Académique Documents
Professionnel Documents
Culture Documents
L
Public Works
Contractors Authori.i
William Doak
Position (Signalure) (Date)
IProgram Director I I
I I I I
Witness (Name) (Signature) (Date)
I I
I I
I II
1190 0
I
RTI Document No.329
Ref: CTC-1S411
Submission to the Associate Director-General
Subject Queensland Health LATTICE Replacement Project
Purpose To request that the Associate Director-General authorise Contract
Change Document 209 relating to a change of IBM's specified
project manager for the Queensland Health LA TriCE
Replacement Project
Background
On 3 February 2010, IBM notified the QHIC Project Board of changes to various IBM
personnel on the Queensland Health LATTICE Replacement Project.
Issues
The contract requires any changes to specified personnel to be dealt with through the
contract change prooess. The contract identifies John Gower as Specified Personnel and
more particularly as the Project Manager. IBM has requested that John Gower be replaced
with Mark Dymock on 8 February 201 D.
The QHIC Project Board has agreed the change of project manager and Contract Change
Document CR209 has been raised to formalise this change as per the contract conditions.
Recommendation
It is recommended that the Associate Director-General authorise the Contract Change
Document CR209 (refer to Attachment A).
1'-'(6
~ ) lot"L tl .:;::.
lz....1...
I
IlL
Responsible officer Margaret Berenyi
General Manager, CorpTech
N talie MacDonald
Recommendation approved
Associate Director-General
RTI Document No.330
&
Queensland
Government
PubUcworks
. Provide Defails:Schedule 29 of
Customer Contract
Contract Change Document (CCD) Form
Submission: Please send this completed fum to CorpTech Strategic Program Office (SPO) - corptechsoo@treasu{y.gld.gov.au
Replacement of IBM's Project Manager,
CR209
SOWS
nl:itif'.Qe:seijpfl(;)o;T;:;;';jc;;:. Replacement of IBM's Project Manager for QHIC 1
All changes to til single issue and SoW should be consolidated into a single Change Control Document prior to submission.
Section 1 - Details of Initiating Officer
Commercial Manager
IBM
Paul Ray
II ifill
I would like the change described in this 03/02/2010
document to be investigated and the
o Customer (CorpTech)
Customer Contract changed accordingly.
i8I Contractor (IBM)
o Other:Y Provide Deteils (e.g. Agency,
SSP etc.):
Note: The initiating officer must sign before
progressing to the SPO.
Section 2 - Contract Change Request Details
Section 3 - Contract Change Request Category
Section 4 - Documents Affected
RTI Document No.331
IBM Change Request (CR) Fonn
Use this form to raise a CR for the IBM Project Environment only.
Section 5 - Change Request Description
, .. >
"','
..:.:.:.....:.: ... ;"
.., ..,':'
z
""':::;::,:':::. ,:"".:";;.,
Replacement of Specified Personnel, Schedule 29
IBM is seeking the Customer's approval for John Gower to be replaced by
Mark Dymock as IBM's Project Manager for the QHIC Project ie SoW Bon
the 8 February 2010.
None
None
An alternative Project Manager would need to be located and proposed.
Section 6 - Consultation Details
..
Project Directorate 2/212010
':includinfJwho, was'.'.'
'keydecisions.:,:/ ...
Establish a change request to
formalise acceptance.
Section 7 - Contract Variation
identify what is proposed to be and "added" to the Contract. Please be '(lfOrd specific and use the exect text deteiled In the Contnrot.
Please provide specific wording including appropriate section references, cleuse numbers, etc.
You mey delete or add extra sections where necessary.
Project Director John Gower 0511112007 Completion of SoW 8
Project Manager Mark Dymock 08102/2010 Completion of SoW 8
Schedule 29 Key contractor personnel (Specified Personnel)
Specified personnel to be provided by the Contractor are listed in Schedule 29, along
with each indiVidual's role, planned start date end planned finish date or event if the
date for the event is not finalised. Changes to this schedule will be made via the
Change Control process
age Q
RTI Document No.332
. IBM Change Request (CR) Form
. Use this form to raise a CR for the IBM Project Environment only.
Section 8- Reviews
Reviewed by; IBM Program Delivery Office .....
Workgroup ,Name.,'
IBM Commercial &
Contracts Management
IBM Resourdng
IBM Finance
Reviewed by: StrateQic Program OffICe (SPO) ...
Workgroup' . .. 'Jllame',
SPO Vendor Management
SPO Schedule & Planning
SPO Resourcing
SPOFinance
Reviewed by; Solution OesiQnAuthority (SOA) .....
SOA Lead Reviewer I
Signature .....
. ... '.' 'Signature .... ' .
.' 1Signature :<
I
.. ,. :.Date ....'''
.Date.
,.......... :,:...,":1 <Oate ,. ,. .:: .. '... '.'
I
Section 9 - Change Request Authorisation Details
All Change Contro' Documents must be signed and dated by a person with authority to approve the change as per Schedule 12
of the Customer Contract.
We hereby endorse the proposed change outlined in this document.
(Signature)
Approval Signatures
We acknowledge and agree that this change request constitutes a Contract Variation, and shall be binding
on parties.
Customers Authorisin
Natalie MacDonald
Position
I ADG-DPW
Contractors Authorisin
William Doak
Position (Signature) (Date)
IProgram Director I I
I
I I
Witness (Name) (Signature) (Date)
I I
'----_-----JI
I
I
RTI Document No.333
Pages 24 through 25 redacted for the following reasons:
- - - - - - - - - - - - - - - - - - - - - - - - - - - -
s49 contrary to public interest
R
e
d
a
c
t
P
a
g
e
Page to be removed
R
e
d
a
c
t
P
a
g
e
Department of Public Works Ref: DPWOOOOO/09
CHIC Board briefing note
Subject QHIC SAP Review
Purpose To provide the QHIC Board with details of the management plan
developed to address risks raised in the QHIC SAP Review
Urgency A condition of exit from User Acceptance Testing (UAT) 4 is that
"Critical issues identified during SAP system audit are assessed
and management plan to resolve is agreed'
Background
The Queensland Health Implementation of Continuity (QHIC) Project will implement a
rostering and payroll sO.lution for Queensland Health. The solution will replace the current
rostering solution, ESP and payroll application, LATTICE with Workbrain and SAP
respectively.
The QHIC Project is currently targeted to go-live in December 2009 with the first pay run
scheduled for Sunday 13 December for an employee pay day of Wednesday
16 December.
CorpTech engaged SAP Australia to undertake an independent Quality Assurance
Solution Review (the "QA Review") and a Project and Risk Management Review ("Project
Management Review") of the QHIC project. The SAP Statement of Work is included at
Attachment 2.
The review was conducted from 31 August 2009 until 4 September 2009.
A condition of exit from User Acceptance Testing (UAT) 4 is that "Critical issues Identified
during SAP system audit are assessed and management plan to resolve is agreed'.
Issues
SAP in their review has raised twelve high risk and five medium risk issues.
A condition of exit from User Acceptance Testing (UAT) 4 is that "Critical issues
identified during SAP system audit are assessed and management plan to resolve is
agreed'.
RTI Document No.336
2
Current position
A meeting of the Project Directorate Forum was convened on Wednesday
14 October 2009 and chaired by the Executive Director, Service Delivery, CorpTech.
Attendees reviewed the SAP recommendations and discussed actions completed or
planned that will form the basis for the management plan (Attachment 1) to address the
UAT 4 specified exit criteria.
Consu Itation
CorpTech, IBM, QHEST and the Queensland Shared Service Partner are members of the
Project Directorate Forum and participated in the review of the SAP report.
Recommendation
It is recommended that the Board:
1. note the risks raised by SAP during their review; and
2. note the actions planned or completed (the management plan) to address the risks
raised and the assessed residual risk after mitigation.
Philip Hood
Executive Director
Service Delivery, CorpTech
31791011
0417143590
Tony Price
Director
QHEST, Corporate Services, Qld Health
32341813
0418724638
Janette Jones
Director
Payroll and Establishment
QH Shared SaNicas Partner
0418752646
Naomi du Plessis
ERPLead
QHIC ProJect, QHEST
t
Corporate SalVices
0407173827
John Gower
Project Manager
QHIC
0417135530
Terry Bums
Quality Assurance Advisor
QHIC Project, QHEST, Corporate Services
0417793338
Jane Stewart
Director
Service Management Offlce, CorpTech
30350551
RTI Document No.337
Attachment 1
Summary of Recommendations and Management
2 High
3
4 High
5 High
6 High
Re-visit functional specifications to ensure there
are clear guidelines around defects and scope
changes.
Re-assess exit and entry points for phases and
milestones and ensure aU future milestones and
phases have agreed exit and entry points which
do not change.
Open
Open
Update the documentation on Interfaces between I Open
SAP and WorkBrain as the current level of detail
is insufficient.
The knowledge transfer sessions to CorpTech I Open
(SAA and Payroll Bureau) should be backed up
with fully documented support processes
(including Reconciliation and Error Handling
between SAP and WorkBrain).
Incorporate at least 1 and 2 weeks of regression I Open
testing into the schedule.
Agree with recommendation.
The QHIC Board has addressed this recommendation. Go
live is currently scheduled for 4 December with the first final
pay ru n on 13 December for an employee pay day of 16
December.
Agree with recommendation. I Medium
All functional and technical specifications have undergone
one review and are currently being updated for changes.
Final documentation will be reviewed and approved prior to
Agree with recommendation.
The OHIC Board has reviewed USer Acceptance Entry and
Exit criteria following endorsement by proposed by the
Project Directorate. Exit criteria provide discretion for the
QHIC Board to accept management plans or otherwise
determine the status of defects. Three more gates with
Medium
Agree with recommendation. I Medium
The Project Directorate has agreed a plan to ensure
appropriate documentation on interfaces between SAP and
Workbrain will be developed and approved prIor to go-live.
i\.l"\l'\r...,,,,,,l of this documentation is oart of Gate 2.
Agree with recommendation. I Med[um
Note. SM is assumed to refer to CorpTech AppHcations
Management.
1. A series of knowledge transfer sessions have been
scheduled between the QHIC Project team and CorpTech.
2. IBM has advised that they w][l deliver the 'Reconciliation
Tool' and full documentation by Friday 16 October. Testing
of this tool will be undertaken over the period 17-18 October.
3. Error handling documentation has been developed and
reviewed and will be approved prior to go-live. Approval of
this documentation is Dart of Gate 2.
Agree with recommendation. ~ Medium
Regression testing will be perfonned throughout the three
week business orocess validation review
Core
RTI Document No.338
-2
8
9
Build the necessary process to monitor and Agree with recommendation.
correct errors during the Payroll Run and generate Error handling documentation is under development and will
appropriate documentation on the same. be approved prior to go-live. Approval of this docu mentation
is Dart of Gate 2.
High Ensure that leave balances (Infotype 2013) are I Completed Agree with recommendation. I Low
not uploaded multiple times. This defect has been corrected, implemented and
successfu
High Due to the nature of the integration between SAP ! Open Agree with recommendation. I Medium
and WorkBrain certain manual processes for All workarounds that are considered will be assessed by the
WorkCover Claim, Terminations etc_. have been Queensland Health Business, QH Shared Service Partner
introduced. Investigate and implement work and CorpTech as required before the next decision gate.
arounds in the system to reduce reliance on these
Include a full pay cycle (15 days) with ad-hoc and I Open Agree with recommendation. I Medium
interim runs as part of the Acceptance Test in a
10 High
This has been scheduled as part of PPV4 and the manual
'Business as Usuaf Scenario using with an up to processes will be factored into the 14 day pay cycle model.
date data set including aU employees. Ensure that
post payroll run related manual processes (e.g.
reconciliation of overpayments, correspondence
on overtime etc.) are included in the Test.
11 The Project has made several modifications to I Open Agree with recommendation. I Low
core SAP code which is likely to impact the
High
Due to the Integ ration between Workbrain and SAP some
solution when SAP changes the functionality in modifications to standard SAP were required within the
new releases. When support packs or SAP notes solution. Some of these modifications were originally
are loaded adjust the code based. on transaction introduced from the Housing ECC5 baseline system. All
SPAU. SAP modifications created in the Housing ECC5 SAP
system have been documented and those introduced
through the QHfC project have been documented.
