Académique Documents
Professionnel Documents
Culture Documents
December 2007
FOREWORD
To meet the growing power demand in the country it is envisaged to add a Capacity of approximately 78577 MW during the 11th Five Year Plan. Due to limited amount of gas availability and limitations in Hydro and nuclear power generation augmentation, bulk of this Capacity Addition is being planned through about 52905 MW coal based thermal power projects only. During last few years with growing thermal power generation, coal supply is proving to be a major cause of concern. With such a massive coal based capacity addition planned, there were apprehensions that coal companies may not be able to cater to the enhanced coal requirement. In view of the above facts it was decided to allocate captive mines to the bulk users of coal and consequently many power utilities have been allocated captive mines. As the Power Utilities have no previous experience of coal mine development, it was apprehended that the mine development may get delayed which would in turn defeat the very purpose of allocation. Hence it was decided to closely monitor the coal mine development by power utilities to ensure: (i) (ii) (iii) (iv) Timely development of allocated mine. Sharing of information/experience between different captive coal mine allottees. Captive mine development before COD of the coal based thermal unit. Removal of any road blocks being faced by the captive coal mine developers.
A monitoring committee consisting of officials from CEA and NTPC was formed for the above purpose. The monitoring committee finalized the list of important milestones to be monitored and the captive mine allottees were asked to submit the status of their mines in the format developed and approved by the committee. Based on the status furnished by the allottees broad status of different captive coal mines has been prepared up to December, 2007 for the III quarter OctDec... It has also been decided that the Broad status shall be continually updated and shall be issued quarterly for the quarters Jan-March, April-Jun, and July-Sept & Oct-Dec. The same will also be put on CEA web site so that all concerned may have the updated status of Coal Mine Block development.
INDEX
Sl. No
1 A 2 3 4 5 6 7 8 9 10 11 12 13 B 14 15 16 17 18 19 20 21 22 23 24
Contents
Summary of Captive Coal Mines Allocated to Power utilities Central Sector Broad Status of Captive Coal Mine Development NTPC Pakri Barwadhi Broad Status of Captive Coal Mine Development NTPC Kerandoi Broad Status of Captive Coal Mine Development NTPC Chattibariatu Broad Status of Captive Coal Mine Development NTPC Dulanga Broad Status of Captive Coal Mine Development NTPC Talipalli Broad Status of Captive Coal Mine Development CIL&NTPC JV Brahmini & Chichropatsimal Broad Status of Captive Coal Mine Development DVC.- Barjora (N) Broad Status of Captive Coal Mine Development DVC.- Kagra Joydev Broad Status of Captive Coal Mine Development DVC.- Kasta (E) Broad Status of Captive Coal Mine Development TVNL & DVC JV 50:50 ( TVNL Lead company) Gandulpara Broad Status of Captive Coal Mine Development JV of M/s Hindalco Industries Ltd., M/s Mahanadi coalfields Ltd and M/s NLC Talabira II & III Broad Status of Captive Coal Mine Development Sasen UMPP Chhatrasal State Sector Broad Status of Captive Coal Mine Development CSEB Gidhmuri Broad Status of Captive Coal Mine Development CSEB Pathurai Broad Status of Captive Coal Mine Development CSEB Parsa Broad Status of Captive Coal Mine Development CMDCL..- Tara Broad Status of Captive Coal Mine Development WBPDCL.-Pachwara (N) Broad Status of Captive Coal Mine Development WBPDCL.-Barjora, Gangaramchak & Bhadulla- Bangaramchak. Broad Status of Captive Coal Mine Development KPCL.-Barang-I (1 to 4), Manoradeep & Kiloni Broad Status of Captive Coal Mine Development TVNL.- Badam Broad Status of Captive Coal Mine Development TVNL Rajbar ( E&D) Broad Status of Captive Coal Mine Development PSEB (Panem Coal Mines Ltd.).Pachwara (Central) Broad Status of Captive Coal Mine Development Orissa Mining Corp.- Utkal-D
Page No.
1-3 5 6 7 8 9 10 11 12 13 14 15 16 18 19 20 21 22 23 24 25 26 27 28
Sl. No
25 C 26 27 28 29 30 31 32
Contents
Broad Status of Captive Coal Mine Development JV of MSPGCL & GSECL ( Mahaguj Colliries Ltd) Machhakatta & Mahanadi Private Sector Broad Status of Captive Coal Mine Development GVK Power Ltd. ( Goidwal Sahib).-Tokisud (N) sub captive Coal Mine , Hazaribagh.. Broad Status of Captive Coal Mine Development Jindal Power Ltd.- Gara- Palma IV (2 &3) Broad Status of Captive Coal Mine Development Utkal Coal Ltd..- Utkal C Broad Status of Captive Coal Mine Development Raipur alloys & Steel Ltd.- Gare Palme IV/7 Broad Status of Captive Coal Mine Development Bhushan Ltd.- Jamkhani Broad Status of Captive Coal Mine Development NALCO- Utkal-E Broad Status of Captive Coal Mine Development- JV of Hindalo & Eassar.- Mahan
Page No.
