Vous êtes sur la page 1sur 55

GROUND IMPROVEMENT WORKSHOP 11-12 JUNE 2010 PERTH, AUSTRALIA

INTRODUCTION TO SOIL , , IMPROVEMENT, PARAMETERS, CLASSIFICATION, CASE HISTORY OF KAUST


Presented by

Serge VARAKSIN
CHAIRMAN OF T.C. Ground Improvement

State of the Art Report

17TH International Conference on Soil Mechanics & Geotechnical Engineering

State of the Art Report


Construction Processes Procds de Construction
Jian Chu
Nanyang Technological University, Singapore

Serge Varaksin
Menard, France

Ulrich Klotz
Zublin International GmbH, Germany

Patrick Meng
Dredging International n.v., DEME, Belgium

Alexandria, Egypt 5-9 October 2009

NOTA : TC 17 meeting ground improvement 07/10/2009 Website : www.bbri.be/go/tc17

PERTH - AUSTRALIA June 2010

Category A. A Ground improvement without admixtures in non-cohesive soils or fill materials

Method A1. Dynamic compaction A2. Vibrocompaction A3. Explosive compaction A4. Electric pulse compaction A5. Surface compaction (including rapid impact compaction). B1. Replacement/displacement (including load reduction using light weight materials) B2. Preloading using fill (including the use of vertical drains) B3. Preloading using vacuum (including combined fill and vacuum) B4. Dynamic co so da o with e a ced y a c consolidation enhanced drainage (including the use of vacuum) B5. Electro-osmosis or electro-kinetic consolidation B6. Thermal stabilisation using heating or freezing B7. Hydro-blasting compaction

B. Ground improvement without admixtures in cohesive soils

Principle Densification of granular soil by dropping a heavy weight from air onto ground. Densification of granular soil using a vibratory probe inserted into ground. Shock waves and vibrations are generated by blasting to cause granular soil ground to settle through liquefaction or compaction. Densification of granular soil using the shock waves and energy generated by electric pulse under ultra-high voltage. Compaction of fill or ground at the surface or shallow depth using a variety of compaction machines. Remove bad soil by excavation or displacement and replace it by good soil or rocks. Some light weight materials may be used as backfill to reduce the load or earth p pressure. Fill is applied and removed to pre-consolidate compressible soil so that its compressibility will be much reduced when future loads are applied. Vacuum pressure of up to 90 kPa is used to pre-consolidate compressible soil so that its compressibility will be much reduced when future loads are applied. S a o dy a c compaction except e ca or o o a drains (or oge e Similar to dynamic co pac o e cep vertical o horizontal d a s (o together with vacuum) are used to dissipate pore pressures generated in soil during compaction. DC current causes water in soil or solutions to flow from anodes to cathodes which are installed in soil. Change the physical or mechanical properties of soil permanently or temporarily by heating or freezing the soil. Collapsible soil (loess) is compacted by a combined wetting and deep explosion action along a borehole.

PERTH - AUSTRALIA June 2010

C1. Vibro replacement or stone columns C. Ground improvement with admixtures or inclusions C2. Dynamic replacement C3. Sand compaction piles C4. Geotextile confined columns C5. Rigid inclusions (or composite foundation, also see Table 5) C6. Geosynthetic reinforced column or pile supported embankment C7. Microbial methods C8 Other methods

Hole jetted into soft, fine-grained soil and back filled with densely compacted gravel or sand to form columns. Aggregates are driven into soil by high energy dynamic impact to form columns. The backfill can be either sand, gravel, stones or demolition debris. Sand is fed into ground through a casing pipe and compacted by either vibration, dynamic impact, or static excitation to form columns. y p , Sand is fed into a closed bottom geotextile lined cylindrical hole to form a column. Use of piles, rigid or semi-rigid bodies or columns which are either premade or formed in-situ to strengthen soft ground. Use of piles, rigid or semi-rigid columns/inclusions and geosynthetic girds to enhance the stability and reduce the settlement of embankments. Use of microbial materials to modify soil to increase its strength or reduce its permeability. Unconventional methods, such as formation of sand piles using blasting and the use of bamboo, timber and other natural products.

