FIRE PREVENTION CHECKLIST

Plan Evaluator: Name of Owner/Establishment: Project Title: Occupancy Classification: Date: Location of Const: No. of Story/s: Checklist No.: Page 1 of 4

Non

Fire Protection Equipment

Compliance Compliance

Remarks

1. Emergency lights provided. 2. Fire extinguisher provided. 3. Illuminated exit signs provided. 4. Building is equipped with fire alarm, sprinkler, and smoke detector. 5. Availability of Personal Protective Equipment such as blankets, helmets, and gloves. 6. Self-closing door; automatic closing doors that are designed to confine smoke and heat and delay the spread of fire.

Checklist No.: Page 2 of 4

MEANS OF EGRESS
7. The number of exits from each floor of a building and from the building itself appropriate for the building occupancy. 8. Exit doors are opened from the direction of exit travel without the use of a key or any special knowledge or effort. 9. Two exit routes provided from elevated platforms, pits, or rooms where the absence of a second exit would increase the risk of injury from hot, poisonous, corrosive, suffocating, flammable, or explosive substances. 10. Doors or passageways that are neither exits nor access to exits, and which could be mistaken for exits, marked NOT AN EXIT or other appropriate marking. 11. Exit signs provided with the word EXIT in letters at least five inches high and with lettering at least one inch wide. 12. All exits kept free of obstructions. 13. The directions to exits, when not immediately apparent, marked with visible signs. 14. Exit doors side-hinged. 15. Doors that swing in both directions and are located between rooms where there is frequent traffic equipped with glass viewing panels. 16. Doors on cold storage rooms provided with an inside release mechanism that will release the latch and open the door even if it's padlocked or otherwise locked on the outside. 17. Exit doors open directly onto any street, alley, or other area where vehicles may be operated, are adequate barriers and warnings provided to prevent employees from stepping into the path of traffic. 18. Properly marked and lighted exits with provision for emergency lights to adequately illuminate exit ways in case of power failure.

Compliance

Non Compliance

Remarks

19. Stairway, vertical shafts, horizontal exits and other means of egress sealed from smoke and heat.

Checklist No.: Page 3 of 4

Non

Fire Protection Equipment


20. Automatic fire alarm system 21. Local fire department familiar with your facility, its location and specific hazards. 22. Fire doors and shutters in good operating condition. 23. Fire doors and shutters unobstructed and protected against obstructions, including their counterweights. 24. Fire doors and shutter fusible links in place. 25. Automatic sprinkler system water control valves, air and water pressure checked periodically as required. 26. The maintenance of automatic sprinkler systems assigned to responsible persons or to a sprinkler contractor. 27. Sprinkler heads protected by metal guards if exposed to potential physical damage. 28. Proper clearance maintained below sprinkler heads. 29. Portable fire extinguishers provided in adequate number and type and mounted in readily accessible locations. 30. Fire extinguishers recharged regularly with this noted on the inspection tag.

Compliance Compliance

Remarks

Checklist No.: Page 4 of 4 Non

Flammable and Combustible Material


31. Combustible scrap, and waste materials such as oily rags stored in covered metal
receptacles and removed from the worksite promptly.

Compliance Compliance

Remarks

32. Approved containers and tanks used for the storage and handling of flammable and
combustible liquids.

33. All connections on drums and combustible liquid piping vapor and liquid tight. 34. All flammable liquids kept in closed containers when not in use. 35. Storage rooms for flammable and combustible liquids have appropriate ventilation
systems.

36. NO SMOKING signs posted on liquefied petroleum gas tanks. 37. All solvent wastes and flammable liquids kept in fire-resistant covered containers
until they are removed from the worksite.

38. Fire extinguishers appropriate for the materials in the areas where they are mounted. 39. Extinguishers free from obstruction or blockage. 40. All extinguishers serviced, maintained, and tagged at least once a year. 41. All extinguishers fully charged and in their designated places. 42. Sprinkler systems are permanently installed, are the nozzle heads directed or arranged
so that water will not be sprayed into operating electrical switchboards and equipment. 43. NO SMOKING signs posted in areas where flammable or combustible materials are used or stored.