29
31 32 33 34 35 36 37
INDEX
Sl. No
1 A 2 3 4 5 6 7 8 9 10 11 12 13 B 14 15 16 17 18 19 20 21 22 23 24
Contents
Summary of Captive Coal Mines Allocated to Power utilities Central Sector Broad Status of Captive Coal Mine Development NTPC Pakri Barwadhi Broad Status of Captive Coal Mine Development NTPC Kerandoi Broad Status of Captive Coal Mine Development NTPC Chattibariatu Broad Status of Captive Coal Mine Development NTPC Dulanga Broad Status of Captive Coal Mine Development NTPC Talipalli Broad Status of Captive Coal Mine Development CIL&NTPC JV Brahmini & Chichropatsimal Broad Status of Captive Coal Mine Development DVC.- Barjora (N) Broad Status of Captive Coal Mine Development DVC.- Kagra Joydev Broad Status of Captive Coal Mine Development DVC.- Kasta (E) Broad Status of Captive Coal Mine Development TVNL & DVC JV 50:50 ( TVNL Lead company) Gandulpara Broad Status of Captive Coal Mine Development JV of M/s Hindalco Industries Ltd., M/s Mahanadi coalfields Ltd and M/s NLC Talabira II & III Broad Status of Captive Coal Mine Development Sasen UMPP Chhatrasal State Sector Broad Status of Captive Coal Mine Development CSEB Gidhmuri Broad Status of Captive Coal Mine Development CSEB Pathurai Broad Status of Captive Coal Mine Development CSEB Parsa Broad Status of Captive Coal Mine Development CMDCL..- Tara Broad Status of Captive Coal Mine Development WBPDCL.-Pachwara (N) Broad Status of Captive Coal Mine Development WBPDCL.-Barjora, Gangaramchak & Bhadulla- Bangaramchak. Broad Status of Captive Coal Mine Development KPCL.-Barang-I (1 to 4), Manoradeep & Kiloni Broad Status of Captive Coal Mine Development TVNL.- Badam Broad Status of Captive Coal Mine Development TVNL Rajbar ( E&D) Broad Status of Captive Coal Mine Development PSEB (Panem Coal Mines Ltd.).Pachwara (Central) Broad Status of Captive Coal Mine Development Orissa Mining Corp.- Utkal-D
Page No.
1-3 5 6 7 8 9 10 11 12 13 14 15 16 18 19 20 21 22 23 24 25 26 27 28
Sl. No
25 C 26 27 28 29 30 31 32
Contents
Broad Status of Captive Coal Mine Development JV of MSPGCL & GSECL ( Mahaguj Colliries Ltd) Machhakatta & Mahanadi Private Sector Broad Status of Captive Coal Mine Development GVK Power Ltd. ( Goidwal Sahib).-Tokisud (N) sub captive Coal Mine , Hazaribagh.. Broad Status of Captive Coal Mine Development Jindal Power Ltd.- Gara- Palma IV (2 &3) Broad Status of Captive Coal Mine Development Utkal Coal Ltd..- Utkal C Broad Status of Captive Coal Mine Development Raipur alloys & Steel Ltd.- Gare Palme IV/7 Broad Status of Captive Coal Mine Development Bhushan Ltd.- Jamkhani Broad Status of Captive Coal Mine Development NALCO- Utkal-E Broad Status of Captive Coal Mine Development- JV of Hindalo & Eassar.- Mahan
Page No.
29
31 32 33 34 35 36 37
Coal Blocks allotted to Power Utilities. Sl.No Name of Block Total reserve Mill.Ts Date of Allotment Name of Utility End use Project. Mile stones
Zero Date Purchase of Submission & Geological Approval of Report from Mining Plan MOC
Schedule Schedule period/Actual period/Actual / / Anticipated Anticipated
Mining Land acquisition Infrastruct Coal Mining and start ure of coal production Lease (Nongrant Forest/Forest)
1 A 1
2 Central Sector Pakri Baradih (Jharkhand) Kerandari (Jharkhand) Chatti Bariatu (Jharkhand) Dulanga (Orissa) Talaipalli (Chhatisgarh) Brahmini & Chichropatsimal (1900+356) (Orissa) Barjora (N) (WB) Khagra Joydev (WB) Kasta (E) (WB) Gondulpara PhI: 62.2 & Ph-II: 54.45 Talabira - II &III ( II-152.3) 1436
11.10.04
NTPC
Basket of NTPC Projects Barh St-II,(2x660 MW) Barh St-II (2x660 MW) Darlipalli, (4x800 =3200MW) Lara, (4000 MW) Kahalgaon Exp. & Farakka Exp. Mejia U-7&8
30.08.05
15.03.06 /25.8.06(A)
15.01.07/ March.08
15.01.07/ March.08 15.11.08/ 15.05.08 15.11.08/ 15.05.08 15.05.09/ 15.05.09 15.11.09/ 15.11.09
NR
Mar.,09/ Mar.,09 -
229
25.01.06
NTPC
