Académique Documents
Professionnel Documents
Culture Documents
by
Jacob Sandikie, Liberia
Malcolm Whitfield, Sierra Leone
Girish Kumnar Sharma, India
VirYilio Fernandez, Philippines
on
get hands
to project has been
actually objective of this group The ammonia operation of
the intermittent
on the construction and experience
the con the basic activities
in This report,
thus, gives
water system.
such a way
0 system, simplified
in operation of the
NH 3 /H2 struction and
laboratory working guidelines.
that it could be used as
and possible
the TAET are discussed on the existing unit
in Problems
are also suggested.
commercially viable modifications
Valve 2 Valve 1
Valve 3.P 2
7
T2
Valve
NH 3
'B-
* NH
2
4:
0
H 0
vNH 3
w V 2
Heat
Figure 1
The Intermittent Ammonia-Water Refrigeration Unit
Components
2 propane tanks (20 Ib)
(V & V )
1 2 Stainless steel piping
2 pressure gauges (P1
& P2 )
4 regular middle valves
2 type-k thermal couple probes
P2T
T1 Valve 1
PI
ValVe 2
Valve 3 1
P2 .
Valve4
VV
Figure 2
Operation
I Pressure Testing
a) b) Open valves 1, 2 and 3 and leave Valve 4 closed.
PUmD enough water into the system to completely fill the 2 tanks
and the piping arrangements.
c) The system is now kept under a pressure of approximately 125 to
150 pounds per square inch for several hours (24 hr).
d) All leaks discovered during this testing process are tightly
closed or sealed by either welding or tightening the screws.
39 psi
P2
39 psi
Vi
v 2
Figure 3
e) f)
g)
T
~V .Valve
Pi
..
Valve
-
Valve
P2
T 2
4:-..
Figure 4
Valve 2
ave 3
vT4
. :
- T"
*..
", --
---
Generator
denser
Figure 5
a)
b)
This will permit initial pressure to build up in tile generator. Next, Valves 2 and
3 are allowed to open and NH3
to flow into
the condenser.
At this stage heat at
V1 is removed. During the
T Valve 1
Valve 2
Valve 3
_ __"_
P2
_
__
_Valve
T2
2__
~-
3'
3 2
Environmental
Generator/Absorber
Condenser/Evaporator
Figure 6
c)
After an
approximate equilibrium is
1T
p
1J
Valve 2
Valve 3
2T
'q
Figure 7
Results Generation time Temperature of NH3 /H2 0 mixture, T 1 Temperature T 2 during heating Temperature T 2 during the cooling mode Ambient air temperature Temperature of Box b Cooling time Quantity of water in the system Quantity of ammonia in the system 2 hours 160OF 850 F 360 F 77OF 590 F 1 hour 4 lb 8 lb
- , " '1-
,-
I-I:-r
I 'i i'
.-
1' . . -. 1*
...
- , i, I
_____
- -_'~_I -i
-:
--
. A_-.-
- /
- -- --
JI. I-!-I-1 I
1 I'-.t:
,1-77 Tv
I:-.
I- .. l ..
---
-
.
.
.....
i i ''
I.I.
..
_.1
.i
.
_ ! iI
.... I
_.___
_-J-l-i
_~
....
--
--
-i
,T.
l_.j
t _I
i.I!: i-'
.-
I;
'
I
.......
.. '- -'-N.... .-
K
-
'
-i/iili',_ [
I--
_ t -- i i lr
--j'..
-71
l..
1 -- I !
I'i VK'-J-,
--
-I FI
'
_ _ 1
.__i ,--l-r---
--''-i;--l7l .. ...
'-I ... -_
tit
.ii-
'-
.....
..
-I...
1 4
iii.1 i
I
i14 f-i
Id It +
I~~
17~
__ __ __
'
Observations
1.
In order to accelerate the absorption process of ammonia in V I during
the cooling process, the propane tank V containing the NH3 /H2 0
1
mixture has
to be manually shaken. Agitation of the NH3 /H2 0
After ammonia is
discharged from the right the fan arm is now being ,heated while the right is
being cooled.
system is
on a very large scale.
(c) serves as
the cooling chamber for condensing and collecting NH3 .
The box area, ammonia is which can be larger, is then cooled and the evaporated through the by-passing pipe that runs
Suggested Modifications
Cooling H 0. 24
-.-..-..
f(b)
~P
'",
11
(a) [
Generator
BOX
Abore A~'Pvi.
.------
Il
'
" (a
(a)
~~~Generator!ArN/I0
3
/l
(a
FanGenerator/ Absorber
Ileat