Vous êtes sur la page 1sur 7

IEEE Transactions on Power Systems, Vol. 9, No.

1, Februaiy 1994 38 1

DESIGN OF TELEMETERING CONFIGURATION FOR ENERGY MANAGEMENT SYSTEMS

N.D.R.Sarma. . V.Veera.Raju K.S.Prakasa Rao


Student member, IEEE Senior member, IEEE

'CMC Limited Department of Elect.


115, Sarojini Devi Road Indian Inst. of Tech., Delhi,
Secunderabad 5 0 0 003 Hauz Khas, NEW DELHI - 110 016
INDIA. INDIA.

ABSTRACT
redundancy and uniform spread [ 13. Hence the
In modern power system control centers, location of RTUs plays an important role in
operation and control of power systems are an EMS project.
carried out with the help of real-time
computers. Live data is captured by Remote To support the security monitoring
Terminal Units (RTUs) located at various function in Energy Control Centers following
stations and transmitted over suitable alternatives are available with regard to
communication media to the control center for placement of RTU:
display, monitoring and control.
a) Placement of RTUs at all the stations to
Telemetering equipment forms a sizable gather the information of the network
component of the project cost. A methodology status (position of switches, breakers)
is presented in which RTUs are located at and all the relevant measurements like
different stations to meet certain criteria MW,MVAR,KV etc.
such as observability of the system and
absence of critical measurements. Additional b) Placement of RTUs at all the stations as
reliability constraint of loss of information in alternative (a) to gather the
from a single RTU for the above two information on network status from all
constraints is also imposed. stations and gathering the information
from measurements at only some selected
Keywords : Energy management systems (EMS), stations.
telemetering system, remote terminal units,
observability, critical measurements. c) Placement of RTUs at only some selected
stations to obtain the network status and
measurements also from the same stations.
INTRODUCTION The remaining information with regard to
network status is obtained manually.
In modern power system control centers,
also called as Energy Control Centers (ECC), The alternative (a) though desirable is
operation and control of power systems are most expensive and may not be practicable.
carried out with the help of real-time Option (c) is the cheapest since the RTU
computers. Live data is captured by Remote placement and measurement systems are located
Terminal Units (RTUs) located at various at a selected number of stations only. Though
stations and transmitted over suitable the network status is not obtained in real-
communication media to the control center time, it can be updated whenever there is a
computer system for display, monitoring and change in the configuration. In the proposed
control. The data received at ECC are prone method option (c) is considered.
to errors arising from transducers,
communication systems etc. A state estimator In this paper a new method for the
is used to provide a reliable and complete design of measurement system is presented
data base. In order to be able to estimate wherein RTUs are placed only at some selected
the state of the system, the measurement substations. The proposed method honors
system should be sufficient .enough to location of RTUs decided apriori and works
estimate the magnitudes and phase angle of from that point.
the voltages of all the buses in the system.
Handschin and Bongers [2] pointed out
Bad data in the measurements should be that local redundancy and the probability of
detected and eliminated from the measurement detecting bad data are the most important
set. Further, it is also well known that for factors when planning a measurement system.
reliable estimation of the system state, the Their method consists of moving the
measurement system should have sufficient measurements from the best to the worst part
of the network, starting with an initial
solution with almost designed redundancy. Roy
93 WM 187-5 PWRS A paper recommended and approved and Villard [ 3 ] described a method in which
by the IEEE Power System Engineering Committee of different possible telemeasurement
the IEEE Power Engineering Society for presentation configurations are compared by off-li'ne
at the IEEE/PES 1993 Winter Meeting, Columbus, OH, simulations of state estimations. Koglin
January 31 - February 5, 1993. Manuscript submitted [4] used a general criterion to
January 7, 1992; made available for printing systematically eliminate Some of the
November 30, 1992. measurements in the system to obtain an
optimal set from various measurements. Phua
and Dillon [5] developed a method based on
entropy criterion. The problem is posed as
non-linear programming problem which is
0885-8950/94/$04.00 0 1993 IEEE
382

solved using a sequential linearly aspects of observability and reviewed some


constrained minimization method. Mafaakher et methods of meter placement.
a1 [6] have used the ability of bad-data
detection of state estimation to design a Critical Measurements L
metering system. Aam, Holten and Gjerda [7]
provided a brief survey of the various A measurement is said to have detectable
methods of optimal meter placements error residual if an error in the measurement
highlighting the advantages and shows up in the measurement residual,
disadvantages of each method. They also residual being the measured value minus
presented a method by extending Koglin's calculated value [13]. It was proved that
method to obtain a more robust solution. there may be some measurements in which an
Nabil Abbasy and Shahidehpour [8] proposed a error in the measurement will not be
mathematical programming problem model to reflected in the residual. The problem of
identify redundant measurements from a given determining which measurements have
set of measurements. Young Moon Park et a1 detectable error residuals is solved by
[ 9 ] presented an algorithm of optimal meter identifying a class of measurements, called
placement for the state estimation, which 'critical measurements' and showing that only
minimizes the total investment subject to a non-critical measurements have detectable
prespecified accuracy of the estimated state. error residuals. Since only non-critical
Hiroyki Mori and Yasuo Tamura [lo] compared measurements have detectable error residuals,
various approaches of meter placement in a bad data in those measurements can be
power system static state estimation and detected. But in the case of critical
proposed a method based on stochastic load measurements, a bad data is not reflected in
flow model. the error residual and hence cannot be
detected. A critical measurement is defined
In all the above methods the emphasis as that measurement, which when not available
was on the design of a measurement system at makes the system unobservable.
the meter level only. An RTU is required to
be located at a station whether one or more Thus critical measurements imply the
quantities are to be measured at this following :
station. Current trend is towards building
transducers at lower costs. Hence it is . loss of critical measurements would make
logical to gather maximum possible the system unobservable.
information by the located RTU in a station.
Thus the design of measurement system at the . an error in the critical measurement
RTU level becomes most relevant. cannot be detected.
In this paper a new methodology for Hence it is important to see that a
design of telemetering configuration is system would not have any critical
presented in which RTUs are located at measurements and be designed accordingly.
different stations to meet certain criteria
such as observability of the system, absence DESIGN TELEHETERING CONFIGURATION
of critical measurements. Additional
reliability constraint of loss of information In this section a new design methodology
from a single RTU for the above two of the telemetering configuration at the RTU
considerations is also imposed. The level is proposed.
locations where RTUs are placed for SCADA
purposes as desired by the utilities are Various inputs and outputs of
honored. The proposed method is tested on 'Telemeterinq Confiqurator' are shown in
standard IEEE systems and on a practical Fig.1. It is assumed that all possible MW and
system. The results are presented and W A R flows in the lines and transformers are
discussed. acquired by the RTU at the sub-station so
that maximum information is gathered from the
THEORY OBSERVABILITY CRITICAL substation ( s f s ) . It is assumed that voltages
are measured at all the buses in the s f s
MEASUREMENTS
where RTUs are placed.
System observability and absence of
critical measurements are important criteria The complete procedure of designing the
for the design of telemetering configuration. telemetering configuration is divided into
The concepts of observability and critical
measurements are explained below. System Specified Desired List of zero
Observability L topology RTU bus bus injection
locations injection measurements
A power system is said to be measurements

4
'observable, in the sense of state estimation
with respect to a given measurement set M , if
the bus voltage magnitudes and angles
throughout the system can be determined by TELEMETERING CONFIGURATOR
processing the measurements in M by a state
estimator. Otherwise the power system is
said to be 'unobservable' with respect to M. Location of RTUs List of measurements
It was proved in [I13 that if measurements in
the system form a spanning tree connecting to be measured by RTUs.
all the buses then the system is observable. Fig.1 Block diagram of telemetering
Clements [ 1 2 ] has explained various
configurator.
383

four phases. Each of these phases is the measurement system ) . The criteria for
explained below : placement of additional RTUs is shown in Fig.
3 as a flow chart.
Phase 1 L Placement of RT.Us till the
redundancy atleast e m a l to 1.0 : Phase 3 i Placement of R T U s to cover
critical measurements i
In general generating stations and some
substations are normally considered as very In this phase additional measurements
important by the utilities from the point of are added to the measurement set by placing
view of data acquisition. These stations are additional RTUs to make the resultant
treated as specified locations for initial measurement system free of critical
placement of RTUs. With this initial measurements.
measurement set the redundancy is computed.
Redundancy is defined as the ratio of number Critical measurements ( line flows and
of known measurements to the number of bus injections ) are first identified using
unknowns (state variables). If the redundancy the complete set of measurements available
is less than 1.0 it implies that state through the RTUs at the end of phase 2.
variables cannot be calculated by the state (Since zero bus injection measurements are
estimator. If the redundancy is less than not physically metered, they need not be
one, location of RTUs is continued at other considered). These are called first order
locations till the redundancy is atleast critical measurements.
equal to 1.0. When the redundancy is atleast
equal to 1.0, the next phaseistomake the system 1. To start with, the first critical
observable. At any stage the criterion for measurement from the above measurement
placing an RTU at a location other than is suppressed. The system becomes
specified locations is to pick up that bus at unobservable-Then one or more additional
which the maximum number of RTUs are to be placed as per the
lines/transformers are incident at the procedure explained in phase 2 to make
corresponding s / s . The details of this phase the system observable under this
are shown in the form of a flow chart in Fig. condition. This will lead to a new set
2. of critical measurements ( called second
order critical measurements ) . This
Phase 2 i Placement of R T U s until the procedure of finding second order
system observable i critical measurements is repeated
sequentially for all the first order
With the measurement set obtained after critical measurements considering one at
the placement of RTUs in phase 1 the system a time.
is tested for observability. The test for
observability is explained in the previous Get the measurement list from phase 1.
I
section. If the system is not observable,
enhancement of the measurement system is done
by placing additional RTUs at appropriate
locations. ( If the system is not observable, observable?
then it is divided into different groups of
buses and/or isolated buses with respect to
Are there any Find the buses
[Place RTUs at specified Locationsj isolated buses which have lines
linking first and
s./

Calculate the redundancy


buses of the first linking first &
isolated bus second, find the

greater than or phase 2


'Arrange these buses so on
in the decreasing
order of number of
1inesfTr incident
at the correspond-
order of number of lines\tr incident ing s / ~ .

4- P e l e J t the '
Is there already an
RTU placed at this bus ? bus with
an RTU in that next bus with next highest
highest
lines/Tr
incident
Place a RTU at this location!
Fig. 2. Flow chart for phase 1.
Fig. 3 . Flow chart for phase 2.
384

2. The first order critical measurement system observable a n d - f r e e from critical


which results in the least number of measurements (to the extent possible ) under
second order critical measurements is such situations, additional RTUs are required
chosen for consideration of placement of to be placed. So in this phase additional
additional RTUs. If, at this stage, the RTUs are placed to consider the l o s s of
number of second order critical information from an RTU. It may be noted that
measurements happens to be same for two sometimes the system may not become free of
or more first order critical critical measurements under this contingency.
measurements, the choice of the bus (es) This has to be repeated for each of the RTUs
for the placement of additional RTU(s) located in the system at the end of phase 3 .
is made by the criterion of the maximum The details of this phase are given in Fig.
number lines/transformers incident at a 5.
bus(es).The critical measurements in the
system at this stage are treated as RESULTS AND DISCUSSION
first order critical measurements.
The proposed method is tested On
The procedure of steps 1 and 2 above is standard IEEE systems, viz., IEEE 14-bus, 30-
now repeated successively till the system is bus, 57-bus systems and on a practical
completely free of any critical system.
measurements. The detail description of this
phase is shown in Fig. 4. Figs. 6-9 give the measurement systems
at the end of phase 1, 2 , 3 and 4 for IEEE
Phase 3 Placement of RTUs under 14-bus system respectively. It can be seen
continsent loss of information L that the IEEE 14 bus system has total number
of 11 substations. It is assumed that the
It is sometimes possible that either the
RTU or the communication from an RTU may fail
and hence the information from an RTU may not ]Get the measurement set from phase 3 1
be available in the measurement set. One way
to overcome such situations is by using
pseudo-measurements. But if utilities would
like to enhance their measurement system
further for SCADA purposes and/or to make the