PERTH - AUSTRALIA June 2010

D. Ground improvement with grouting type admixtures

D2. Chemical grouting D3. Mixing methods (including premixing or deep mixing) D4. Jet grouting D5. Compaction grouting D6. Compensation grouting E1. Geosynthetics or mechanically stabilised earth (MSE) E2. Ground anchors or soil nails E3. Biological methods using vegetation

E. Earth reinforcement

g Solutions of two or more chemicals react in soil pores to form a gel or a solid precipitate to either increase the strength or reduce the permeability of soil or ground. Treat the weak soil by mixing it with cement, lime, or other binders in-situ using a mixing machine or before placement High speed jets at depth erode the soil and inject grout to form columns or panels Very stiff, mortar-like grout is injected into discrete soil zones and remains in a homogenous mass so as to densify loose soil or lift settled ground. Medium to high viscosity particulate suspensions is injected into the ground between a subsurface excavation and a structure in order to negate or reduce settlement of the structure due to ongoing excavation excavation. Use of the tensile strength of various steel or geosynthetic materials to enhance the shear strength of soil and stability of roads, foundations, embankments, slopes, or retaining walls. Use of the tensile strength of embedded nails or anchors to enhance the stability of slopes or retaining walls walls. Use of the roots of vegetation for stability of slopes.

PERTH - AUSTRALIA June 2010

Unified Soil Classification System

PERTH - AUSTRALIA June 2010

Unified Soil Classification

PERTH - AUSTRALIA June 2010

Sampling methods

2.1 UD: 2 or 3 Shelby Tube Suitable for cohesive soils 2.2 Piston sampler Osterberg Suitable for cohesive and fine granular soils 2.3 SPT: suitable for cohesive and granular Soil 2.4 Core barrel Suitable for rock type of soils 2.5 Block sample UNDISTURBED UNDISTURBED UNDISTURBED

REPRESENTATIVE SAMPLE

REPRESENTATIVE SAMPLE

PERTH - AUSTRALIA June 2010

Soil Identification

Define terms important for Unified Soil Classification System


Percent Fines e ce es Mechanical Analysis Liquid Limit Plastic Limit, Plasticity Index Water Content Organic

PERTH - AUSTRALIA June 2010

Laboratory Engineering Properties

PERTH - AUSTRALIA June 2010

10

Laboratory Engineering Properties Direct shear test (imposed failure plane) ,

PERTH - AUSTRALIA June 2010

11

Laboratory Engineering Properties Triaxial on cohesionless soil , Mohr Coulomb curve

PERTH - AUSTRALIA June 2010

12

Laboratory Engineering Properties W, W Co, Ce, Cv, Pc, k Av, C k,

Consolidation test

Frame with consolidation units


13

PERTH - AUSTRALIA June 2010

Laboratory Engineering Properties Proctor Test w, wcpt, max, Proctor curve

PERTH - AUSTRALIA June 2010

14

Different types of In Situ tests

Vane test (VT)

Static Cone Penetration Test (CPT)

Standard Penetration Test (SPT)

Pressuremeter (PMT)

PERTH - AUSTRALIA June 2010

15

Laboratory Engineering Properties Why Soil Improvement ? g p y y (avoid failure) ) To increase bearing capacity and stability ( To reduce post construction settlements To reduce liquefaction risk (seismic areas) Advantages over classical solutions Avoid deep foundation (price reduction also on structure work like slab on pile) Avoid soil replacement p Save time Avoid Avoid to change site Save money !

