4 CONCRETE TEMPLATE MADE ON SITE F'C= 100 KG/CM2. THICKNESS OF 7 M2 110.00 14 M2/JOR
CM. INCLUDES: MATERIALS, LABOR, TOOLING AND EQUIPMENT
SUPPLY AND BACKFILL OF BANK PRODUCT MATERIAL, COMPACTED WITH
TAMPING AND WATER, IN LAYERS OF 15 CM. THICKNESS, INCL. HAULING
5 WITHIN THE CONSTRUCTION SITE, MEASURING COMPACTED. M3 85.00 5 M3/JOR
VINYL PAINT FOR INTERIORS AND EXTERIORS COMEX VINIMEX 756 SATIN-
MATTE IN WHITE SUNRISE COLOR, TWO COATS ON A LAYER OF SEALER,
INCLUDES MATERIALS, LABOR, TOOLS, EQUIPMENT AND EVERYTHING
12 M2 290.00 35 M2/JOR
NECESSARY FOR ITS GOOD EXECUTION.
45x45 CM. FLOORING TILES, GLUED WITH 1:3 SAND CEMENT MORTAR,
JOINTED WITH WHITE GROUT. INCLUDES: LAYOUT, CUTS, WASTE, TOOLS,
14 MATERIALS, EQUIPMENT AND LABOR. M2 550.00 8 M2/JOR
QUADRILLA
1 MASON OFFICIAL + 1
ASSISTANT
1 JOURNEYMAN + 4 LABORERS
1 JOURNEYMAN + 2 LABORERS
1 JOURNEYMAN + 1 LABORER
1 JOURNEYMAN + 1 LABORER
1 JOURNEYMAN + 1 LABORER
1 JOURNEYMAN + 1 LABORER
1 JOURNEYMAN + 1 LABORER
1 JOURNEYMAN + 1 LABORER
1 JOURNEYMAN + 1 LABORER
1 JOURNEYMAN + 1 LABORER
1 JOURNEYMAN + 1 LABORER
BASIC CONCRETE F'C
MATERIAL 100 150 200 250 300
MORTAR
MATERIAL 1:3 1:4 1:5