Get the measurement list from phase 2


4
Find the critical measurements
(line flow & bus injection measurements)
Is the no. of c:itical
measurements = O?
1

IConsider first critical measurement 1


.L
Supress this measurement from the
list. The system is unobservable
J,
Place an RTU to make the system
observable. Find the number of
critical measurements and store
them. Also store the number(s) of
bus(es) along with the number of of RTU whose loss of RTU whose loss
1inesfTr. at this bus(es) where an results in more results in more
RTU is placed to make the system no. of critical no. of groups.
observable. measurements. If there is a tie
& among these cases
Are all critical select that case
critica1
measurements covered ?
< which has more
no. of 1inesfTr.
measurements, covered by the
L ~
RTU .
Now consider that case which makes the
system to have less number of critical
measurements after placing the RTU to
cover this case. If there is a tie in
number of critical measurements, select
that case where the number of 1inesfTr.
incident are more at the bus where an RTU
is placed to cover this case. Place an
lthere in the list of RTUs. ,
&
I
RTU at the selected location to cover Go to phase 2 - placement of RTUs to
khis case. 1 make the system observable.
Fig. 4 . Flow chart for phase 3 . Fig. 5 . Flow chart for phase 4 .
385

R *Bus-lnjection
p R T U
-
o,Zero Bus-
measurement
+ Line -Flow
in jection tuiearur e me nt
Measur a m ent

Fig.7 Measurement System a t t h e end of


Fig.6 Measurement System a t t h e end of Phase 2 f o r I E E E 1 4 bus system.
Phase 1 f o r IEEE 1 4 Bus system.

R
R

Fig.8 Measurement System a t t h e end of Fig.9 Measurement System a t t h e e n d of


Phasa 3 f o r IEEE 1 4 bus system. a l l p h a s e s f o r IEEE 1 4 bus system.

R 50
Fig. 10 Measurement System a t t h e end of
all p h a s e s f o r I E E E 30 bus system.
386

specified locations of RTUs are substations stations, 5 2 transmission lines and 6


