Académique Documents
Professionnel Documents
Culture Documents
1, Februaiy 1994 38 1
ABSTRACT
redundancy and uniform spread [ 13. Hence the
In modern power system control centers, location of RTUs plays an important role in
operation and control of power systems are an EMS project.
carried out with the help of real-time
computers. Live data is captured by Remote To support the security monitoring
Terminal Units (RTUs) located at various function in Energy Control Centers following
stations and transmitted over suitable alternatives are available with regard to
communication media to the control center for placement of RTU:
display, monitoring and control.
a) Placement of RTUs at all the stations to
Telemetering equipment forms a sizable gather the information of the network
component of the project cost. A methodology status (position of switches, breakers)
is presented in which RTUs are located at and all the relevant measurements like
different stations to meet certain criteria MW,MVAR,KV etc.
such as observability of the system and
absence of critical measurements. Additional b) Placement of RTUs at all the stations as
reliability constraint of loss of information in alternative (a) to gather the
from a single RTU for the above two information on network status from all
constraints is also imposed. stations and gathering the information
from measurements at only some selected
Keywords : Energy management systems (EMS), stations.
telemetering system, remote terminal units,
observability, critical measurements. c) Placement of RTUs at only some selected
stations to obtain the network status and
measurements also from the same stations.
INTRODUCTION The remaining information with regard to
network status is obtained manually.
In modern power system control centers,
also called as Energy Control Centers (ECC), The alternative (a) though desirable is
operation and control of power systems are most expensive and may not be practicable.
carried out with the help of real-time Option (c) is the cheapest since the RTU
computers. Live data is captured by Remote placement and measurement systems are located
Terminal Units (RTUs) located at various at a selected number of stations only. Though
stations and transmitted over suitable the network status is not obtained in real-
communication media to the control center time, it can be updated whenever there is a
computer system for display, monitoring and change in the configuration. In the proposed
control. The data received at ECC are prone method option (c) is considered.
to errors arising from transducers,
communication systems etc. A state estimator In this paper a new method for the
is used to provide a reliable and complete design of measurement system is presented
data base. In order to be able to estimate wherein RTUs are placed only at some selected
the state of the system, the measurement substations. The proposed method honors
system should be sufficient .enough to location of RTUs decided apriori and works
estimate the magnitudes and phase angle of from that point.
the voltages of all the buses in the system.
Handschin and Bongers [2] pointed out
Bad data in the measurements should be that local redundancy and the probability of
detected and eliminated from the measurement detecting bad data are the most important
set. Further, it is also well known that for factors when planning a measurement system.
reliable estimation of the system state, the Their method consists of moving the
measurement system should have sufficient measurements from the best to the worst part
of the network, starting with an initial
solution with almost designed redundancy. Roy
93 WM 187-5 PWRS A paper recommended and approved and Villard [ 3 ] described a method in which
by the IEEE Power System Engineering Committee of different possible telemeasurement
the IEEE Power Engineering Society for presentation configurations are compared by off-li'ne
at the IEEE/PES 1993 Winter Meeting, Columbus, OH, simulations of state estimations. Koglin
January 31 - February 5, 1993. Manuscript submitted [4] used a general criterion to
January 7, 1992; made available for printing systematically eliminate Some of the
November 30, 1992. measurements in the system to obtain an
optimal set from various measurements. Phua
and Dillon [5] developed a method based on
entropy criterion. The problem is posed as
non-linear programming problem which is
0885-8950/94/$04.00 0 1993 IEEE
382
4
'observable, in the sense of state estimation
with respect to a given measurement set M , if
the bus voltage magnitudes and angles
throughout the system can be determined by TELEMETERING CONFIGURATOR
processing the measurements in M by a state
estimator. Otherwise the power system is
said to be 'unobservable' with respect to M. Location of RTUs List of measurements
It was proved in [I13 that if measurements in
the system form a spanning tree connecting to be measured by RTUs.
all the buses then the system is observable. Fig.1 Block diagram of telemetering
Clements [ 1 2 ] has explained various
configurator.
383
four phases. Each of these phases is the measurement system ) . The criteria for
explained below : placement of additional RTUs is shown in Fig.
3 as a flow chart.
Phase 1 L Placement of RT.Us till the
redundancy atleast e m a l to 1.0 : Phase 3 i Placement of R T U s to cover
critical measurements i
In general generating stations and some
substations are normally considered as very In this phase additional measurements
important by the utilities from the point of are added to the measurement set by placing
view of data acquisition. These stations are additional RTUs to make the resultant
treated as specified locations for initial measurement system free of critical
placement of RTUs. With this initial measurements.
measurement set the redundancy is computed.
Redundancy is defined as the ratio of number Critical measurements ( line flows and
of known measurements to the number of bus injections ) are first identified using
unknowns (state variables). If the redundancy the complete set of measurements available
is less than 1.0 it implies that state through the RTUs at the end of phase 2.
variables cannot be calculated by the state (Since zero bus injection measurements are
estimator. If the redundancy is less than not physically metered, they need not be
one, location of RTUs is continued at other considered). These are called first order
locations till the redundancy is atleast critical measurements.
equal to 1.0. When the redundancy is atleast
equal to 1.0, the next phaseistomake the system 1. To start with, the first critical
observable. At any stage the criterion for measurement from the above measurement
placing an RTU at a location other than is suppressed. The system becomes
specified locations is to pick up that bus at unobservable-Then one or more additional
which the maximum number of RTUs are to be placed as per the
lines/transformers are incident at the procedure explained in phase 2 to make
corresponding s / s . The details of this phase the system observable under this
are shown in the form of a flow chart in Fig. condition. This will lead to a new set
2. of critical measurements ( called second
order critical measurements ) . This
Phase 2 i Placement of R T U s until the procedure of finding second order
system observable i critical measurements is repeated
sequentially for all the first order
With the measurement set obtained after critical measurements considering one at
the placement of RTUs in phase 1 the system a time.
is tested for observability. The test for
observability is explained in the previous Get the measurement list from phase 1.
I
section. If the system is not observable,
enhancement of the measurement system is done
by placing additional RTUs at appropriate
locations. ( If the system is not observable, observable?
then it is divided into different groups of
buses and/or isolated buses with respect to
Are there any Find the buses
[Place RTUs at specified Locationsj isolated buses which have lines
linking first and
s./
4- P e l e J t the '
Is there already an
RTU placed at this bus ? bus with
an RTU in that next bus with next highest
highest
lines/Tr
incident
Place a RTU at this location!
Fig. 2. Flow chart for phase 1.
Fig. 3 . Flow chart for phase 2.
384
R *Bus-lnjection
p R T U
-
o,Zero Bus-
measurement
+ Line -Flow
in jection tuiearur e me nt
Measur a m ent
R
R
R 50
Fig. 10 Measurement System a t t h e end of
all p h a s e s f o r I E E E 30 bus system.
386
.. . . ... ... .. -. ..
..--