Inspected By:

Date Checked:

ZONING CHECKLIST
Plan Evaluator: Name of Owner/Establishment: Project Title: Occupancy Classification: Date: Location of Const: No. of Story/s: Checklist No.: Page 1 of 2

HEIGHT REGULATION
1. Work centers at height is properly organized. 2. Work at height takes account of weather conditions that could endanger health and

Compliance

Non Compliance

Recommendation

safety.
3. Height of workplace is safe. 4. Workstation equipment at height is appropriate inspected.

PROVISION TO ZONING
5.The setbacks existing be reduced.

Compliance

Non Compliance

Recommendation

6.As part of the construction can do the ordinances inhibit or prohibit the clear cutting of the project site. 7. Traffic of heavy construction to specific areas, such as areas of proposed roadway or any delivering products. 8. Areas required to be identified on plans and marked in the field? 9. Municipality require an as-built inspection before issuing a certificate of occupancy. 10.The municipality require the restoration to compacted areas in accordance with the Sediment Control Standards. 11. The municipal area encourage zoning the most appropriate use of land.

Checklist No.: Page 2 of 2 OPEN SPACE 12. Maximum allowable impervious cover in open space areas. 13. Limitations on the allowable disturbance of existing vegetated areas in open space. 14. Open space designs allowed in the municipality. 15. Flexible site design incentives available for developers that utilize open space design options.
Compliance Non compliance Recommendation

NEW ZONING
16. A secure of safety in zoning from fire, panic and other dangers. 17. The new zoning provide adequate light and air. 18. The new zoning adopted with a view to conserving the value of buildings. 19. The new zoning give consideration to the peculiar suitability of the property for particular uses. 20. The new zoning avoid the undue concentration of population.. 21. A new zoning designed in accordance with the comprehensive plan. 22. The new zoning encourage the most appropriate use of land throughout such County or municipal area. 23. The new zoning facilitate the adequate provision of transportation, water, sewer, schools, parks, fire, police, and other public requirements.

Compliance

Non Compliance

Recommendation

Inspected By:

Date Checked:

FIRE PREVENTION CHECKLIST


Plan Evaluator: Name of Owner/Establishment: Project Title: Occupancy Classification: Date: Location of Const: No. of Story/s: Checklist No.: Page 1 of 4

MAINTENANCE
1. All parts thereof shall be maintained in a safe and sanitary condition. 2. All devices or safe guards, which are required by this code in a building or structure when considered, altered, or repaired, shall be maintained on good working order.

Compliance

Non compliance

Recommendation

BUILDING PERMITS AND AREA


3. A building permit from the building official for whichever of such work is proposed to be under taken for the building or structure 4. Building permit, inspection and other fees covered by city and municipal ordinance 5. Allowable floor areas for one-story buildings not exceed the limits determined in accordance with occupancy groups and types of construction . 6. Each portion of a building separated by one or more area separation walls may be considered a separate building.

Compliance

Non compliance

Recommendation

Checklist No.: Page 2 of 3

DESIGN REQUIREMENTS
7. Buildings adjoin or have access to public space, yard, or street on not less than one side and permanently maintained. 8. The center line of an adjoining street or alley is considered an adjacent properly line. 9. Windows are not less than 75 centimeters (30inches) from the side and rear and rear property. 10. Exterior walls have fire resistance and opening protection in accordance with requirements set by the secretary. 11. Projections beyond the exterior wall are not extend beyond a point one-third the distance to the property line from an exterior. 12. Distance is measured at right angles from the property line. 13. The sum of the area of such openings are not exceed 50 percent of the total area of the wall in each story.

Compliance

Non Compliance

Recommendation

14. The design and construction of the building and structures are in compliance with the provisions of the national structural code for buildings.

Checklist No.: Page 3 of 3

BUILDING PROTECTION

Compliance

Non Compliance

Recommendation

15. Building equipped with an automatic sprinkler system. 16.System operation monitored by an alarm company. 17. Value operation monitored by an alarm company 18. The building equipped with a fire detection system.

19. The system provide an alarm signal in the building. 20. Portable fire extinguishers provided. 21. All extinguishers have a current inspection tag. 22. Designated smoking areas properly indentified. 23. All electrical switches and receptacles in good repair.

Inspected By: