Product shall be delivered in accordance with Shipping & Logistics Department Procedures. Related documents: SD 15.01 - Loading & Reporting SD 15.02 - Back Orders & Back Orders Shipment SD 15.03 - Daily Shipping Schedule SD 15.05 - Back Orders & Back Orders Shipment MDB 15.01 - Receiving & Storage Of Materials MDB 15.02 - Issuance Of Raw Materials MDB 15.03 - Issuance Of Buyout Items MDB 15.04 - Issuance Of Production Store Item (Timber) MDB 15.05 - Issuance Of Production Store Items MDB 15.06 - Issuance Of Consumables Items

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 26 of 42

Title: Product Realization

Section 4.6
4.6 CONTROL OF MONITORING AND MEASURING DEVICES o

General The QC Department is responsible for identification, maintenance of procedures and calibration for all measuring and testing equipment. All instruments shall be frequently checked to ensure that these are within the calibration tolerance. Instruments shall be labeled with the date of last calibration and the signature of the calibrating inspector.

Training

Users of the instruments shall be trained to detect adverse trends in measurement results and action taken to investigate the possible causes. Record of calibration and maintenance of the testing equipment shall be kept by QC. o

Control Procedure Validity of previous results: Should any testing equipment be found out of tolerance during calibration, the QC shall review the measurement results and compare with the last calibration results. The validity of the previous results shall be assessed and action shall be taken to ensure that the products during the period in question comply fully with the contract requirements. Frequency of Calibration of individual tool/equipment shall be established depending on the usage and the nature of the measurements. It shall be stated in the list of equipment requiring calibration.

Calibration shall be carried out with reference to a standard, which shall be traceable to a national, or an international standard, as applicable.

Ultrasonic Testing Machine shall be calibrated as per Section 6.18 and 6.21 of AWS D1.1 (1998).

All calibration shall be carried out under the environmental conditions and procedures specified in the manufactures instructions.

Ultrasonic machine and paint thickness gauge shall be calibrated with the standard block and shims arranged for this purpose only. Calibration shall be done prior to perform each set of testing and the instrument is adjusted accordingly. No stickers are required to be pasted on each instrument. The instrument shall be sent for repair and calibration only if they show no response to the usual calibration procedure. Only a representative sample shall be checked for measuring tapes.

All reference test equipment shall be stored and handled properly to preserve the fitness and accuracy of the equipment.

Related documents: ZSM 11.01 - Control Of Measuring & Test Equipments

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 27 of 42

Title: Product Realization

Section 4.6

QCP 11.01 - Rockwell Hardness Tester (Eseway) QCP 11.02 - Procedure For 345-Digital Coating Thickness Gauge QCP 11.03 - Procedure For Measuring The Thickness Using Vernier Caliper QCP 11.04 - Procedure For Accurate Usage Of A Micrometer QCP 11.05 - The Usage Of Paint Adhesion Tester 'Elcometer' QCP 11.06 - Humidity Record (Thermo-Hygrometer)

QUALITY SYSTEM MANUAL

Revision # 5

Title: Measurement, Analysis, Improvement Date: 20.09.08

Section 5.1-5.2
5.1 GENERAL

Page 28 of 42

Zamil Steel plans and implements the monitoring, measurement, analysis and improvement processes needed

to demonstrate conformity of the product, to ensure conformity of the quality management system, and

To continually improve the effectiveness of the quality management system. This shall include determination of applicable methods, including statistical techniques, and the extent of their use (refer to Section 5.4 of this Quality System Manual). 5.2 5.2.1 MONITORING AND MEASUREMENT Customer Satisfaction As one of the measurements of the performance of the quality management system, Zamil Steel monitors information relating to customer perception as to whether the company has met customer requirements. Zamil Steel uses, as the case may from time to time be decided, such methods as questionnaire, telemarketing, customer direct contact or workshops for obtaining customer feedbacks. Analysis of Data Related Customer Satisfaction All customer feedbacks are analyzed and actions are taken for correction or improving Quality Management System effectiveness. Management Review Customer Feedback, as one of the input data, shall be analyzed and be included in the System Status Report prepared by Management Representative before management reviews. Related Documents: ZSM 14.01 Corrective/Preventive Action Requests PDB 14.01 Processing of Customers Claim; PR 14.07 Handling Claims; QCP 14.02 Investigation of Customers Claim by Operations & QC Department 5.2.2 Internal Audits o Responsibility

Management has appointed the Production Supervisor as the Lead Auditor to conduct Internal Quality Audits as per # ZSM 17.01. A qualified auditor working with other department shall audit QC Department. o Regular Audits

QUALITY SYSTEM MANUAL

Revision # 5

Title: Measurement, Analysis, Improvement Date: 20.09.08

Section 5.1-5.2

Page 29 of 42

An audit program shall be planned, taking into consideration the status and importance of the processes and areas to be audited, as well as the results of previous audits. The audit criteria, scope, frequency and methods shall be defined as per procedure Internal Quality Audits as per # ZSM 17.01. o Additional Audits

Management may require additional audits to verify implementation of new processes or to investigate identified deficiencies in the existing procedures/processes. o Corrective Action

Internal Audit findings shall be conveyed to the concerned Department Manager/Supervisor. In the event that a deficiency is identified, the department Manager/Supervisor shall take appropriate action within an agreed upon time schedule. o Follow-up of Corrective Action

Follow-up activities shall include the verification of the actions taken and the reporting of verification results. o Management Review

The Management Representative shall present a periodic report of the implementation status of the quality system within the Division. Records Records of internal audits are maintained. Related Documents ZSM 17.01- Internal Quality Audits 5.2.3 MONITORING AND MEASUREMENT OF PROCESSES o Monitoring And Measurement:

To demonstrate the ability of the quality management system processes to achieve planned results, Zamil Steel applies suitable methods for monitoring and, where applicable, measurement of processes. o Results (Data) Analysis of Processes Monitoring and Measurement

Respective Department Manager/ Supervisor and Management Representative analyze characteristics and trends of processes including opportunities for corrective/preventive actions.

QUALITY SYSTEM MANUAL

Revision # 5

Title: Measurement, Analysis, Improvement Date: 20.09.08

Section 5.1-5.2
o Management Review

Page 30 of 42

Process performance, as one of the input data, shall be analyzed and be included in the System Status Report prepared by Management Representative before management reviews. o Corrective Actions:

When planned results are not achieved, corrective action shall be taken, as appropriate, to ensure conformity of the product. 5.2.4 MONITORING AND MEASUREMENT OF PRODUCT o In-Process Inspection and Testing

The QC Department conducts two types of in-process inspections:

ZS Standard Quality Plan (Inspection & Test Program)

Steel components shall be inspected at a random basis at Dimensions, Welding and Painting stages of manufacturing. All measurement and testing shall be carried out to the extent stated in the Standard ITP.

Customers Approved Quality Plan

Any special inspection and testing requirements agreed by and approved by both the customer and Zamil Steel prior to actual production shall be followed. Any required inspection technique not available at ZS (e.g., destructive mechanical testing or radiography) shall be sub-contracted to a recognized independent testing agency.

Final Inspection & Release of Product Procedure

Documented process procedures included in-process inspection criteria at each manufacturing and finishing stage. The enforcement of these procedures is monitored by Zamil Steels Quality Control Department and as such ensures that the manufactured product conforms in all respects to the quality standards of this Quality System Manual. o Product release Unless otherwise contract permits, all actual final release of product is authorized only upon verification that the documented evidence of such inspection has been created and is available for examination. In case the contract permits, the final release of product is authorized by Quality Control Department, and by documented authorization from the customer. o Inspection and Test Records

QUALITY SYSTEM MANUAL

Revision # 5

Title: Measurement, Analysis, Improvement Date: 20.09.08

Section 5.1-5.2

Page 31 of 42

All product inspection reports shall be available at the QC. All non-conformance reports (NCR) issued (with the disposition action undertaken) shall be maintained with the inspection reports. o Analysis of Inspection results (Data) The conformity to product requirements, through the development of processes and working procedures take in the chance of preventive action. o Management Review

Product conformity, as one of the input data, shall be analyzed and be included in the System Status Report prepared by Management Representative before management reviews. Related documents QCP 10.01 - Inspection Of Hot Rolled Plates & Sections, Hot Rolled Black QCP 10.04 - Inspection Of Pre-Painted Sheet Coils QCP 10.06 - Visual/Dimensional Welding Inspection QCP 10.06 - Liquid Penetrate Examination QCP 10.07 - Magnetic Particle Testing QCP 10.08 - Ultrasonic Testing QCP 10.11 - Standard Painting Inspection QCP 10.14 - Final & Shipping Inspection QCP 10.18 - Checking The Weld Quality On Automatic Welding Machine QCP 10.26 - Dimensional Inspection QCP 10.40 - Specification, Codes & Tolerances For PEB QCP 10.41 - Procedure for Fabrication & Inspection of std. anchor bolts

