Project Overview Statement Executive Summary

Project Name: VPN branch connectivity Department: IT Department Last Updated: September 2 2010 Author: Cyrus Neccesito Project Manager(s): Marvin Chiong and Cyrus Neccesito Executive Sponsor: Project Department Owner:

Project Business Case


Project Overview The 10-Q Grocery grown to a chain of 150 stores distributed nationwide. During its growth, each branch was allowed to operate autonomously. Each branch processes business data using its own system but all using Microsoft Excel. For purpose of consolidating company data, especially accounting data. To establish this a group of IT are hired to design and install a system that will update central office files in real time. The group decided to use a VPN, A virtual private network (VPN) is a network that uses a public

telecommunication infrastructure. The goal of a VPN is to provide the organization with the same, secure capabilities, but at a much lower cost. It encapsulates data transfers between two or more networked devices not on the same private network so as to keep the transferred data private from other devices on one or more intervening local or wide area networks. To establish this, a DSL modem and LAN system in each building will be installed assisted by a router to manage the flow of data packets for the PCs in each branch. The Internet Service Provider assigned will
provide the connection for the internet for the Head Office.

Business Issue/Opportunity Increase the amount of sales. Increase the number of franchise. Increase the company profit.

Confidential Document1 Last printed 4/29/2012 5:11:00 AM

Project Overview StatementExecutive Summary

Project Business Goal Provide good quality products to costumers Prevent shortage of quantity of products Provide an up to date accounting data and other business data. Provides greater profit

Primary Project Objectives


Primary Project Objectives Provide a network that connects the head office and the sub-branches. Provide LAN connection for each branches and head office. Provide faster processing of business data. Provide good internet connection for business transactions. Provide a secured network and data transferring.

Project Benefits
Project Benefits Faster data transferring. Enhanced database for data. Improved system for transferring of the uploaded transaction data to the database. More secured data transfer and network communication between offices.

Primary Project Deliverables


Milestone 1 Deliverables 1 Approval of network design Deliverables 2 Approval of proposed project plan Deliverables 3 Signing of contract between the company and project manager.

Milestone 2 Deliverables 1 - Testing of installed network.

Milestone 3 Deliverables 1 Sign off on the contract between the parties.

Project Conditions
Project Assumptions

Confidential

Page 2

4/29/2012

Project Overview StatementExecutive Summary

Internet and LAN connections are present for each branches PCs and printers are already available for network configuration. Updated database every week can be achieved. Every transaction is monitored every day.

Project Risks

Delayed equipments order delivery. Delayed installation of the Digital Subscriber Line (DSL) connection Inablity to acquire a Digital Subscriber Line (DSL) connection for rural areas.

Project Constraints The Networking Project does not account for the payment of the DSL subscription to PLDT or any other ISP as well as the monthly billings of each office.

Project Critical Success Factors (Key Performance Indicators)


Project Critical Success Factors Successful connection between head office and branches Successful connection to the internet Working Web-based application

Project Duration Estimates


Project Milestone Project Start Date Milestone 1 Milestone 2 Milestone 3 Project End Date Date Estimate 09/09/10 09/10/10 10/08/10 10/09/10 10/09/10 Confidence Level High High High High High

APPROVALS
Prepared By ______________________________________ Project Manager

Approved By ______________________________________
Confidential Page 3 4/29/2012

Project Overview StatementExecutive Summary

Project Sponsor ______________________________________ Executive Sponsor ______________________________________ Client Sponsor