DEVIS AU GROS ŒUVRE D'UNE CHAMBRE DOUCHE

DESIGNATION UNITE QUANTITE PRIX UNITAIRPRIX TOTAL EN FCFA


FONDATION
Fouille m3 3.888 2,000 7,776
Remblai fouille m3 2.43 1,000 2,430
beton de proprete 150 Kg m3 0.81 60,000 48,600
mur en agglos 15 plein m2 9.72 14,800 143,856
Acier HA pour amost de poteaux kg 17.28 1,000 17,280
beton 350 Kg m3 0.144 90,000 12,960
coffrage m2 2.4 5,000 12,000
chainage bas -
coffrage m2 5.49 5,000 27,450
beton 350 Kg m3 0.549 80,000 43,920
Acier HA kg 54.9 1,000 54,900
Sous total fondation 371,172
ELEVATION
Dallage

2,500 26,735
Remblai par apport de terre
compactee m3 10.694
polyane m2 14.09 350 4,932
Beton dose 200 m3 1.409 70,000 98,630
Mur elevation agglo creux 15 m2 54 8,950 483,300
Poteaux -
Coffrage m2 6.72 5,000 33,600
Beton dose 350 m3 0.504 80,000 40,320
Acier HA Kg 60 1,000 60,000
Chainage haut -
coffrage 5.49 5,000 27,450
beton dose 350 Kg 0.549 90,000 49,410
Acier HA 54.9 1,000 54,900
Enduit mortier dose a 250 Kg m2 108 2,000 216,000
Sous total elevation 1,095,277
TRAVAUX DE REVETEMENT
carreaux en ciment 20 x 20 m2 0 12,500 -
plinthe 0 2,500 -
faiences
m2 0
8,000 -
sous total revetement
-
TRAVAUX DE PEINTURE
Brossage de ciment m2 0 500 -
Peinture a eau m2 0 1,555 -
Sous total peinture -
TRAVAUX DE COUVERTURE
Couverture en tole endulee m2 0 5,100 -
Faux plafond en contre plaquet 8 mmm2 0 12,000 -
Sous total couverture -
Total 1,466,449
Divers 15 % 146,645
Total general 1,613,093