Approval of this documentation is part of Gate 2.
Refer Risk 17.
12 Plan and implement a parallel pay run on go live. I Closed High Disagree with recommendation. I Medium
This risk has been previously considered by the QHIC
Board. Due to the nature of the LATTICE payroll application
and its inability to cater for retrospective processing,
adjustments to wages and salaries are performed via 'code
value adding'. Further the large size of the payroll precludes
parallel payroll running.
The QHIC Board has assessed the risk and noted that there
is no abilitv to do this on a standard oav run. Parallel
RTI Document No.339
-2
13 ! Medium I Communicate the detailed schedule throughout Open Agree with recommendation.
the project with detailed explanations about the The QHIC and QHEST projects have planed or undertaken
requirements to meet key milestones and critical detailed communication throughout both the stakeholder
project points. and project communities.
CorpTech has similarly communicated to its workforce
throughout the project.
Communication activities will continue both pre and post go-
live. Weekly Project status meetings are conducted by the
Project Manager where progress regarding work products
es is discussed.
14 I Medium I Ensure that there is enough emphasis and an Open Agree with recommendation.
allocated period for technical cutover and Extensive technical and business cutover activities have
executive bUSiness cutover. been planned and documented and are continually revised
as required. Project is comfortable with the timeframe
allocated.
Final
15 I Medium I Build necessary email alerts when Interface files Open Agree with recommendation.
are not available or if there has been a failure, The QHIC project is developing sCripts for the alerting
otherwise additional manual processes will be process.
required which will impact support costs. CorpTech has implemented a pager alert system to receive
these alerts and is implementing additional monitoring
capability within WebSphere in conjunction with CITEC. It is
acknowledged that full testing of this capability will not be
completed before UAT exit; however this is planned prior to
a-live.
16 I PJledium I Accommodate the import of support packs based Closed Agree with recommendation.
on the project schedule or apply the necessary The QHIC Board is aware that not aU support packs will be
SAP Notes. able to be applied to the system pre ga.-live. Planning for the
application of support packs and Conflict Resolution
ts post 9
17 I Medium ! Ensure modification history documents are create I Open I Agree with recommendation.
Refer Risk 11.
I Low
I Low
I low
I Low
I low
RTI Document No.340
Attachment 2
Prepared for
Queensland Government .. CorpTech
RTI Document No.341
-2
Scope of Work
Description of Engagement: CorpTech, with its Systems Integration partner IBM, has embarked on
a project to design, build and implementation of SAP HRiPayrolJ into Queensland Health and is
currently in the Realisation phase of the project. CorpTech has requested SAP to undertake an
independent Quality Assurance Solution Review (the "QA Review") and a Project & Risk
Management Review ("Project Management Review").
Scope of Work:
Quality Assurance Solution Review:
The QA Review will focus on the following areas for the key agreed business processes of CorpTech:
Completeness ofconfiguration
Quality of configuration
Flexibility of the configuration
Use of"best practice" models and processes compared with bespoke processes
Use ofcurrent SAP functionality, evaluating whether it is used for the purpose for which it has
been designed
Evaluating whether "SAP Gaps" have been covered in an appropriate manner, and detenninillg
that the quality oftlle "developments" is suitable.
Project & Risk Management Review:
The objective of the Project Management Review is to identify risks with the implementation process
and determine the necessary actions that are best suited to assist with a successful project leading to go
live.
The Project Management Review involves a stmctured approach in assessing the project risks. SAP
will aim to schedule a series ofonsite review interviews with key project team members. The outline
process is as foll.ows:
Conduct a kick-off meeting with the pl'Oject leaders to set expectations and review the agenda
Review project information and status with the project manager(s)
Interview key team members
Sample and study related pl'Oject documentation
Provide a debriefing (discussion) of the preliminary findings
Within seven (7) days after the review; deliver the Project Management Review report with the
detailed findings and recommendations
Conduct a f o l l o w ~ u p discllssion to ensure the report is understood and answer any questions.