31.12.06
NR
243
25.01.06
NTPC
31.12.06
NR
4 5 6
NR NR
61.11
03.03.05
In
103.8
03.03.05
DVC
Mejia U-7&8
13.10.04
04/05 (A)
01/06 /
28.9.06 (A)
In
9 10
70 116.65
03.03.05
Mejia U-7&8
13.10.04
Dec-06/ 12/1/2006 / NF Jun-07/Applicati 10/06 on (Application 12/06 12/06 / 06/07 / Submitt NQ Forest ed Land GR not received as yet
Jun.,07/ -
-/Mar.,07- Jun.,08/---
Jun-07
Sep.,2008/ April.,09
April.,2010
11
152.3
10.11.05
12
Chhatrasal
150
26.10.06
JV.of NLC & M/s Hindalco & M/s M h Sasan di Sasan UMPP (4000 MW) (PFC) SVUMPP
2010-11
6042.86
Date of Allotment
Name of Utility
Mile stones
Zero Date Purchase of Submission & Geological Approval of Report from Mining Plan MOC Schedule Schedule period/Actual period/Actual / / Anticipated Anticipated 7 8
Mining Land acquisition Infrastruct Coal Mining and start ure of coal production Lease (Nongrant Forest/Forest)
1 B 1
2 State Sector Gidhmuri ( Chhatisgarh) Pathuria ( Chhatisgarh) Parasa ( Chhatisgarh) Tara (Chhatisgarh) Pachwara (N) (Jharkhand) 80.27
11
23.09.04
CSEB
Bhaiyathan TPS (2x500 MW) Bhaiyathan TPS (2x500 MW) Bhaiyathan TPS (2x500 MW) Prem Nagar TPS JV of IFFCOCSEB Sagardigi (2x300 MW), Bakereshwar (2x210 MW), Santaldh (1x250 MW) ---Do-----
10.10.04
07.05.05 (A)
Jan.,07/ Oct.,07
'06/08 (R&R) 12/07 (Forest) /10/07-04/08 '06/08 (R&R) 12/07 (Forest) /10/07-04/08 ----/13.11.07
Mar.,09/
2010-11
269.2
23.09.04
CSEB
10.10.04
07.05.05 (A)
Jan.,07/ Oct.,07
Mar.,09/
2010-11
3 4
100 25.04
02.08.06 13.08.03
CSEB CMDCL
13.02.05/ 13.10.07
386
26.04.05
WBPDCL
8 9 10
Bajora, Gangaramchak (Kasta) & BhadullaGangaramchak Barang-I (1 to 4) Manoradeep & Kiloni (103 Minable) (M h Badam t ) (Jharkhand) Rajbar (E&B) (Jharkhand) Pachwara Central 289 ( Minable) (Jharkhand) Utkal-D (Orissa)
22
23.06.03
WBPDCL
23.06.03
06.08.03/ 28.08.04(A)
22.06.04-22.12.06/----
22.12.04/ 28.11.05(A)
22.06.05 / Awaited
22.06.06/----
---
22.12.06/
2007-08
103
Nov.,03
KPCL
Ballary -1 (500 MW) + Raichur-8( 250 MW) Tenughat st-III (3x210 MW)
16.07.04
24.02.04
--/08.12.04 (A)
--/18.05.06(A)
In progress 2.09.06 (A
In progress
In progress
April.,08
03.11.03
03.11.03
May.,05/ June.,06
May.,05/ Oct.,06
-----/10/08 April.,20012
26.12.01
11
153.31
19.12.03
29.07.02
09.02.02/ 08.02.02(A)
29.01.04/ 06.01.05
29.07.04 /16.11.0 4
Comp.
Comp.
-/ March.,06 (A)
- / July.,07
Machhakatta & Mahanadi 12 1250 (B)Total Reserve State Sector ( Million MT) Sl.No Name of Block 3068.32 Total reserve Mill.Ts Date of Allotment 06.02.06
Koradi (2x500 MW) & Chandrapura (1x500 MW) Ukai (1x500 MW)
Nov.,11/ Aug.,11
Name of Utility
Mile stones
Zero Date Purchase of Submission & Geological Approval of Report from Mining Plan MOC Schedule Schedule period/Actual period/Actual / / Anticipated Anticipated 7 8
Mining Land acquisition Infrastruct Coal Mining and start ure of coal production Lease (Nongrant Forest/Forest)
1 ('C) 1
2 Private Sector
11
Tokisud (N) sub 51.9 07.01.02 captive coal Mine, Hazaribagh (Jharkhand) Gare-Palma IV 2 246 01.07.98 &3 246 ( Mine-able reserve 180 mt) (Chhatisgarh) 130.384 29.05.98 Utkal-C (130.384 Minable) (Orissa) Gare Palme-IV/7 (Chhatisgarh) Jamkhani (Orissa) Utkal -E ( 122.48 / 61.89 Minable) (O i Mahan ) 110 122.48
07.01.02
21.02.02/ 18.03.04(A)
07.07.03/ 30.09.07
07.07.03/ 07.12.07
07.07.04/ 07.03.08
07.01.07/ 07.06.10
07.01.06/ 01.01.09
01.07.98 -/ May.,2000
30.04.99/ 25.01.01
30.06.99/ 22.09.04
-/ 06.09.04
April,06/ 15.04.05
29.06.98 Utkal Coal Chaudwar (108 Ltd. MW), UPLTPP PhI ( 120 MW), Ph-II (240 MW)
23.04.06/ 05.10.06
23.04.06/ Jan.,08
23.10.06 April,07- Oct.,07/ July.,07 / April.,08 12.05.05 (A) 24.04.02/ 25.02.07(A) 30.12.07/ 31.12.09
4 5 6
25.04.2000 Raipur alloy Captive TPS & Steel Ltd. 03.11.03 27.08.04 Bhushan Ltd NALCO Bhushan Ltd (40+60 MW) Captive TPS (2x120 MW)
25.04.2000 08.06.00/ 09.09.00(A) 12.11.03 27.08.04 05.05.05/ 05.05.05 12.10.04/ 22.04.05 (A)