PERTH - AUSTRALIA June 2010

16

Soil Improvement Techniques


Without added materials Cohesive soil
Peat , clay

1D i Drainage 2 Vacuum

With added materials 4 Dynamic replacement 5 Stone columns 6 CMC 7 Jet Grouting 8 Cement Mixing

Soil with ith friction


Sand , fill

3 Dynamic consolidation 4 Vibroflottation

PERTH - AUSTRALIA June 2010

17

Parameters For Concept

Soil characteristics -Cohesive or non cohesive - Blocks? Water content water table position content, Organic materials Soil thickness Structure to support -Isolated or uniform load -Deformability y

Site environment -Close to existing structures -Height constraints Available construction time

PERTH - AUSTRALIA June 2010

18

Paramaters for Concept

CONCEPT
FILL SBCz GWT 2 4 6 8 1 0 1 2 FILL Depth (m) 30% SB z 80 % 50 % z FILL Depth (m) t (about 10 years) 1 2 3 4 S (%) 50% (SBC) 30% (SBC) 90% (SBC) 80% (SBC) 60% (SBC) FILL Depth (m) FILL+UNIFORM LOAD FILL+ LOAD SBCz GWT SBCz GWT

PARAMETERS
- Age if fill saturated or not -PL -Selfbearing level -, EP or EM -QC, FR -N N -R.D. (???) -Shear wave velocity -Seismic parameters -Grain size G i i

DC : h(m) = C

C(menard) = 0.9-1 C(hydraulic) 0.55 C(h d li ) = 0 55

SBC LOAD

= 0.9-1 (SILICA SAND) = 0.4-0.6 (SILICA SAND)

S.B.C. = Self Bearing Coefficient S.B.C. S B C = S(t) S( )

PERTH - AUSTRALIA June 2010

19

Case History
Nice International Airport Runway consolidation p y Granular soil

Very high energy (170 t 23 m) t,


PERTH - AUSTRALIA June 2010
20

KAUST PROJECT

Concept and Application of 2,600,000 m of ground improvement for King Abdulla University of Science & Technology (KAUST)

PERTH - AUSTRALIA June 2010

21

localisation

PERTH - AUSTRALIA June 2010

22

Master Plan

PERTH - AUSTRALIA June 2010

23

Original site Conditions

PERTH - AUSTRALIA June 2010

24

Jeddah, a modern city

PERTH - AUSTRALIA June 2010

25

Discovering the Habitants

PERTH - AUSTRALIA June 2010

26

Areas to be treated

Areas to be treated Al Khodari (1,800,000 m2 ( , , Saudi Bin Ladin 720,000 m2

Schedule 8 months

PERTH - AUSTRALIA June 2010

27

Dates for soil improvement

KAUST Dates for soil improvement

PERTH - AUSTRALIA June 2010

28

Dynamic Consolidation

Wave Type Rayleigh Shear Compression

Percent of Total Energy 67 26 7

After R.D. Woods (1968)

PERTH - AUSTRALIA June 2010

29

Specifications

Isolated f I l d footings up to 150 tons i 1 0 Bearing Bearing capacity 200 kPa Maximum footing settlement 25 mm Maximum differential settlement 1/500 Footing location unknown at works stage

PERTH - AUSTRALIA June 2010

30

Concept 150 TONS Depth of footing = 0.8m Below G L G.L. Engineered fill + 4.0 z = 200 kN/m / 2 meters arching layer + 2.5 Working platform (gravelly sand) + 1.2 Compressible layer from loose sand t very soft sabkah d to ft bk h 0 to 9 meters

PERTH - AUSTRALIA June 2010

31

Decision process of selection of technique

Presence of Silt (Sabkha) layer

No

Yes

No Deep silt (Sabkha) layer, ie bottom elevation higher than 5 m below Working Platform Level

Deep silt (Sabkha) layer, ie bottom elevation lower than 5 m below Working Platform Level

Transition layer > 2 m

Transition layer < 2 m

Case A

Case B1

Case B2 Sabkha Substitution over 1 m + DR

Case B3 HDR + temporary surcharge

DC

DR

PERTH - AUSTRALIA June 2010

32

Selection of technique

0,80

Preloading

FPL

DR (Dynamic Replacement) HDR (High Energy Dynamic y Replacement) + Surcharge

De esign

> 2,80

WPL Working Platform NGL GWT

Soil Conditio ons

> 4,50

BSL (variable)

PERTH - AUSTRALIA June 2010

33

PMT compared with loading of column


PMT loading test applies the cavity expansion theory which is similar to granular column bulging under applied vertical load.

PM MT

sc q ult,sc = tan 2 + PL 2 4 direct measurement of PL

Pressure induced to fail the surrounding soil = g p y pp y ultimate bearing capacity of column supported by lateral pressure of the surrounding soil.
PERTH - AUSTRALIA June 2010
34

Typical Site Cross Section of Upper Deposit

PERTH - AUSTRALIA June 2010

35

Variation in soil profile over 30 meters

PERTH - AUSTRALIA June 2010

36

Typical soil profile


Lim Pressure it
0 3.0 5 1 0 1 5 20 25 30

Pressurem eter Modulus

Cone Resistance

0 3.0

40

80 120 160 200 240


3.0 2.5 2.0 1.5

8 10 12 14

2.0

2.0
7.5

64.9 1.0

1.0 0.5 0.0 00 -0.5 -1.0

1 .0

2.8
0.0

36.0 0.0
Elevation (m E m
Elevation (m E m

Elevation (m E

1.0
-1 .0

9.8 -1 0 1.0 3.8 -2.0 61.5

-1.5 -2.0 -2 0 -2.5 -3.0 -3.5 -4.0 -4.5 -5.0 -5.5 -6.0 -6.5

0.9
-2.0

2.2
-3.0

-3.0 22.9

3.2
-4.0

-4.0

-5.0

-7.0 -7.5 -8.0


Ep (bar)
qc (Mpa)

-5.0

-6.0
Pl (b ) (bar)

PERTH - AUSTRALIA June 2010

37

Human Resources

1. Project 1 P j t management (4) t 2. Production team (32) 3. Mechanical team (18) 4. 4 Survey team (16) 5. Administrative team (6) 6. G 6 Geotechnical team (8) h i l 7. Safety and Quality (2) 8. Logistic team (4)

PERTH - AUSTRALIA June 2010

38

Typical surface conditions

PERTH - AUSTRALIA June 2010

39

Typical test pits (120) and grain size

PERTH - AUSTRALIA June 2010

40

PERTH - AUSTRALIA June 2010

41

Equipment Resources
13 DC/DR Rigs of 95 to 120 tons g 15 pounders from 12-23 tons 30 vehicles (bus, 4x4, pick-up, berlines) 1 truck with crane 1 forklift 3 CPT rigs 1 drill + pressuremeter 15 containers 1 set of site offices

PERTH - AUSTRALIA June 2010

42

Equipment Resources
13 DC/DR Rigs of 95 to 120 tons g 15 pounders from 12-23 tons 30 vehicles (bus, 4x4, pick-up, berlines) 1 truck with crane 1 forklift 3 CPT rigs 1 drill + pressuremeter 15 containers 1 set of site offices

PERTH - AUSTRALIA June 2010

43

Equipment Resources
13 DC/DR Rigs of 95 to 120 tons g 15 pounders from 12-23 tons 30 vehicles (bus, 4x4, pick-up, berlines) 1 truck with crane 1 forklift 3 CPT rigs 1 drill + pressuremeter 15 containers 1 set of site offices

PERTH - AUSTRALIA June 2010

44

PMT results before DC


Before DC
Limit Pressure

0 3

10

15

20

25

30

Elevation (m EL)

-1

-2

-3

4 -4

-5

-6

-7

-8

Minimum

Pl (bar)

Average

PERTH - AUSTRALIA June 2010

45

PMT results before and after DR


Before DR
Limit Pressure
0 3.0 5 10 15 20 25 30 3.0 0 5

After DR Between columns


Limit Pressure
10 15 20 25 30

2.0

2.0

7.5
1.0 10 1.0 10

23.4

2.8
0.0 0.0

4.3

15,2

1.0

1.9

18,0

Elevation (m EL) E

-1.0

0.9 09
-2.0

Elevation (m EL) E

-1.0

3.3 33
-2.0

16,7 16 7

2.2
-3.0

5.8
-3.0

14,1

3.2
40 -4.0

3.4
-4.0

8,2

9.2
-5.0 -5.0

12,2

-6.0

-6.0

-7.0

-7.0

-8.0

-8.0

Pl (bar) Between columns

Pl (bar) Inside columns

PERTH - AUSTRALIA June 2010

46

Analysis of improvement
ANALYSIS OF (PL-Po) IMPROVEMENT AS FUNCTION OF ENERGY AND FINES P
KAUST Saudi Arabia
1.6 1.4 14 1.2