The Project Management Review is typically conducted at the end of each phase of the project, and it
RTI Document No.342
-2
foclises upon project management, key deliverables of the phase and critical success factors. The
Project Management Review is designed to set confidence in the ability of the project to deliver, on
time and on budget.
As the project is near the end of Realisation the following are relevant focus areas at this stage:
Realisation - This Project Management Review OCC\.lrs just before integration testing
(corrections in customising are still possible at this point oftime). Focus areas include the
System Configuration, Know-how Transfer, Change Management and Communication. The
use of Solution Manager and quality of project documentation will also be assessed.
Final Preparation - This Project Management Review occurs before going live (between two
and four week's prior to go-live). The focus areas include End User Training, Go-Live Plan,
Productive Support, GoingLive Check.
CustomCI' Obligations: CorpTech (and IBM) will provide access to appropriate resources, project
documentation, solutions, technology and any other appropriate information that is required by SAP to
complete the scope ofwork.
SAP Deliverables: A management presentation and detailed review report will be compiled,
consolidated and presented to CorpTech.
Payment: The services will be provided on a fixed service fee basis of $25,000 excluding
GST to be invoiced on completion of the engagement. The fees quoted exclude all
reasonable travel, accommodation, and other related expenses (for example, meals and taxi
fares) for consultants working away from their home office or who are required to travel to
other CorpTech sites during the course of the project.
SAP resource: Review Component: Estimated Start Date: Estimated End
Date:
i Nick Parker Risk Management 1
Program & Project
Management
10/08/09 18/08/09
Andrew Lindsay I
Marcus Kendall
HRlPayroll 10/08/09 17/08/09
Ram
Ramanathan
HR/Payroll- Technical 10/08/09 17/08/09
Jacek Klatt Technical 10/08/09 17108109
___ Fixed Service Fee:
All servIces rendered under thIS Statement of Work shall be subject to the Customer Contract between
Customer and SAP, issued pursuant to GITC Q"470.
000000000
RTI Document No.343
EXECUTIVE DIRECTOR CTC* 14049
SlIBJECT
Implementation of Infrastructure for the WorkBraln Proof of Concept (POC) Phase Three
BACKGROUND
The prime contractor IBM has proposed implementing WorkBrain to process the awards for
whole of Government (w-o-G) Human Resources payroll. The WorkBrain POC environment
is urgently required in order to validate this functionality to be delivered through this solution
as an altemative to SAP. It is also requIred to confirm the capabnlty of the proposed solution
to scale up to satisfy expected e n d ~ s t a t e demand and requirements, when all agencies are on
the new Shared Service Solutions (SSS). The criticality of this application demands
comprehensive and progressive evaluation and early identification of issues and prOVisioning
capacity and environments for this Worbrain POC will facilitate this evaluation process.
The once-off implementation and ongoing costs for Phase One were approved in a previous
brief, CTC-13933 (attachment one). The costs noted in that brief were the additional costs of
provisioning fnfrastructure earlier than anticipated.
There are three phases to the IBM WorkBra!n POC:
Phase one is non fostering volume tests on the awa(ds calculation (currently
underway); ,
Phase two Includes rostering and awards calculation fcir rostering agencies (currently
being built); and
Phase three is full end state rostering and awards calculation excluding reporting.
The results of the testing of WorkBrain will provide validation and confirmation of the
proposed solution underpinning the IBM prime contractor submission.
CURRENT STATUS
The environment for Phase Three must be Implemented so that testing can commence by the
4 April 2008. Your urgent approval of this brief is required In order to satisfy the aggressive
timeframes of the IBM program of work for the poe.
There may be further oncs"off costs forthis work once detailed seoping has been undertaken.
However with a six week vendor procurement cycle, there isn't enough time to conduct
detailed scoplng prior to the order being delivered to CITEC.
This briefing note is seeking approval for the implementation charges to be Incurred to
Implement the end state production environment for WorkBrain and the ongoing costs.
Phase Three Costs -Implementation
The once off implementation charges for establishing the Work8rain POC environment for
Phase Three is $29,901.30 as detailed in the attached CITEC proposal (attachment two). As
noted above there may be further onre-off costs and these will be subject to another quote.