144
12.04.06 HINDALCO 1000MW TPP of & ESSAR ESSAR & 650 MW 12.04.06 of HINDALCO Ltd.
27.05.06/ 15.06.06(A)
11.12.06/ 11.05.06
11.04.07/
Nov.,07
11.11.07/ Nov.,07
11.04.08 / Sep.,08
----/March.,08
Sep.,08
11.10.09/
10/09
('C) Total Reserve Private Sector ( Million MT) Grand Total (A+B+C)
804.764 9915.944
CENTRAL SECTOR
12/2008
2019-20
RATE OF PRODUCTION (mtpa) (As per Approved Mining Plan) 2018-19:14.5 2013-14:-10.00 2008-09:- 2.1 2019-20:15.0 2014-15:-10.50 2009-10:- 4.17 2015-16:-11.5 2010-11:- 5.5 2016-17:-12.5 2011-12 :-8.0 2017-18: 13.5 2012-13 :- 9.06 FULL CAPACIT RATE OF 15 PRODUCTION (mtpa)
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC
Schedule Dates Schedule Actual / period Anticipat ed ZERO DATE (30.08.05) 11/04 04/05 (A)
Brief Status
Text portion of GR received from MOC on 30.08.05. Coordinated block boundary received From CMPDI on 30.08.05. CBM block boundary issue (ONGC/ION) is still under resolution. As advised by MOC, Mining plan was revised to 15 MTPA and re-submitted to MOC on 12.05.06. Mining plan approved by MOC for 15 Mty on 25.08.06. EIA/EMP application submitted on 28.06.07 comments from expects Committee MOEF received on 5.10.07 response being given. Noc/Consent is awaited from Distt. Administration.
01/07
03/08
4 5 6 7 8
Forest Clearance Mining Lease grant Land acquisition (NonForest/Forest) Infrastructure Coal Mining and start of coal production
03/08
* As per NTPCs best effort schedule, however, subject to timely clearances & notifications from state/central Govt. organizations and timely completion of railway link for coal evacuation.
2016-17
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan
Schedule Dates Schedule Actual / period Anticipated ZERO DATE 31.12.06 31.01.07(A) . 11/07 & 01/08 11/07 & 01/08
Brief Status
4 5 6
Forest Clearance Mining Lease grant Land acquisition (NonForest/Forest) Infrastructure Coal Mining and start of coal production
Work awarded to M/s ACMM on dated 04.04.07, work almost completed. Mining Plan to be submitted to MOC in Month Nov.07. Work under progress One season data collected. Approval for TOR & Pre FR obtained as per MoEF guidelines. Preliminary proposal submitted on 26.03.2007 Clarification sought from MoC Section 4 Gazette notification published on 26.10.07. Section 7 application to be submitted to MoC shortly.
11/09
7 8
12/10
05/10
2015-16
7.0
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC GR availability with boundary issue resolution from ONGC 2 Submission & Approval of Mining Plan
Schedule Dates Schedule Actual period / Anticip ated ZERO DATE 31.12.06 18.03.0 6(A) 11/07 & 01/08 11/07 & 01/08 11/07 & 05/08 05/08 NR 05/10 11/09 12/10 06/10
Brief Status
GR made available to NTPC on 18.03.06 by Central Mine Planning and Design Institute. Delineated block boundary is still awaited.
4 5 6 7 8
Forest Clearance Mining Lease grant Land acquisition (NonForest/Forest) Infrastructure Coal Mining and start of coal production
Work awarded to M/s ACMM on dated 04.04.07, work almost completed. Mining Plan to be submitted to MOC in Month Nov.07. Work is under progress. One season data collected. Approval for TOR & Pre FR obtained as per MoEF guidelines. Preliminary proposal submitted on 26.03.2007 Clarification sought from MoC Application for section 7 notification was submitted to MOC on 19,10,07
*Capacity shall be based on approval of Mine Plan which is under preparation. Status of linked project - Barh St.-II (2X800/660 MW): FR has been approved. Land & water confirmation received. Site specific studies are in progress, Interim EIA report under finalization. Main plant award Expected shortly.
Sl No
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 3 Submission & Approval of Mining Plan EIA/EMP Studies & Approval
Schedule Dates Brief Status Schedul Actual / e period Anticipated Interim GR available to NTPC on ZERO DATE 18.03.06 by Central Mine Planning 18.03.06** 18.03.06 (Interim) 15.05.0815.07.08 15.11.0815.05.09 15.05.09 NR 15.11.10 15.05.0815.07.08 15.11.0815.05.09 15.05.09 NR 15.11.10
and Design Institute (CMPDIL). Draft GR received on 29.09.07 from MECL is under review.
Mining plan can be prepared after availability of complete GR Application for MOEFs clearance on Pre-FR & TOR for engaging the agency for EIA/EMP studies is being prepared. Clarification sought from MOC Section 4 Gazette notification published on 18.10.07. Section 7 application under preparation, to be submitted to MOC shortly.
4 5 6
Forest Clearance Mining Lease grant Land acquisition (NonForest/Forest) Infrastructure Coal Mining and start of coal production
7 8
15.05.11
15.05.11
** The block was partially explored by CMPDIL. 4000 mts of drilling to be done. Accordingly NTPC has engaged Mineral Exploration corporation (MECL ) for balanced exploration work and MECL started work on 23.11.06.expected Zero date 31.12.07 arrived shall be the date by which MECL may submit complete GR after completion of detailed exploration & analysis of data. Till date (25.06.07) 3326.65 mts of drilling completed by MECL. * Capacity shall be based on approval of Mine plan, which is under preparation. Status of linked project Darlipalli (3200 MW): In principal Land & water clearance received. Site specific studiesare in progress, Main plant award Expected shortly.
2011-12
2023-24
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval 4 5 6 7 8 Forest Clearance Mining Lease grant Land acquisition (NonForest/Forest) Infrastructure Coal Mining and start of coal production
Schedule Dates Schedule Actual / period Anticipated ZERO DATE 30.06.08* 24.02.06 (Interim) 15.11.0815.01.09 15.05.0915.11.09 15.11.09 NR 15.05.11 15.11.11
Brief Status
Regionally explored (by GSI) only. Interim GR made available to NTPC on 24.02.06.
Application for MOEFs clearance on Pre-FR & TOR for engaging the agency for EIA/EMP studies is being prepared. Clarification sought from MOC
Section 4 Gazette notification published on 2610.07. Section 7 application under preparation, to be submitted to MOC shortly.
**The block was regionally explored by GSI. About 4000 mts of drilling to be done. Accordingly NTPC has engaged Mineral Exploration corporation (MECL ) for balanced exploration work and MECL started work on 11.08.06. Expected Zero date 30.06.08 arrived shall be the date by which MECL may submit complete GR after completion of detailed exploration & analysis of data. Till date (30.06.07) 32501.85 mts of drilling completed by MECL. Exploration completion expected by Dec.,07. * Capacity shall be based on approval of Mine plan, which is under preparation Status of linked project Lara (4000 MW): Land & water commitment still awaited from State Govt. Topographical survey and EIA work awarded on 25.10.06 GO- Tech investigation is under award process.
BENEFICIARY PROJECT COMMISSIONING SCHEDULE OF PROJ ANTICIPATED DATE OF COMMENCEMENT OF COAL PRODUCTION ANTICIPATED DATE OF ATTAINING FULL CAPACITY
1900 + 356 TOTAL RESERVE (GEOLOGICAL/MINEABLE) (Million Tonnes, mt) DATE OF ALLOTMENT 25.01.06 TYPE OF MINING OC RATE OF PRODUCTION (mtpa)
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval 4 Forest Clearance 5 Mining Lease grant 6 7 8 Land acquisition (NonForest/Forest) Infrastructure Coal Mining and start of coal production
Schedule Dates Schedule Actual / period Anticipated ZERO DATE 25.01.06 18.03.06 (Interim)
Brief Status
Allocation letter not yet issued by MOC. All milestones pending.
MoC vide letter dated 25.01.06 addressed to Chairman, Coal India Ltd. have communicated the decision taken during the meeting held under the Chairmanship of Principal Secretary to Honble Prime Minister on 08.12.06, In respect of operation of Brahmini (1900MT) & Chichro Patsima (356 MT) blocks through a 50:50 joint venture between CIL and NTPC under Ministry of Coal. Detailed Schedule will be communicated after formation of JV. Accordingly Zero date and other milestones shall be arrived by JV in due course of time. Present Status: MOU between NTPC & CIL has been signed on 15.03.07. A joint business group has been constituted. Draft JV agreement sent to CIL on 11.06.07. Status of linked project Kahalgaon Exp. (500 MW) & Farakka Exp. (500 MW): Farakka order placed on BHEL in Oct.,06
10
2009-10
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval Approval of MOEF in terms of Reference (ToR under New guide lines dt. 14.09.06
Schedule Dates Schedule Actual / period Anticipated ZERO DATE (13/10/2004) 04/2005(A) 01/2006 09/2006 25.05.06(A)
Brief Status
Application on 16.11.06 submitted
4 5 6 7 8
Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
GR of Bajora(N) Purchased. MP submitted on 08.03.06 to MOC & approved on 24.08.06. Presentation made on 20.11.06. Letter prescribing ToR received on 27.12.06.Application will be submitted by 15.01.07 for public hearing by State Pollution Board (SPB). For EMP clearance application will be submitted after public hearing Application submitted on 16.11.06 Submitted on 20.10.06 Submitted
Identification of transportation of coal to MTPS : The issue taken up with Railway for installation of captive line. TITES has been entrusted for surveying activity. Status of linked project: Mejia U- 7&8 (2X250 MW): LOA for Mejia U-7 &8 placed on M/s BHEL
11
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval Approval of MOEF in terms of Reference (ToR under New guide lines dt. 14.09.06
Schedule Dates Schedule Actual / period Anticipated ZERO DATE (13/10/2004) 04/2005(A) 01/2006 09/2006
Brief Status
GR of Khagrapurchased. Joydev
4 5 6 7 8
Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
by MoC on 28.09.06. Presentation made on 20.11.06. Letter prescribing ToR received on 27.12.06.Application will be submitted by 15.01.07 for public hearing by State Pollution Board (SPB). For EMP clearance application will be submitted after public hearing. No forest Land Submitted on 24.11.06 Submitted.
04/2009
Identification of transportation of coal to MTPS : Natundanga ( an abandoned ECL sidings near Pandabeshwar Station has been earmarked. Taken up with Railway. Status of linked project: Mejia U- 7&8 (2X250 MW): LOA for Mejia U-7 &8 placed on M/s BHEL
12
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC
Schedule Dates Schedule Actual / period Anticipated ZERO DATE (13/10/2004) 04/05 (A)
Brief Status
GR not yet received from ECL as ECL is yet to finalize their Asset situated over this block. Persuaded with ECL to obtain the said at the earliest. Milestones to be finalized after receipt of GR. Preparation of mining plan is pending.
2 3 4 5 6 7 8
Submission & Approval of Mining Plan EIA/EMP Studies & Approval Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
Status of linked project: Mejia U- 7&8 (2X250 MW): LOA for Mejia U-7 &8 placed on M/s BHEL
13
COMMISSIONING SCHEDULE OF PROJECT ANTICIPATED DATE OF COMMENCEMENT OF COAL PRODUCTION ANTICIPATED DATE OF ATTAINING FULL CAPACITY
OC 1st year : 0.60 2nd year : 1.50 3rd Year : 2.00 4th Year : 2.00 2.0 +2.0
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval 4 5 6 7 8 Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
Brief Status
04/2010
Allocated on sharing basis with M/s TVNL and DVC at the rate of 50:50. Gazette notification is due by MOC for which mining plan can not be prepared.
14
BENEFICIARY PROJECT COMMISSIONING SCHEDULE OF PROJECT ANTICIPATED DATE OF COMMENCEMENT OF COAL PRODUCTION ANTICIPATED DATE OF ATTAINING FULL CAPACITY
TOTAL RESERVE (GEOLOGICAL/MINEABLE) (Million Tonnes, mt) DATE OF ALLOTMENT TYPE OF MINING
May.,2009
Sl No.
Milestones
Brief Status
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 3 4 5 6 7 8 Submission & Approval of Mining Plan EIA/EMP Studies & Approval Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
2010-11
The joint venture agreement is proposed to be signed by 30.06.07. Thereafter, other activities/milestone for the development will be achieved in due course. All pre- mining activities are pending.
15
3.0
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval 4 5 6 7 8 Forest Clearance Mining Lease grant Land acquisition (NonForest/Forest) Infrastructure Coal Mining and start of coal production
Brief Status
Approx.2000m exploration balance. Drilling suspended for want of forest clearance. As per CMPDIL .GR is expected to be ready after 6 months of completion of drilling. Obtained MOE&F clearance by CMPDIL is critical Status of linked project Sasan Ultra Mege Power Project (4000 MW): Bidding completed.
16
STATE SECTOR
17
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan
Schedule Dates Schedule Actual / period Anticipated ZERO DATE 10.10.04 7/5/05(A) 06/06 02/07
Brief Status
01/07
10/07
4 5 6
Order placed on CMPDIL for preparation of MP, FR and DPR on 30.05.05. MP submitted on 22.08.06 and presentation made on 04.10.06 Order placed on M/s Kirloskar Consultants Ltd. For preparation of rapid EIA and EMP studies on 14.09.05. Draft EIA has been received & its finalization is held up for want of approval of MP. Tender for work for forest clearance opened on 07.11.05 and shall be finalized shortly. After brief departmental survey officers called for survey, demarcation, preparation of land use and collection of and details etc
7 8
12/07 03/09
12/08 2010-11
Consultants appointed for framing NIT for JV documents. Pending Milestones need to be expedited: Mining Plan approval, Mining lease, Forest, Environmental and land acquisition. Status of linked project Bhaiyathan TPS (2x500 MW):
18
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval
Schedule Dates Schedule Actual / period Anticipated ZERO DATE 10.10.04 7/5/05(A) 06/06 02/07
Brief Status
01/07
10/07
4 5 6
Order placed on CMPDIL for preparation of MP, FR and DPR on 30.05.05. MP submitted on 22.08.06 and presentation made on 04.10.06. Order placed on M/s Kirloskar Consultants Ltd. For preparation of rapid EIA and EMP studies on 14.09.05. Draft EIA has been received & its finalization is held up for want of approval of MP. Tender for work for forest clearance opened on 07.11.05 and shall be finalized shortly. After brief departmental survey officers called for survey, demarcation, preparation of land use and collection of land details etc
7 8
Consultants appointed for framing NIT for JV documents. Pending Milestones need to be expedited: Mining Plan approval, Mining lease, Forest clearance, Environmental clearance and land acquisition. Status of linked project Bhaiyathan TPS (2x500 MW):
19
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval
Brief Status
4 5 6
Order placed on CMPDIL for preparation of MP, FR and DPR on 30.05.05 Order placed on M/s Kirloskar Consultants Ltd. For preparation of rapid EIA and EMP studies on 14.09.05 Tender for work for forest clearance opened on 07.11.05 and shall be finalized shortly. Application submitted for prospecting license After brief departmental survey officers called for survey, demarcation, preparation of land use and collection of land details etc.
7 8
Consultants appointed for framing NIT for JV documents. Unexplored block. Status of linked project Bhaiyathan TPS (2x500 MW):
20
Sl Mining Plan submitted for approval Milestones No. Mine Block already explored. Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval 4 5 6 7 8 Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
Schedule Dates Actual / Schedule period Anticipated ZERO DATE 13.08.2003 20.04.05(A) 13.04.04 13.02.05 13.04.06 13.10.07 13.08.07 13.08.05 13.11.07 13.11.07 13.08.06 03/08 13.10.08 10/08
Brief Status
Pending Milestones need to be expedited: Mining Plan approval, Mining lease, Forest clearance, Environmental clearance and land acquisition Status of linked project: Prem Nagar TPS JV of IFFCO-CSEB:
21
DATE OF ALLOTMENT TYPE OF MINING RATE OF PRODUCTION, mtpa FULL CAPACITY RATE OF PRODUCTION, mtpa
2.5
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 2 3 4 5 6 7 8 Purchase of Geological Report from MOC Submission & Approval of Mining Plan EIA/EMP Studies & Approval Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
Brief Status
Prospecting is almost completed. GR under preparation and shall be submitted to CMPDIL for assessment and grading.
Status of linked project: Sagardighi (2X250MW) Unit-1-. Synchronization expected in 11/2007. Unit-2-, Synchronization expected in 01/2008.
