ROUTE MAP OF JOB PROGRAMMED IN VOLEX POLAND

Date : 25-01-08

Item MONTH JANUARI FEBRUARI


JOB PROGRAMMED PIC REMARKS
no.
WEEK WK1 WK2 WK3 WK4 WK5 WK1 WK2 WK3 WK4 WK5

1 Put measurment onto shaft moulding for clamp high setting Tommy

Put a marking onto the base mould and based plate molding for
Tommy/Seter
guide line to do quick set up mold

Records all mould with the accessories and arrangement the


2
mould on regal/storage with proper identification
Seter Used form number FM 003
Continue record the parameter with all product and update the Used form number FM 001 for
3
different to next revision with history Tommy/Seter newbury/ FM 002 for multiplas
4 Update molding maintenance check list for all moulding machine
Tommy/Seter Used form number : FM005
5 Provide a cover onto the layer material in Hopper dryer
Piotr M/Maint. Request from supplier
Request a termometer to check room temperature for parameter
6
control Piotr M Request from supplier
Segregate the PVC material which mixed up with other color
7
material due to do not have cover Operator
Follow up with outside maintenance people for moulding
8
servicing Piotr M
9 To implement the information white board for mould movement
Piotr M/Seter
10 To service the mold which unloading from molding machine
Seter

Record all the mold problem such as damage on insert mold,


11 damage cable grip or on mold bar. And ask mold maintenance to
repair and follow up the date delivery
Tommy/Seter Used form number : FM004
Planned to add a timer on molding machine to cut off the switch
Make the circuit control and ask to
12 temperature after 15minutes to avoid burn the pvc inside srew
buy the material
barrel. Tommy/Maint.
To train all the technicians/seter how to operate and trouble
13
shoot the multipas machine Tommy/Engineer
14 To train on how to clean the burn pvc inside screw barrel
Tommy
Train the operator on how to do on change over material
15
moulding machine to avoid mixed up Tommy