CATALOG OF LABOR CONCEPTS AND PERFORMANCES

CODE COMPLETE DESCRIPTION UNIT QUANTITY PERFORMANCE


CLEAN LAYOUT AND LEVELING OF THE LAND, CONSIDERING ONLY THE
CONSTRUCTION AREA, INCLUDES: MATERIALS, LABOR, TOOLS AND
1 NECESSARY EQUIPMENT. M2 685.00 300 M2/JOR

HAND EXCAVATION IN SOIL TYPE "B" UP TO 2 METERS DEEP. INCLUDES


SHARPENING, SLOPES AND OFF-SITE HAULING OF UNUSABLE MATERIAL.
2 M3 350.00 4 M3/JOR

CONCRETE F'C= 250 kg/CM2, IN FOUNDATION, INCLUDING: MATERIALS,


LABOR, TOOLS, EQUIPMENT AND EVERYTHING NECESSARY FOR ITS
3 CORRECT EXECUTION. M3 125.00 3 M3/JOR

4 CONCRETE TEMPLATE MADE ON SITE F'C= 100 KG/CM2. THICKNESS OF 7 M2 110.00 14 M2/JOR
CM. INCLUDES: MATERIALS, LABOR, TOOLING AND EQUIPMENT
SUPPLY AND BACKFILL OF BANK PRODUCT MATERIAL, COMPACTED WITH
TAMPING AND WATER, IN LAYERS OF 15 CM. THICKNESS, INCL. HAULING
5 WITHIN THE CONSTRUCTION SITE, MEASURING COMPACTED. M3 85.00 5 M3/JOR

SHORING FOR FOUNDATION WITH 16 MM PINE PLYWOOD AND 3RD GRADE


PINE WOOD. APPARENT FINISH ON COUNTERBRACES AND DADOES.
6 M2 115.00 10 M2/JOR
INCLUDES FORMWORK AND FALSEWORK.

STEEL FOR FOUNDATION REINFORCEMENT, WITH No.3 ROD, F'Y = 4200


KG/CM2. INCLUDES: SUPPLY, INSTALLATION, ASSEMBLY. OVERLAPS,
7 SADDLES, HOOKS AND WASTE. KG 683.00 150 KG/JOR

CONCRETE COLUMN F'C=250 KG/CM2 25 X 20 CM. REINFORCED WITH 4


VAR.#4 AND 2 VAR.#3 STIRRUPS#2 @ 20 CM. INCLUDES: ASSEMBLY,
8 FORMWORK, FORMWORK REMOVAL, POURING, MATERIALS, TOOLS AND ML 68.00 4 ML/JOR
LABOR.

WALL BASED ON COMMON RED PARTITION WALL OF 7 X 14 X 28 CM. 1:3


CEMENT-SAND MORTAR, COMMON FINISH. INCLUDES: MATERIALS, TOOLS
9 AND LABOR. M2 145.00 12 M2/JOR

PLASTERING OF WALLS WITH CEMENT-SAND MORTAR 1:4, 1.50 CM THICK,


FINISHED WITH PLUMB AND SCREED. INCLUDES: MATERIALS, TOOLS AND
10 M2 290.00 14 M2/JOR
LABOR.

CONCRETE FLOOR MADE ON SITE F'C=150 KG/CM2 OF 10 CM THICK.


REINFORCED WITH 10-10/6-6 ELECTROWELDED MESH.
11 INCLUDES: MATERIALS AND LABOR.
M2 550.00 11 M2/JOR

VINYL PAINT FOR INTERIORS AND EXTERIORS COMEX VINIMEX 756 SATIN-
MATTE IN WHITE SUNRISE COLOR, TWO COATS ON A LAYER OF SEALER,
INCLUDES MATERIALS, LABOR, TOOLS, EQUIPMENT AND EVERYTHING
12 M2 290.00 35 M2/JOR
NECESSARY FOR ITS GOOD EXECUTION.

WATERPROOFING IN CONCRETE SLABS BASED ON A LAYER OF COMEX


BRAND MOLE PRIMER AND THEN A PREFABRICATED WATERPROOFING
MEMBRANE OF 3.5 MM SBS GRANULATED MOLE ROLL. TERRACOTTA
COLOR, APPLIED WITH A BUTANE GAS TORCH. INCLUDES: MATERIALS,
13 LABOR, TOOLS, EQUIPMENT AND EVERYTHING NECESSARY FOR ITS M2 685.00 25 M2/JOR
CORRECT EXECUTION.

45x45 CM. FLOORING TILES, GLUED WITH 1:3 SAND CEMENT MORTAR,
JOINTED WITH WHITE GROUT. INCLUDES: LAYOUT, CUTS, WASTE, TOOLS,
14 MATERIALS, EQUIPMENT AND LABOR. M2 550.00 8 M2/JOR
QUADRILLA

1 MASON OFFICIAL + 1
ASSISTANT

0.5 JOURNEYMAN + 2 LABORERS

1 JOURNEYMAN + 4 LABORERS

1 JOURNEYMAN + 2 LABORERS

0.5 JOURNEYMAN + 2 LABORERS

1 JOURNEYMAN + 1 LABORER

1 JOURNEYMAN + 1 LABORER

1 JOURNEYMAN + 1 LABORER

1 JOURNEYMAN + 1 LABORER

1 JOURNEYMAN + 1 LABORER

1 JOURNEYMAN + 1 LABORER

1 JOURNEYMAN + 1 LABORER

1 JOURNEYMAN + 1 LABORER

1 JOURNEYMAN + 1 LABORER
BASIC CONCRETE F'C
MATERIAL 100 150 200 250 300

CEMENT 0.273 0.339 0.373 0.445 0.482


ARENA 0.5 0.48 0.47 0.465 0.46

GRAVA 0.68 0.67 0.65 0.64 0.63


WATER 0.205 0.22 0.205 0.2 0.236

MORTAR
MATERIAL 1:3 1:4 1:5

CEMENT 0.51 0.43 0.36


ARENA 1.1 1.12 1.15
WATER 0.272 0.266 0.261
MORTAR
MATERIAL 1:3 1:4 1:5

CEMENT 0.51 0.43 0.36


ARENA 1.1 1.12 1.15
WATER 0.272 0.266 0.261
STAIRS HEIGHT REQUIRED DISTANCE 3%
1 0.18 6
2 0.36 12
3 0.54 18
4 0.72 24
5 0.9 30
6 1.08 36
7 1.26 42
8 1.44 48
9 1.62 54
10 1.8 60