22
BENEFICIARY PROJECT COMMISSIONING SCHEDULE OF PROJECT ANTICIPATED DATE OF COMMENCEMENT OF COAL PRODUCTION ANTICIPATED DATE OF ATTAINING FULL CAPACITY
TOTAL RESERVE (GEOLOGICAL/MINEA BLE) Million Tonne, mt DATE OF ALLOTMENT TYPE OF MINING RATE OF PRODUCTION (mtpa) FULL CAPACITY RATE OF PRODUCTION(mtpa)
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 2 3 4 5 6 7 8 Purchase of Geological Report from MOC Submission & Approval of Mining Plan EIA/EMP Studies & Approval Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
Schedule Dates Schedule Actual / period Anticipated ZERO DATE 23.06.2003 06.08.03 22.02.04 22.06.04/ 22.12.06 22.12.04 22.06.05 22.06.06 28.08.04(A) 27.06.05(A)
Brief Status
Applied for Mine lease. Production shall start immediately after grant of mine lease.
28.11.05(A)
22.12.06
2007-08
Status of linked project: Sagardighi (2X250MW) Unit-1-. Synchronization expected in 11/2007. Unit-2-, Synchronization expected in 01/2008.
23
COMMISSIONING SCHEDULE OF PROJECT ANTICIPATED DATE OF COMMENCEMENT OF COAL PRODUCTION ANTICIPATED DATE OF ATTAINING FULL CAPACITY Sl No.
Milestones
Brief Status
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 2 3 Purchase of Geological Report from MOC Submission & Approval of Mining Plan EIA/EMP Studies & Approval
4 5 6 7
8 Coal Mining and start of coal production . JV for mine exploration formed. Status of linked project: Bellary Unit-1 Synchronized on 03.12.07.
MP approved vide letter No. 13016/12/2004-CA dated 08.12.04. 18/05/06(A) Environment clearance obtained vide L/No.J-11015/400/2005IA.II(M) dated 18.05.06 from MOEF. As per one of the conditions in section B clause (xvi) clearance has been published on 24.05.06 in local newspaper Navbharat ( Hindi) & Lokmat ( Marathi) St-I forestry clearance in progress 22.09.06(A) Mining Lease deed has been executed on 22.09.06. Land acquisition is being made vigorously Permission for opening the mine obtained from DGMS vide letter dated 4.6.2007. Mobilization of equipment for mining operation started. Most of the mining equipment has already reached site . 04/2008
Note: Pre mining activities started. Coal production expected to start during 2007-08. Railway siding work is in progress at Magri.
24
12/2008
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval 4 5 Forest Clearance Mining Lease grant
Schedule Dates Schedule Actual / period Anticipated ZERO DATE 03.11.2003 11/03 07/04 05/05 05/05 11/03(A) 12/04(A) 06/06 10/06
Brief Status
Land acquisition
Application for grant of Mining lease submitted to DC, Hazbag on 26.05.05. Forwarded to Distt Mining Officer Application for Land acquisition submitted to DC, Hazbag on 19.11.05. Application for diversion of forest land submitted on 19.11.05
7 8
Status of linked project: TENUGHAT ST. III (3X210 MW): Finalization of EPC contractor is in progress.
25
OC 1st year : 1.00 2nd year : 3.00 3rd Year : 5.00 4th Year : 7.50 7.5
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC
Brief Status
Raibar (E&D ) Coal block is only regionally explored. It will take about 3 years to complete detailed exploration and preparation of GR. Hence the delay in commencement of coal production.
2 3 4 5 6 7 8
Submission & Approval of Mining Plan EIA/EMP Studies & Approval Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production 04/2012
26
03/09
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval 4 Forest Clearance
Schedule Dates Actual / Schedule period Anticipated ZERO DATE 29.07.02 09/02/02 19/12/02 29/01/04 29/01/04 08/02/02(A) 05/11/03(A) 04/01/05(A) 06/01/05 St.II clearance pending 16/11/04 completed Completed 03/06 (A)
Brief Status
5 6 7 8
Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
29/07/04
Status of linked project: LEHRA MOHABAT GHTP ST II (2x250 MW) (U-3&U-4): U-3 : synchronization expected in Nov.,.07. U-4 : : synchronization expected in Feb.,08
27
Sl No.
Milestones
Brief Status
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval 4 5 6 7 8 Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production 07/2007
Pending Milestones Mining lease execution, Forest clearance and land acquisition Status of linked project: Captive
28
COMMISSIONING SCHEDULE OF PROJECT ANTICIPATED DATE OF COMMENCEMENT OF COAL PRODUCTION ANTICIPATED DATE OF ATTAINING FULL CAPACITY
Mid 2014
Sl No.
Milestones
Brief Status
Exploration under progress in Machakatta by CMPD. Exploration to be taken up in Mahanadi. GR is expected to be available by March.,2008.
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC Submission & Approval of Mining Plan EIA/EMP Studies & Approval Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production GR will be ready by 12/2008.