QUALITY SYSTEM MANUAL

Revision # 5

Title: Measurement, Analysis, Improvement Date: 24.12.03

Section 5.3
5.3

Page 32 of 42

CONTROL OF NON-CONFORMING PRODUCT o General The PEB Division shall record all non-conformances on Incoming Materials, Drawings and Manufacturing Processes. o Fabrication Documents Engineering shall be responsible for checking the accuracy of all fabrication documents. o Goods in-Process QC Department shall inspect and monitor the goods in process through all stages of production. Non-conformance shall be reported as per Procedure # ZSM 13.01. o Review and disposition of the reported nonconformance The concerned department shall validate the NCR and define the process to resolve it. Disposition shall be reported. If required by the contract, the non-conforming product shall be reported for concession to the customer. The record of actual measurements shall be maintained. o The Management Representative shall analyze nonconformances and shall provide periodic reports for the review of the management. Records Records of the nature of nonconformities and any subsequent actions taken, including concessions obtained, shall be maintained. Related documents ZSM 13.01 Product Non-Conformities; PDB 10.01 Repairing of the Mis-Fabricated Steel Structures; PDB 13.01 Rectification Of The Pieces Pointed Out By QC; QCP 10.09 Control Of Non Conforming Processed Products QCP 10.16 Repairing of the Mis-Fabricated Steel Structures;

QUALITY SYSTEM MANUAL

Revision # 5

Title: Measurement, Analysis, Improvement Date: 20.09.08

Section 5.4
5.4 ANALYSIS OF DATA

Page 33 of 42

Zamil Steel determines, collects and analyses appropriate data to demonstrate the suitability and effectiveness of the quality management system and to evaluate where continual improvement of the effectiveness of the quality management system can be made. This shall include data generated as a result of monitoring and measurement and from other relevant sources. The analysis of data provides information relating to

Customer satisfaction; Conformity to product requirements;

Characteristics and trends of processes and products including opportunities for preventive action; and

Suppliers.

Statistical Techniques Identification of Needs Where applicable, Statistical Techniques shall be employed to verify product quality characteristics.

Procedures Customers complaints (claims) and in-process non-conformance reports shall be statistically analyzed. Resultant information shall be used to monitor the quality of the product.

5.5 IMPROVEMENT 5.5.1 Continual Improvement Zamil Steel continually improves the effectiveness of the quality management system through the use of the quality policy, quality objectives, audit results, analysis of data, corrective and preventive actions and management review. Management Representative shall prepare System Status Report and send to top management on the performance of the quality management system and any need for improvement before Management Reviews. 5.5.2 Corrective And Preventive Action o General Zamil Steel shall determine and take actions to eliminate the cause of:

Existing nonconformities in order to prevent their re-occurrence; and Potential nonconformities in order to prevent their occurrence.

QUALITY SYSTEM MANUAL

Revision # 5

Title: Measurement, Analysis, Improvement Date: 20.09.08

Section 5.4

Page 34 of 42

Corrective/preventive actions shall be appropriate to the effects of the potential problems. The PEB Division shall follow the Procedure # ZSM 14.01 for Corrective and Preventive Action Requests (CAR). The management undertakes to implement appropriate changes in the procedures. o Corrective /Preventive Action All customer complaints shall be recorded by the CSD. Immediate Corrective Actions shall be taken, if appropriate. Market feedback, other than complaints shall be referred to Marketing Department for consideration and preparing recommendation. During reviews, Management may decide on Corrective Actions to be undertaken by the concerned department or may refer such decision to the Marketing Department. Corrective Action to address in process non-conformances may be undertaken by the concerned department, resulting in revision of existing procedures or implementation of a new procedure. Corrective Action resulting from internal audits performed by the Management Representative or resulting from external audits shall be referred to management for consideration or implementation. Suggestion from within or outside Zamil Steel shall be referred to Marketing Department for consideration. Preventive Action Requests shall also follow the Procedure ZSM # 14.01.

o Review and verification Corrective/Preventive Action The results of corrective/preventive actions are reviewed and verified to ensure their effectiveness o Management Review

The status of Corrective and Preventive Actions shall be reviewed in the Management Meeting. Records Corrective/preventive actions are recorded as required by ZSM # 14.01. Related documents ZSM 14.01- Corrective/Preventive action Requests. PR 14.07 - Handling Claims. PDB 14.01 Processing of Customers Claim; QCP 14.02 Investigation of Customers Claim by Operations & QC Department

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 35 of 42

Title: Annex1

Organization chart

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 36 of 42

Title: Annex1

Organization chart

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 37 of 42

Title: Annex1

Organization chart

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 38 of 42

Title: Annex1

Organization chart

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 39 of 42

Title: Annex1

Organization chart

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 40 of 42

Title: Annex1

Organization chart

QUALITY SYSTEM MANUAL

Revision # 5 Date: 20.09.08 Page 41 of 42

Title: Annex1

Organization chart

QUALITY SYSTEM MANUAL

Title: Annex 2

Revision # 5 Date: 20.09.08 Page 42 of 42

Interaction of Processes