RTI Document No.344
-2
Phase Three Costs - Ongoing
The ongoing capacity costs requires a commitment of 36 months, please see the table below.
Four * HP BL68Sc Production at 317 Edward Street DC, Production
$13.530.00
support for three years at $3075.00 each '
Three * HP BL685e Production at Windsor DC, Production support for
$11,259.60
three $3412.00 each
One HP BL460c Production at 317 DC, Production support at $1673 $1,840.30
One HP BL460c Production at WIndsor DC, Production support at $1854 $2,039.40
3 "(;r UJst
;J. 9311 cU,g'
for funding approval of
$13,980,203 (inc GSl) for the provision of on-going support services from CITEC for
2007-2008 (see attachment three). The ongoing costs forWorkBrain POC Production
environment are Included in this budget and purchased as line items in the existing contract
with CITEC.
RECOMMENDATION
That you:
1. sign the attached CITEC proposal (attachment two); and
2. sign the attached requisition for $29,901.30 (attachment four).
Prepared by: /-
Endorsed by:'
Gary Palmer Philip Hood / '
Director Deputy Executive Director
Technology Solutions, CorpTech CorpTech
Tel: 3227 7712 Tel: 3247 5225
Date: 3 ojI 't actY"
Date: /f. / 0 /?
Recommendation Approved: .. ...................................................................,......
Date: .. ...........................................................................
Ccnticl: . Gary Palm<lr
Divlolon: . Director, Capled'!. SoIu!i<lm
T....p/loM; (07) 32271712 .
ID: G;'j)5. SSS\TO Dirtlda\lltlGlil1t/-Note,\CITEC GOMIIII Bom.l:!OOSOl30 BN DIR EO CT1400W oflnlrastrudur& fer
Worl<Bn!in POe PheM1!.dO<> .
000
RTI Document No.345
s.48 - Exempt information
s.48 - Exempt information
a Queensland Government REQUISITION
FOR GOODS AND SERVICES
(FORM 31)
Approval Is given for expenditure to be Incurred for the oupply of goods I rendering of services as follows;
Name of Omcer: GllryPalmer Brandl: sss . Infraslruclvra
Telephone No: 32277712
ExplmaUon: CITEe costs for the Immmenletion of Inrre$truetura for Wor1!.BraIn Proof Of Cooncept (pQC) Phase Three
Date Good$ Required By;
TOTAL $
I
1.
1Gb
APPROVED ' qI UJ'o D.A.N. 2 POSITION ,(jl:r of
(Please SpeQ\'y Ti\I$) (Date)
AssetClasll
AlaetShllll Number _________
D"......"..undHI1fI.
Dst.elfAmeMleo Tradeln Con$ldal'lld No I Yes (details atlaclled)
Computer Hardware/Softwe.e/Servic88 Information Technology Srancb Use Only
PIllS'. complete.ll.tuft,.
Fl3n:Ej,N
_ ......4..'2/"",-=-_______
Dato: ;)0 II I OJ"
If not c;ompatlble and/or not the ITPlan, has the client been adVised? Yes I No
If not compatible dQ YOU cb]lret ro thllllurch_ prOCeeding? Vee I No
RTI Document No.346
CorpTech Action Sheet
(effective 15106/06)
__
___.__ ..__ .. ___J
I. 3. Sighted By Program Director: Name: Date: J
Action Required
Signature
Comment c Review Other (use section below)
3ea) Funding Requests or Invoices for Payment:
Approval is required from the Finance Manager prior to submission to Office of Executive Director
o Recommended for payment (If comments required use other information section) Yes I No
By (print name): Signature:
::J } Fund_Available
Signature
L :
Colleen Orange,ymanceorrector
3(b) Contracts:
o If this matter involves engagement of contractors/consultants and/or the acquisition of
goods and services via Request for Offer/Contract have you consulted with
Procurement Services, CSQ? Yes I No
Contract documents will be returned to the relevant Program Director follOwing approval by the ED. It will be the responsibility of
the Program Director's office to record and forward to CSQ for processing.
Other Information (background) and comments:
i t
I
!,..... ....... ...-"--"-, , ....---...4
____..__ ..______"..___._,,_._._._....__...._.____.....___..___..__.__... ___ I
I ..--....-....--..-----..-'II
t--------""..-----....-------........ ,-------...-.--...
l J
4. Executive Director
Comments by Executive Director
OED use only
.. "
o Entered on OED database
o Not approved by
see ED's comments
o Completed on OED
database
0:\05 .. SSS\TO .. Technology\Ol Administration\Forms & Templates\Orange Action Sheet Template.doc
RTI Document No.347
_. ----_... _-----
DEPUTY EXECUTIVE DIRECTOR CTC-14373
SUBJECT
Establishment of an Enterprise Resource Planning (ERP) Central Component (ECC) pre
production and production environment for the Queensland Health Implementation of
Continuity (QHIC) project.
BACKGROUND
With vendor support discontinuing for the current Queensland Health Human Resource
solution, priority attention has been given to its replacement by CorpTech. As a result,
Program 42 has accelerated and condensed the project to facilitate the migration from
Lattice onto an interim SAP ECC and Whole of Government Workbrain solution.
CURRENT STATUS
There is an urgent requirement to establish an environment to host the pre-production and
production ECC systems to enable the OHIC project team to meet the projects go-live date.
This briefing note is seeking approval for the once off implementation charges to be incurred
to enable the establishment of this environment for OHIC.
Costs - Implementation
The once off implementation charge, for establishing the capacity to support the
establishment of this environment, is $11,343.20 (Inc GST) as detailed in the attached CITEC
proposal (attachment one).
Costs Ongoing
The ongoing capacity costs requires a commitment of 36 months, please see the table below.
for funding approval of $13,980,203 (Inc GST) for the provision of on-going support
ces from CITEC for 2007-2008. The ongoing costs for the OHIC environments are
included in the 2008-2009 budget estimates.
RTI Document No.348
s.48 - Exempt information
s.48 - Exempt information
-2
RECOMMENDATION
That you sign the attached CITEC proposal (attachment one).
Prepared by: Endorsed by:
GarypalmJ Philip Hoo
Director Deputy Executive Director
Technology Solutions, CorpTech CorpTech
Tel: 32277712 Tel: 32475225
7/
r
/
200
?
Date: / ..J1,l-r0 3:
Date:
Contact: Gary Pillmer
B"",.h- C",!,T..:h, Techoo]ogy SolU1in.
Tel: 3227 7712
Doc TO; Q;\I}5 - SSS\Ta - TI!noIol!)'1OO Ditect.rIBriefing-NoIoOICTlliC Gonem 8N DUt lID CT14373 I.'roculoment ofCapac;ty fer QHIC Ptoduairu> IWd Pro
Produclion...doe
RTI Document No.349
Pages 40 through 44 redacted for the following reasons:
- - - - - - - - - - - - - - - - - - - - - - - - - - - -
out of scope
R
e
d
a
c
t
P
a
g
e
Page to be removed
R
e
d
a
c
t
P
a
g
e
Page to be removed
R
e
d
a
c
t
P
a
g
e
Page to be removed
R
e
d
a
c
t
P
a
g
e
Page to be removed
R
e
d
a
c
t
P
a
g
e
----------------------
CorpTech Action Sheet
(effective 151061061
yU\lVv'\ev
World:)\' -p'{ VI
Name:
---- - ..--
Name:
Program Director: Name:
Action Required
rrI Signature o Comment D Review o Other (use section below)
3(a) Funding Requests or Invoices for Payment:
Approval is required from the Finance Manager prior to submission to Office of Executive Director
o Recommended for payment (If ccmments required use ollier Information seellon) Yes I No
By (print name): Signature:
o Funds Available
Signature II>/tD/or
Colleen Orange, Finance Director
3(b) Contracts:
o If this matter involves engagement of contractors/consul1ants and/or the acquisition of
goods and services via Request for Offer/Contract have you consulted with
Procurement Services, CSQ? Yes I No
Contract docul11ents will be returned k> lIle relevant Pro!lram Directorfolfowing approval by the ED, It will be the responslbillly 01
Ille Progmm Director's offioe 10 record and lmwllrd 10 CSO for processing.
Other Information (background) and comments:
....-..
