LE CALCUL POUR LE PLANCHER DU RDC

330 A DIVISER PAR 8 CE QUI CORRESPOND A LA DURÉE DE RÉALISATION DES VOILES DU RDC

ENSUITE DIVISER PAR LE TEMPS EFFECTIF PAR JOUR DE 7,80 H

ON TROUVE 5,28 SOIT 5 OUVRIERS

VOIR TABLEAU CHARGE DE GRUE OU SATURATION DE GRUE

OBJECTIF = DETERMINER UNE DUREE DE CYCLE OPTIMISEE

CONCERNE : LE GO EN SUPERSTRUCTURE POUR DES SURFACES D’ETAGE D’AU MOINS 400


M2 ENVIRON

ON PREND EN COMPTE UN NIVEAU

SUR LA BASE DES SYSTEMES CONSTRUCTIFS ENVISAGES ON VA DETERMINER TOUTES LES


MANUTENTIONS A LA GRUE ASSOCIEES

ON ASSOCIE A CHAQUE MANUTENTION UN TEMPS DE CYCLE QUI EST SOUVENT EXPRIME EN


MINUTES CENTESIMALES (EXEMPLE : 7,50 MNS REPRESENTENT 7 MINUTES ET 30
SECONDES)

SE REFERER AU TABLEAU « EXEMPLE DE TABLEAU »

ON A DIFFÉRENCIÉ LES OUVRAGES : VOILES, POTEAUX, PLANCHERS, UN ATELIER DE


PRODUCTION EN PRÉFABRICATION, OUVRAGES DIVERS

POUR CHAQUE OUVRAGE ON PRÉCISE LES DIFFERENTES MANUTENTIONS

COLONNE 2 = DONNÉE DE LA DURÉE DU CYCLE

COLONNE 3 = DETRMINER LE NOMBRE DE CYCLES

COMMENT ? PRENONS LE CAS « DECOFFRER/COFFRER LES BANCHES »

IL FAUT LA DONNEE DU LINEAIRE DE VOILES

HYP : 662 ML POUR UN NIVEAU (C’EST UNE DONNEE QU’IL FAUDRAIT CALCULER)

ON DIVISE 662 PAR L’HYPOTHESE DE MANUTENTION

662 / 4,30 = 153,90 ARRODI A LA VALEUR ENTIERE SUPERIEURE

ON EN DEDUIT LE NOMBRE DE CYCLES


ON EN DEDUIT ENSUITE LA DUREE DE MANUTENTION PAR TACHE

ON PROCEDE DE MÊME POUR TOUTES LES TACHES RELATIVES AUX VOILES

ON FAIT ENSUITE LE TOTAL POUR L’OUVRAGE « VOILES » : 4934,50 MNS

CETTE OPERATION ON LA REPETE POUR TOUS LES OUVRAGES : ICI, POTEAUX,PLANCHERS, ET


DIVERS COMME PREFABRICATION OU MANUTENTIONS DIVERSES

ENSUITE ON FAIT LA SYNTHESE : FAIRE LA SOMME DE TOUTES LES DURÉES DONC TOTAL
POUR UN NIVEAU A SAVOIR 8365,20 MNS

CELA CORRESPOND A LA DURRE MINIMALE DU CYCLE

ON VEUT DETERMINER UNE DUREE EN JOURS COMME POUR L’EXERCICE PRECEDENT

ON DIVISE 8365,20 PAR 60 MNS CE QUI DONNE DES HEURES : 139,42 H DE GRUE

LA GRUE FONCTIONNE PAR EXEMPLE 8H PAR JOUR

ON DIVISE 139,42 PAR 8 ET ON OBTIENT 17,43 JOURS

C’EST OPTIMAL SI LA GRUE FONCTIONNE A 100 %

IL FAUT TENIR COMPTE DES ALEAS DE FONCTIONNEMENT DONC ON APPLIQUE UN


COEFFICIENT DE PONDERATION SUR LES 8 HEURES

ON APPLIQUE EN GENERAL UN COEFFICIENT ENTRE 0,70 ET 0,90 DONC EN MOYENNE 0,80

DONC LE NOUVEAU CALCUL DONNE : 139,42 A DIVISER PAR 8 X 0,80

21,78 SOIT 22 JOURS CE QUI CORRESPOND A LA DUREE DU CYCLE