PL-Po (MPa) 10% I=8 SI = 4,7

BASIS 60 grainsize tests 180 PMT tests PARAMETERS

20%
1 0.8

I = 6,25 SI = 2,3 KAUST KAUST 30% I = 5,5 SI = 1,5 I = 3,1 SI = 0,72 I=3 SI = 0,56
500

PL Po = pressuremeter limit pressure kJ/m3 = Energy per m3 (E) % = % passing n200 sieve I = improvement factor

0.6 0.4 0.2

DC DOMAIN DR DOMAIN

S.I : energy specific improvement factor

PLF PLi

I 100 E

40%

LEGEND Average pre-treatment values Average values between phases Average post-treatment values

50%
0 0 100 200 300 400

Energy ( (kJ/m3)

PERTH - AUSTRALIA June 2010

47

Stress distribution
Analysis of Worst Case Scenario for Various Grids

. 5.5 5.5 3.80

3.80

PERTH - AUSTRALIA June 2010

48

Site procedure
A Identify depth trend of SABKAH by CPT Tests B Closely eye witness the penetration of pounder to confirm DC or DR treatment C Verify by PMT that factor of safety is at least 3 for bearing capacity D Verify by stress analysis that limit pressure at any depth exceeds factors of safety of at least 3 in order to safely utilize the settlement analysis (no creep) E F Vary the grid to obtain at any location the condition D Test the gravelly sand columns and check if specified settlement is achieved hi d

G Monitor surcharge if HDR is required


PERTH - AUSTRALIA June 2010

49

Provisionnal master plan

PERTH - AUSTRALIA June 2010

51

It can be assumed that those impacts do generate a pore pressure at least equal to the pore pressure generated by the embankment load. This new consolidation process with the final at a time tf, where

For the considered case, du = U and thus tf = U1t1 + (1-U1)tf

TV = 0 848 = 0,848
With

C'v (t'1 t1 ) Cv T1 + H H

The Table allows to compare the gain in consolidation time, at different degrees of consolidation. consolidation
U 1 10% 20% 30% 40% 50% 60% 70% 80% 90%

t1/tf 0.009 0.037 0.083 0.148 0.231 0.337 0.474 0.669 1.00

du C' V = C V 1 + (1 U1)
The following equation allows to compare the respective times of consolidation being: tf with impact tf without i ith t impact t

t1/tf 0.901 0.807 0.725 0.659 0.615 0.602 0.632 0.735 1.00

Suppos g p a y co so dat o co p eted Supposing primary consolidation completed U = 0.9 or T = 0.848 if du=U1, then tf = U1t1 + (1-U1)tf The optimal effectiveness occurs around U1 = 60%. One can thus conclude that, theoretically the y , consolidation time is reduced by 20% to 50%, what is for practical purpose insufficient.
52

t' f =

(1 U1 ) du t1 + tf du + (1 U1 ) du + (1 U1 )

PERTH - AUSTRALIA June 2010

Dynamic surcharge

PERTH - AUSTRALIA June 2010

53

Settlement curves from dynamic surcharge

8,000
10,0

7,000
5,0 19/1 21/1 23/1 25/1 27/1 29/1 31/1 2/2 4/2 6/2
11 - 1 10 11 - 2 10 11 - 3 10

6,000

5,000

11 - 1 10 11 - 2 10

0,0

4,000

11 - 3 10 11 - 4 10

5,0

11 - 4 10 1 1 - AVG 10

3,000

1 1 - AVG 10

2,000

10,0

1,000 1 000

15,0

0,000 19/1

21/1

23/1

25/1

27/1

29/1

31/1

2/2

4/2

6/2

20,0

PERTH - AUSTRALIA June 2010

54

PERTH - AUSTRALIA June 2010

55

GROUND IMPROVEMENT WORKSHOP 11-12 JUNE 2010 PERTH, AUSTRALIA

Thank You

Vous aimerez peut-être aussi