--.. ....
.. . .. ........._... _.
...'
4. Executive Director
Comments by Executive Director
.. .
..-._.__.._..._-- ..... '---.--......
OED use only
.._.__. ....___.__ ..... .._.... J
G:\05 SSS\l'O - Toolmology\CH t\.{iln[nistfatjol!\FOr'ms & Ttlnphde\Orangc Action: Sheet Template.doc
RTI Document No.355
s.48 - Exempt information
s.48 - Exempt information
Ref: CTC 14898
Submission to the Executive Director
Subject CITEC proposal to implement Workbrain Pre-Production
Infrastructure (REF: 5001623)
Purpose To request:
1. approval to establish a pre-Production environment utilising
multiple physical servers; and
2. acceptance of a quotation from CITEC (refer Attachment 1):
r. to establish the capacity to support the setting up of the
environment; and
11. for the backup and restore test.
Background The objective of this project is to provide an environment which
can simulate the Production architecture to minimise the risk of
defects occurring in Production due to architecture differences
between Production and non-Production environments.
Issues
Workbrain Production architecture comprises a fully clustered multi instance solution utilising
multiple physical servers for component separation and redundancy. Non-Production
environment architecture on the other hand generalty involves single instance components
co-hosted on a single physical server.
This difference in architecture means that defects may not be evident or occur until a solution
is moved into Production despite thorough testing in the Test and UAT environments.
To reduce the risk of defects not being identified until go-live a pre-Production can be
established to test the cluster Production architecture.
Current Status
This proposal to establish a pre-Production environment utilising multiple servers, will
allow the complex Production architecture to be simulated in a final test environment to
ensure a smoother cut-over and go-live. In addition this environment will also provide a
more compatible Stress &Volume testing environment and provide a Production support
test environment.
RTI Document No.356
RTI Document No.357
s.48 - Exempt information
Pages 48 through 53 redacted for the following reasons:
- - - - - - - - - - - - - - - - - - - - - - - - - - - -
out of scope
R
e
d
a
c
t
P
a
g
e
Page to be removed
R
e
d
a
c
t
P
a
g
e
Page to be removed
R
e
d
a
c
t
P
a
g
e
Page to be removed
R
e
d
a
c
t
P
a
g
e
Page to be removed
R
e
d
a
c
t
P
a
g
e
Page to be removed
R
e
d
a
c
t
P
a
g
e
CorpTech Action Sheet
(effective 15/0BIOO)
3. Sighted By Program Director: Name: Philip Hood Initial PH Date:
Action Required
o
Comment
o
Review
o
Other (lise section below)
3(a) Funding Requests or Invoices for Payment:
Approval Is required from the Finance Manager prior to sUbmissIon to Office of Executive Director
00 Recommended for payment (If comments required use other Information S&C!ion) Yes I No
By (print name): Signature:
!RI
Funds Available Signature
Colleen Orange, Finance Director
3(b) Contracts:
ffiI If this matter involves engagement of contractorslconsultants andlor the acquisition of
goods and services via Request for Offer/Contract have you consulted with
Procurement Services, CSO? Yes I No
Contract doouments will be returned 10 the relevant Program Dlreclor following ap PrcMll by the ED. II will be !he responsibility of
tile Program Dlredo(s office III record and forward 10 esa for processing.
r [nformation (background) and comments:
-----1
i
... ... ....-I
-------------------------------,
IflIejltJlby Executive Director
OED use only
,.....,.-:;---, ...
RTI Document No.364
3(a) Funding Requests or Invoices for Payment:
Approval is required from the Finance Manager prior to submission to Office of Executive Director
o Recommended for payment (If comments required use other information section)
By (print name): Signature:
o
3(b) Contracts:
o If this matter involves engagement of contractors/consultants and/or the acquisition of
goods and services via R.equest for Offer/Contract have you consulted with
Procurement Services, eSQ? Yes / No
Contract documents will be returned to the relevant Program Director following approval by the ED. It will be the responsibility of
t e Program Director's office to record and forward to CSQ for processing.
her Information (background) and comments:
Comments by Executive Director
CorpTech Action Sheet
(effective 16/06/06)