consisting of buses 1 , 2 , 8 and (5,6). The transformers [a system smaller than a
redundancy with this measurement system is practical system considered here]. It can be
found to be greater than s.0.. So at the end very easily seen that the proposed method is
of phase 1 there are 4 RTUs in the system ( more systematic and hence takes much smaller
Fig. 6 ) . Now in order .to make the system time than that of Aam et a1 [7]. Such
observable, one additi'onal RTU is required at functions usually take longer times and are
the substation consisting of buses 4 , 7 and 9. required only in planning stages.
(Fig.. 7 ) . Further to make the system free of
critical measurements, two more RTUs are .............................................
required at the substations containing buses Phase No. of RTUs for various systems
11 and 13 respectively (Fig. 8). Now in order (Figure in brackets is redundancy)
to consider the criterion of l o s s of IEEE IEEE IEEE Practical
information from any single RTU, one more RTU 14 bus 30 bus 57 bus system
is placed at the substation containing bus (61 buses)
10. However it is not possible to make the .............................................
system free of critical measurements due to No. of s f s
loss of information from an RTU because of in the system 11 26 42 47
the topology of the IEEE 14 bus system. Thus
at the end of all phases there are total PHASE 1 4(1.49) 7(1.31) 7(1.12) 12(1.30)
number of 8 RTUs for the IEEE 14 bus system PHASE 2 5(2.44) 13(2.39) 20(2.56) 24(2.75)
as shown in Fig. 9. PHASE 3 7(2.89) 14(2.47) 23(2.67) 33(3.26)
PHASE 4 8(3.07) 17(2.73) 24(2.72) -
Fig. 10 gives the measurement system for .............................................
IEEE 30-bus system at the end of all phases. Fig.11 Summary output for test systems
In the case of a practical system
considered for the study which has 65 buses s1. System Cost in million Rupees.
and 99 lines, it is found that 24 no. of RTUs No. option(a) option(b) option(c)
are required to make system fully observable. Proposed
If it is required to make the system free of method
critical measurements it is found that it .............................................
needs seven additional RTUs which implies 1 IEEE 14 bus 2.968 2.854 2.251
additional costs. Thus telemetering system 2. IEEE 30 bus 6.851 6.547 4.939
can be designed keeping in view the 3. IEEE 57 bus 11.363 10.569 6.748
objectives outlined in this paper and alsa' 4. Practical 13.148 12.508 9.691
the financial considerations. The system
measurement system arrived at this method ____________________-------------------------
gives a good spread of measurements since it Fig.12 Cost particulars for various
is designed based on observability of the alternatives. (options are as
system and absence of critical measurements. described in 'Introduction')
The summary output for the various test
systems studied is given in Fig. 11. In all
the cases it is found that it is not possible
to make the system free of critical
measurements due to loss of information from
an RTU. However loss of information from an IEEE 14-bus system
RTU keeps the system observable. All the phases executed 00 00 32.20
First three phases 00 00 13.62
The cost particulars for different executed
systems for various alternatives are given in IEEE 30-bus system
Fig.12. It is assumed that the cost of an RTU All the phases executed 00 19 44.64
is Rs. 0.2 million and cost of MW and W A R First three phases 00 01 09.44
transducers is Rs. 9000 each. The cost of executed
monitoring the status is assumed'to be Rs. IEEE 57-bus system
500 and the cost of voltage transducer is All the phases executed 02 13 18.38
taken as Rs. 2000. It can be easily seen that First three phases 00 30 42.68
the proposed scheme has the lowest cost and executed
meets the required criteria. Practical system
First three phases , 06 59 00.21
Fig. 13 gives the execution times on executed
VAX-11/750 of Digital Equipment Corporation,
USA, ( without floating point accelerator )
for first three phases and for all the phases
separately for each of the system studied.
With regard to the practical system it has
taken about 7 hours to execute first three
phases. For the purpose of comparison of CONCLUSIONS
time taken for design of measurement system
by a different method is referred to here, as Anew design methodology has been
available in published literature. Aam proposed for the telemetering' configuration
Holten and Gjerda [7] state that it took 13 of an Energy Management Systems based on a
hours on a 32-bit Nord-500 mini-computer systematic approach. The methodology ensures
[which is faster than VAX 11/750 used in our at planning stage
study] for a system consisting of 45
* complete observability of the system
387
* absence of critical measurements [8]. Nabil Abbasy and S.M.Shahidehpor, "An
(hence ability to detect bad data in Optimal set of measurements for the
all the measurements ) Estimation of Systems States in Large-scale
Power Networks*I, Journal of Electrical
* the observability'of' the system in Machines and Power Systems, Vol 15, No.4-5,
the case of loss of information for pp 311-332, 1988.
any single , RTU and absence of
critical measurements, if possible. [9]. Young Moon Park, Young Ayun Moon, Jin
Boo Choo and Tae Won Kwon, "Design of
* a good spread of the measurements in Reliable Measurement Systems for State
the system. EstimationBt,IEEE Trans. on Power systems,
V01.3 No.4, pp 830-836, Aug. 1988.
The proposed method has been tested on
standard IEEE system viz., IEEE 14-busI 30- [lo]. Hiroyuk Mori, Yasuo Tamura, IIComparison
bus, 57-bus systems. It is also tested on a of Approaches to meter placement in Power
practical utility system and the results are System Static-State Estimation" ,
presented and discussed. International Journal of Energy Systems,
VO1.8, No.3, pp 139-163, 1988.
ACKNOWLEDGMENTS
[ll]. G.R.Krumpholz, K.A.Clements, P.W.Davis,
The authors thank CMC Limited for 'Power System Observability : A Practical
providing facilities to carry out this work Algorithm Using Network Topology', IEEE
and for the support and encouragement given Trans. on Power Apparatus and Systems, Vol.
in bringing out this paper. The authors also PAS-99, No. 4, pp 1534-1542, July/Aug. 1980.
would like to acknowledge the reviewers for
their valuable comments and suggestions in [12]. K.A.Clements, 'Observability method
improving this paper. and optimal meter placement', Electrical
Power and Energy Systems, Vol. 12, No.2, pp
REFERENCES 88-93, April 1990.

