Vous êtes sur la page 1sur 32

Highway Construction

The Road Construction Process


The type of road construction used varies from one job to another. The type of construction adopted for a particular road depends on: the volume and nature of traffic to use the road, the nature of the materials available, , the topography, foundation conditions, type and availability of construction equipment, and financing arrangements and timing.

The Road Construction Process


Any road construction job consists of number of basic steps steps, although the relevant importance and the interaction between these steps will vary from job to job. These steps can be summarized as: planning, programming and pre-construction activities; site clearance; setting out; tti t earthworks; bridge construction; drainage structures; pavement construction; placement of road surfacing; placement of road furniture; and landscaping.

Earthworks
The eventual aim of the earthworks phase of the construction is to position the subgrade underlying the pavement layers in the right location and at the correct level, and to p g , provide drainage. g The operations to be performed are: formation of cuttings by excavating through high ground, formation of embankments by filling over low ground ground, shaping the finished surface to design levels, and excavating for drainage works. The Th earthworks i often th l th k is ft the largest t k i th road b ildi t task in the d building process and therefore careful planning and organisation are essential. Speed and efficiency depend very much upon the quantity and types of earthmoving plant available available.

Sequence of Operations
The normal sequence of operations in cut and fill work is: In Cut excavate to the depth necessary to reach formation level, transport away from the site undesirable material such as organic soils, haul suitable materials from cuts to fill areas, and , suitably dispose of any excess cut material. In Fill drain water from depressions and dispose of any unsuitable p p y underlying material, spread fill material in horizontal layers not more than 250 mm thick, and thoroughly compact these layers to required density.

NED roadwork-11 Aug 2009 roadwork 11

Subgrade prepared

Base course materials stacked

40

Pavement Construction
Gravel and Crushed Rock Pavements Source: pits quarries pits,quarries. Haulage: trucks. Spreading: grader or paver. Compaction: higher compaction standard than subgrade; different roller types used. Accuracy of levels important. Asphalt Pavements Manufacture: fixed plants (up to 400 tonnes per hour), or large mobile plants. Haulage: trucks. Placement: paving machine. Compaction: rollers - smooth vibrating drum and pneumatic pneumatictyred. Usually final layer thin to achieve good riding surface.

Pavement Construction
Cement Concrete Pavements Manufacture: ready-mixed batching plant plant. Haulage: agitator truck. Large quantities: site manufacture + normal trucks. Placement: slip-form paver. Compaction: internal vibrators + external screeds.

Placement of Road Surfacing


May be gravel, sprayed bituminous seal, asphalt or cement concrete. Construction of Sprayed Bituminous Surfacing Pavement must be sound. For new work: compaction and trimming of underlying gravel or crushed rock pavement. For existing bituminous surface: patching. Steps: Sweep surface - drawn rotary broom + hand sweeping. sweeping Prepare binder - transport to job by road or rail tanker, or in drums. Flux and/or cutback binder. Incorporate adhesion agent. Prepare aggregate - stockpiles precoating stockpiles,

Spray binder - air temperature should be > 15 C; no rain should be threatening; mark out spray run runalignment and start and finish. Apply aggregate - quick incorporation into hot bitumen before e cessi e cooling; sp eade s eq i ed drag befo e excessive cooling spreaders required; d ag broom to correct spreading inconsistencies. Roll surface - to bed stone; pneumatic-tyred or static steel drum rollers. Drag broom Record work - quantities bitumen sprayed, aggregate sprayed spread, etc. Traffic control - throughout steps 1 to 10; minimise traffic d l t ffi delays.

Construction of HMA Road C t ti f R d

Sweeping is usually carried out with drawn mechanical brooms, although some hand sweeping is often required as well. ll

It is found that a prime or seal will adhere better to an underlying gravel pavement if the pavement is slightly damp. g y p

Transport of bitumen to the job site will usually be by rail tanker or road tanker.

The mix falls through a series of inclined vibrating screens and the various size fractions are stored i h t storage bins. f ti t d in hot t bi The plant operator then weighs out the correct proportions of each size for a single batch. The sizes are mixed and then the required amount of hot bitumen q is added and mixing continued. The batch is then discharged from the mixer into a waiting truck, and the batching process repeated.

In the Brisbane plant, the batches of hot mix are stored in insulated storage g bins, and this means that arriving trucks can be filled more rapidly.

Asphalt Paving Paving.


This is a view of the front of a typical t i l self-propelled, floating screed, paving machine. Tip trucks discharge the p g hot asphalt into the front hopper and it is then conveyed to the rear of the machine by a chain and slat conveyor. This picture shows a truck with its tray tipped, discharging mix into the paver. paver The operator sits on top and steers the machine to the required alignment.

Asphalt Paving.
The screed unit consists of levelling arms, a screed plate which vibrates to act as a tamper, and thickness controls. It is supported by the mix which gives it a floating action. A long moving reference beam, beam mounted on shoes (or skis) can be used to ensure the screed follows a smooth line regardless of irregularities in the surface being paved.

Construction of RCC Road

Construction of RCC Road

Construction of RCC Road

Placement of dowels and tie bars

Dowel bars Do el ba s location

PCC thickness

Roofing paper

Roofing paper-1

Tie bars

Dowel b k t D l basket

Placement of reinforcement

Dowels images

Forms, Forms Steel form


Figure 7.113: Steel Forms

Wooden Form

Removal of Form

Vibrator

Vous aimerez peut-être aussi