AppendixF:ConstructionCostEstimate

Apreliminaryconstructioncostestimatewasdevelopedforthepreferredconceptualdesign.Payitems wereidentifiedandroughquantitytakeoffsweredeveloped.Unitcostswereassignedbasedon historicalcostdatafromtheDistrictofColumbia,DDOTandothersources.Itisassumedthateach phasewillbeaseparateconstructioncontract.Costsarebasedon2010dollarswitha20%contingency appliedtototalcostforeachphase.Theestimatedoesnotincludefurthercostsforengineeringdesign oracquisitionofanyrightofwayoreasements.Aspreviouslystatedtheestimatewasbrokenintothe anticipateddesignphases.Amoredetailedbreakdownofthecostestimateislocatedinthefollowing tables.

PhysicalImprovements10%ConceptDesignCostEstimatesSummary
Section 1stPlaceNE:RiggsRoadtoWMATAProperty WMATAProperty GallowayStreetNE:WMATAPropertytoSouthDakotaAvenue WayfindingSigns Total $760,000 $1,720,000 $440,000 $10,000

$2,930,000
Note: Thiscostestimateisaplanninglevelestimateonly. TheWMATAPropertySectioncouldincludeadditional$600kinoptionalplazaammenities (see'WMATAProperty'estimateformoredetails)

Vous aimerez peut-être aussi