[l]. A.Bose and K.A.Clements,'Real-Time [13]. K.A.Clements, G.R. Krumphoiz and


Modeling of Power Networks', proceedings of P.W.Davis, 'Power System State Estimation
IEEE, Vol. 75, NO. 12, pp 1607-1622, Dec. Residual Analysis : An Algorithm using
1987. Network Topology', IEEE Trans. on Power
Apparatus and Systems, Vol.PAS-100, pp 1779-
[2]. E.Handschin and C.Bongers, 'Theoretical 1787, April 1981.
and Practical Considerations in the Design of
State Estimators for Electric Power System', N.D.R.Sarma (S"81-Mf87-S1189)
Proceedings of the International symposium, was born in Kuchipudi, Andhra
'Computerized Operation of Power Systems Pradesh, India on 7th Oct.
(COPOS '75'), '18-20 Aug 1975 Brazil, edited 1961. He received the B.Tech
by Savu Crivat Savulescu pp 104-136. (Elect.) and M.Tech. (Elect.)
with Specialization in Power
[3]. A.Le Roy and P. Villiard, 'Application System Engineering from
of State Estimation Methods to the Evaluation Regional Engineering College,
of a Telemeasurement Configuration for Energy Warangal, India in 1983 and
Power Systems', Proceedings of the 1986 respectively. Presently he is working at
International Symposium, 'Computerised CMC Limited, Secunderabad. He has registered
Operation of Power Systems (COPOS '75'); 18- for Ph.D degree in the Dept. of Elect. Engg.
20 Aug.1975, Brazil, edited by Savu Crivat at IIT Delhi, India. His areas of interest
Savulescu pp 156-175. include Real Time control of Transmission and
Distribution Systems.
[4]. H.J. Koglin, 'Optimal Measuring system
for State Estimation', Proceedings, PSCC V.Veera was born in
Conference Paper 2.3112, Cambridge, Sept. Andhra Pradesh, India in 1956.
1975. He received B.E. (Elect.) from
Osmania University and M.Tech.
[5]. K . Phua, T.S. Dillon, 'Optimal Choice of (Electrical) with
Measurements for State Estimation', Power specialization in Power system
Industry and Computer Applications Engineerinq from I.I.T.,
Conference, Torento, Canada, 24-27, pp 431- Madras.He is working as systems
441, May 1977. Specialist at CMC Limited,
Secunderabad since 1982. His areas of
[6]. F.Mafaakher, A Brameller and J . F . interests are Energy Management Systems,
Bermudez, tlOptimum Metering design using Security Analysis, Power System Restoration.
fast-decoupled estimator", Proceedings, IEE,
Vol 126, No.1, pp 62-68, January 1979. K.S.Prakasa Rae (S'70-M'74-SM'81) was born in
Prakkilanka,A.P,India on July 15th , 1942. He
[7]. S. Aam, L.Holten and O.GJerda, 'Design received his B.E. (Elect. ) , M.E. (Power
of the Measurement System for State Systems) from Osmania Univ., in 1964 and 1966
Estimation in the Norwegian High-voltage respectively. He obtained his Ph. D degree
Transmission Network', IEEE Transaction on from the Indian Inst. of Tech. Kanpur, India
Power Apparatus and Systems, Vol.PAS-102, in 1974. He is presently a professor in the
No.12, pp 3769-3777, Dec. 1983. Elect. Engg. Dept. of 1.I.T Delhi, India. His
fields of interest are Power System Planning,
Operation and Reliability.

.. . . ... ... .. -. ..
..--

Vous aimerez peut-être aussi