MINUTES OF THE MEETING HELD at Chandigarh on 19th Novemb

Sr. No. Name Designation


1. Mr. Atul Madan GM-PI-Hq
2. Mr. Manish PI–
Jalandhar
3. Mr. Summit Madan Branch-MAN
Team
4. Mr. D K Sharma Branch Sales
5 Mr . Vijay Srivastava OSP
6 Mr.Jagdeep Dhillon DGM TTSL
7 Mr . Harsimran Ops Support

MINUTES OF MEETING
Sr. No. Description Ownership Timelines
1 Infrastructure Activities at Chandigarh
O&M/OPS
support(Harsim
Stacking of UPS in rack for Space creation ran) 31-Dec-07
O&M/OPS
Stacking of batteries and rearrangement by piling support(Harsim
them up for better utilization of space. ran) 29-Feb-08
2 MAN Fiber and POP requirements
Sharing of MAN fiber on TTSL built route O&M(Nishat)
31-Mar-08
Chandigarh Potiential customer loactions and new Sales(D K
pops creation proposal. Sharma) 31-Mar-08
4 Fibers to be provided for Baddi connectivity from O&M/OSP(Su
the Panchkula ring. mmit,Vijay) Immediate.
3 BW requirements/Equipement Upgrade
PI/Engineering(
Plan for XDM 1000 at Chandigarh SEC17 POP Manish,amit) Immediate.
PI/Engineering(
Plan for XDM1000 at TTSL Mohali ,termination of
Manish,amit)
mohali rings at TTSL . 31-Dec-07
4 Baddi POP
PI/Engineering/
Baddi POP electronics to be discussed and Sales(Manish,D
decided. K Sharma) 31-Dec-07
Sales/OSP(D K
Baddi Potiential Customer locations. Sharma,Vijay) 31-Dec-07
5 OFF NET to ON NET
PI/Engineering(
Manish,Summit
Plan for offnet to onnet coversion for HFCL Mohali. ) 29-Feb-08
6 CIP /Shifting of Radio
Removal RF link (ministry circuits ) and converting
O&M/PI(Summi
them on to MAN network.Removal of this rack
t,Sanjay)
,saving on power and space. 29-Feb-08
7 Disaster Recovery /Dual POP
Plan for the feasibilty of developing TTSL Mohali as O&M/PI(Amit,S
30-Jun-08
Dual POP /disaster recovery site ummit/Zia)
Chandigarh on 19th November' 2007
Location
Mumbai
Jalandhar

Chandigarh

Chandigarh
Chandigarh
Mohali
Chandigarh

F MEETING
REMARK

Suggested to stack up the UPS on a rack for better utilization of space.

Suggested to stack up the batteries on a rack for better utilization of


space.

Permission of sharing of fibers on TTSL build routes for MAN


Chandigarh.
Sales to provide detail for the potiential customer location ,PI to
suggest pops based on the deleivery points.
Fibers to be realeased from MAN O&M for connectivity of Baddi fiber
to Panchkula ring.

PI/Engineering team to provide plan for XDM 1000 at Chandigarh.


PI/Engineering team to provide plan for XDM 1000 at TTSL Moahi,ring
shortening by terminating Hutch traffic,HFCL traffic at TTSL Mohali
location.

PI to provide electronics detail in consulations with DATA,sales and


engineering team.
Sales to provide detail for the potiential customer location at
Baddi,OSP team to built accress network on that.

Plan to terminate the HFCL Mohali traffic at TTSL Mohali making this
loaction as handshake point.
To convert this ministry circuits as MAN circuits thereby saving on rack
space and power.

Proposal to develop TTSL Mohali as Dual POP site as alternative to


Sec 17 site.
MINUTES OF THE MEETING HELD at Jalandhar on 20th November'
2007
Sr. No. Name Designation
1. Mr. Atul Madan GM-PI-Hq
2. Mr. Manish P I – Jalandhar
3. Mr. Sanjay Bhat Branch-Ops Head
4. Mr. Jitender Bhalla Branch-Data
Head
5 Mr . Amit Chopra P I – Jalandhar

MINUTES OF MEETING
Sr. No. Description Ownership Timelines
1 NLD ring shortening

Ring Shortening between Chandigarh and O&M/PI/Engineering(


Jalandhar Manish,Bharat,Zia)
30-Jun-08
2 OFF NET to ON NET
O&M/PI/Engineering/
Hutch/HFCL offnet /onnet coversion plan at OSP(Amit,Nishat,Vija
Jalandhar y) 30-Jun-08
3 BW requirements/Equipement Upgrade
PI/Engineering(Amit,
31-Mar-08
Plan for XDM 1000 at Jalandhar Manish)
Thapar Institute Partial BW offnet to onnet by taking PI/Engineering/CM(M
handoff at Patiala anish,Sahab) 31-Mar-08
4 Disaster Recovery
PI/Engineering(PK
Proposal for utilization of space of GDS Jal for DR Sharma,Sanjay,Mani
site or data center. sh) 30-Jun-08
Location
Mumbai
Jalandhar
Jalandhar
Jalandhar

Jalandhar

REMARK

Suggested to reduce the ring between Chandigarh and


Jalandhar on the newly built TTSL route through
Kharar,Nawanshahar,Hoshiarpur .This segement is
already maintained by VSNL O&M.

Suggested to connect newly deployed Hutch MSC with


the MAN network.

PI/Engineering team to provide plan for XDM 1000 at


Jalandhar.
PI/Engineering team/capacity Management to shift
Patiala MPLS BW on the newly created Hutch BW.

To propse for space utilization for the area vacated by


GDS closure.