Académique Documents
Professionnel Documents
Culture Documents
Power Division
Ministry of Power, Energy and Mineral Resources Government of Bangladesh
- Renewable Energy Project Investors will be exempted from corporate income tax for a period of 10 years. - Renewable Energy Equipment and raw materials will be exempted from charging 15% VAT An incentive tariff may be considered for electricity generated from renewable energy sources which may be 10% higher than the highest price of electricity purchased by the utility from private generators.
3
Full/ Partial Duty exemption: Solar Panel Solar Panel manufacturing equipment LED Light Solar Operated Light Wind Power Plant Promotional Funds for Renewable Energy Projects through: Bangladesh Bank IDCOL Commercial Banks
..(JUNE 11)
Category Solar Home System (SHS) Other Solar PV Applications (e.g. Markets, Office Buildings etc.) Roof-top Solar PV Systems of New Electricity Consumers Wind Energy Biomass based electricity Biogas based electricity Achievement 47 MW (1 Million Units) 1 MW 3 MW 2 MW 1 MW 1 MW
Total
55 MW
Grid Connected Solar PV 400 kW Power Plant 1 MW 3 MW 3 MW 5 MW Solar PV System Solar LED Street Light System. Solar Powered Irrigation Pump (each 14 kWp ) Solar Powered Irrigation Pump (each 8 kWp ) & SHS Solar-Wind Hybrid Power Plant 28 kW 225kW 280 kW 222 kW
1 MW
BPDB
Hatia Island
TOTAL (Est.) 35 MW
160 MW 500 MW
10
A. COMMERCIAL PROJECTS
Program 1 2 3 Solar Irrigation Pumps Solar Power Mini Grid System a) Solar Park at govt. land b) Solar Park at Railway Area 4 5 Solar Power in Private Commercial and Residential Buildings Solar Power in Industries Total Capacity (MW) 150 25 115 20 10 20 340
11
IDCOL
Grant & Credit Support Tech. Assist. Loan Repay. Water Tariff
Impl.
Water
O&M
Farmers Group
13
2. MINI GRID SOLAR POWER SYSTEM AT REMOTE VILLAGES UNDER RAPSS MODEL
- Guideline for Remote Area Power Supply System (RAPSS) was undertaken in 2007 - 30 remote Upazillas have been identified under RAPSS where grid expansion is not planned for next 10-15 years - New area identification under process Private RAPSS Operator as Area Franchise will be hired through Competitive Bidding
-
- Necessary Grant and credit support will be extended through IDCOL. - REB will supervise the project as well as, will provide tariff subsidy to the RAPSS Operator. - Total Solar Power Capacity Addition: 25 MW
14
Grant Grant
Power Cell
Selects operator Through bidding
RAPSS Fund
(under Power Division/Power cells control)
REB
Monitoring Tariff Subsidy
RAPSS Operator
[Equity Participation]
Loan Repay.
15
Primarily 4 potential sites have been identified , may have other location to be identified:
Sl. No. 1. 2. 3. 4. Location Rajabarihat, Rajshahi PGCB Grid Sub-station Compound, Ishwardi, Pabna Rajshahi (Char area at the river Padma) Adjacent area near Bangabandhu Bridge Land available 52 Acres 18 Acres 500 Acres 150 Acres Total Est. Gen. Capacity 15-20 MW 5-6 MW 150-160 MW 30-40 MW 200-226 MW
16
IMPLEMENTATION MODEL
BPDB
Selects PRG PCG
15 Yrs PPA
BPDB
17
Tariff
Guarantee Fee
- Solar PV Park may installed at those areas - Project may be implemented on IPP basis - Generated Power may be fed into the grid on commercial basis
-
- IPP Developer would have land lease agreement with Railway - Total Solar Power Capacity Addition: 20MW
18
2. 3. 4.
15 Yrs LLA
BPDB
RAILWAY
Selects Land Lease Fee
Technical Assist.
[Equity Participation]
Implementation Model
15 Yrs PPA
BPDB
20
Tariff
Loan Repayment
Technical Assistance
Tech. Support
Project Participant
23
24
B. Social Projects
25
Technical Assistance (Project dependent): Project Design Preparation of Standard Procurement and Contract Documents Detail Feasibility Study Capacity Building
Financial Support
Grant Support Low Interest Credit Support (For Capital Cost Buy down)
1. 2. 3.
4. 5.
Implementation Support Fiscal Incentives for Project Investors and Operators Import Duty Exemption (Full/ Partial) for certain technology and equipment Land Acquisition (Project Dependent) Institutional Support
28
29
Requires Institutional capacity building support both in public and private sector. Strong R&D support also needs to be facilitated Capacity development support for CDM project preparation An Integrated Capacity Development Project may include all those essentials Setting up institution for the Standardization of equipment
31
WAY FORWARD
This initiative would be considered as a landmark success story for the govt. Its success will be rest upon the govt. development partners and the private entrepreneurs initiatives by working together very closely. Development partners support will be very much needed to go for this programme. It would be a model for other developing countries who envisage making a mass breakthrough in solar power development.
32