2 3 4 5 6 7 8
11/2011
08/2011
29
PRIVATE SECTOR
30
BENEFICIARY PROJECT COMMISSIONING SCHEDULE OF PROJECT ANTICIPATED DATE OF COMMENCEMENT OF COAL PRODUCTION ANTICIPATED DATE OF ATTAINING FULL CAPACITY
TOTAL RESERVE (GEOLOGICAL/MINEABLE) Million Tonne, mt DATE OF ALLOTMENT TYPE OF MINING RATE OF PRODUCTION, mtpa FULL CAPACITY RATE OF PRODUCTION, mtpa
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval 4 5 6 7 8 Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
Schedule Dates Schedule Actual / period Anticipated ZERO DATE 07.01.2002 21.02.02 07.09.02 07.07.03 07.07.03 07.01.04 07.07.04 07.01.07 07.01.06 18.03.04(A) 05.04.06(A) 30.09.07 07.12.07 31.10.07 07.03.08 07.06.10 01.01.09
Brief Status
Status of linked project: Goindwal Sahib TPP: The units are likely to commissioned U#1 01/10, U#2 07/10 respectively. Order for Main equipment not yet placed.
31
U#1: 02.09.07(A) U#2: 02/08 U#3: 01/08 U#4: 05/08 15.06.2007 ( Production started) 02/2006(Ph-1) 08/2007(Ph-2)
5.25
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval 4 5 Forest Clearance Mining Lease grant
Schedule Dates Schedule Actual / period Anticipated ZERO DATE (1/7/98) 05/00 30.04.99 30.06.99 25.01.01 22.09.04 06.09.04 09/05 06.09.04
Brief Status
Application for seeking approval of coal controller and notice to Director general (Mine safety) issued in 12/05.
6 7
04/06
15.04.05 12/06
Strengthening of approach road completed. Power & water supply completed. Silo & bunkers expected by 12/06. Removal of over burden in progress Exploration & GR preparation done by M/s JPL itself..Production started
09/06
Status of linked project O.P Jinal STPS ( 4x250 MW):Order placed on BHEL on 29.06.04. Unit -1:
Synchronized on 02.09.07. Unit-2 BLU schedule for 12/2007.; U-3 BLU schedule for 11/07. Unit-4 : HT is expected in 10/07.
32
COMMISSIONING SCHEDULE OF PROJECT ANTICIPATED DATE OF COMMENCEMENT OF COAL PRODUCTION ANTICIPATED DATE OF ATTAINING FULL CAPACITY
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 EIA/EMP Studies & Approval 4 Forest Clearance
Schedule Dates Schedule Actual / period Anticipated ZERO DATE 29.06.1998 13.07.98 18.09.00(A) 23.06.05(A) 23.04.06 23.04.06 05.10.06 01/08
Brief Status
Rescheduled based on receipt of approved mining plan. EIA and EMP studies completed and applied for MOE&F clearance. Due to settlement, the village sheets have undergone changes and therefore the total forest area is likely to change. A detailed exercise is being undertaken with involment of IDCO officials to work out the exact position and the diversion proposals shall be re-submitted
5 6 7 8
Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
Pending Milestones: Forest clearance, mining lease and land acquisition. Chairman, IPICOL had called for a review meeting on 16.12.06 on status of land acquisition of different projects. Steps are being taken by Govt. of Orissa to expedite the entire process. Status of linked project: Choudwar (108),UPL TPP Ph-I(120), Ph-II(240):Choudwar (108 MW) already in operation. Ph-1 ( 120 MW) DPR prepared. Coal supply agreement was signed on 29.03.06 between UCL & UPL for supply of coal to 120 MW. Forest clearance was not required. Water supply arrangements completed. Major equipment tenders are received & processed. Arrangements are being made for awarding EPC contract. excepted in June 08.
33
27.02.2008 27.02.2012
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC Prep of GR Submission & Approval of Mining Plan EIA/EMP Studies & Approval Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
Schedule Dates Schedule Actual / period Anticipated ZERO DATE 25.04.2000 08.06.00 08.06.00 24.12.00 24.10.01 NA 09.09.00(A) 06.02.03(A) 30.09.05(A) NA 24.04.02 24.04.03 20.05.07 06/05 12.05.05(A)
Brief Status
2 3 4 5 6 7 8
34
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 Submission & Approval of Mining Plan 3 4 5 6 7 8 EIA/EMP Studies & Approval Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
Schedule Dates Schedule Actual / period Anticipated ZERO DATE 12.11.2003 05.05.05 05.05.05 04/06
Brief Status
It is learned that Mining Plan already cleared by MOC on 13.03.06, however formal communiqu awaited.
2008-09
30.06.07
40MW Power plant already commissioned in mid 2005 and another 60 MW unit ready for Since power plant is being set up at end use project site of sponge iron where the coal middlings shall be used for power generation hence there is no requirement of water ,silo and bunker at mine officer. Pending Milestones: Forest clearance, environmental clearance, mining lease and land acquisition Status of linked project: BHUSHAN LTD(40 + 60 MW), 40MW- Already Commissioned . 60 MW Ready
for commissioning.
35
31.03.2010
2.0
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 3 4 5 6 7 8 Submission & Approval of Mining Plan EIA/EMP Studies & Approval Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
Schedule Dates Schedule Actual / period Anticipated 27. 08.2004 12.10.04 22.04.05 (A)
Brief Status
GR was delayed by 6 months. GR made available in April., 2005. Mining Plan approved in July,2006 . Unexplored block completed
Milestones: Forest clearance, environmental clearance, mining lease and land acquisition
Status of linked project: Captive
36
Sl No.
Milestones
Allotment of Captive Coal Mine block including coordinated boundaries from MOC 1 Purchase of Geological Report from MOC 2 3 4 5 6 7 8 Submission & Approval of Mining Plan EIA/EMP Studies & Approval Forest Clearance Mining Lease grant Land acquisition Infrastructure Coal Mining and start of coal production
Brief Status
27.05.06
15.06.06 (A)
11.10.09
10/09
37