A.

CF02A

Tencuieli interioare de 2 cm grosime, driscuite exec manual la pereti


sau stalpi pe supr. Plane cu mortar var-ciment M25-T pe zidarie

1. Grupa 1
[2x(5.85 + 5.95) + (2 x 0.45] x 3.35 - [(0.90 x 2.10) + (1.80 x 2.70)+2x(0.90 x 2.70) +
(2.70 x 2.10)] = 82.075 17.28 = 64.80 m2
2. Grupa 2
[2x(5.85 + 5.95) + (2 x 0.45] x 3.35 - [(0.90 x 2.10) + (1.80 x 2.70)+2x(0.90 x 2.70) +
(2.70 x 2.10)] = 82.075 17.28 = 64.80 m2
3. Cabinet medical
2 x (4.00 + 3.05) x 3.35 [(0.90 x 2.10) + ( 0.90 x 2.55) + (1.80 x1.80)] = 39.80 m2
4. Oficiu
(2.30 + 4.00) x 3.35 [(0.90 x 2.10) + (1.80 x 1.80)] = 16.00 m2
5. Cancelarie
(3.30 + 4.00) x 3.35 [(0.90 x 2.10) + (1.80 x 1.80)] = 19.30 m2
6. Grup sanitar B.
[2 x (1.95 + 4.00)+ (2 x 2.05)] x 3.35 [(0.90 x 0.60) + 2 x (0.90 x 2.10) + (0.80 x
2.10)] = 47.60 m2
7. Grup sanitar F
[2 x (1.95 + 4.00)+ (2 x 2.05)] x 3.35 [(0.90 x 0.60) + 2 x (0.90 x 2.10) + (0.80 x
2.10)] = 47.60 m2
8. Centrala termica
[2 x (4.00 + 4.75) + (2 x 0.20)] x 3.35 [(0.90 x 2.70) + (0.90 x 2.10) + (1.80 x 1.80)]
= 52.40 m2
9. Depozit
[2 x (3.05+1.80) x 3.35 [(0.90 x 2.10) + (0.90 x 2.55)] = 28.30 m2
10. Hol
[(4 x 6.00) + (2 x 3.20) + (2 x 2.35) +1.70 + 1.80 + (2 x 1.95) + (2 x 0.20) + (2 x 0.25)
+ 0.10 + (2 x 0.20)] [2 x (0.90 x 2.10) + 2 x (0.80 x 2.10) + 3 (0.90 x 2.10) + (0.90 x
2.55)] = 132.00 m2
11. Hol acces principal
[(2 x 2.45) + 4.05] x 3.35 [2 x (0.90 x 2.10) + (1.80 x 2.70) + 2 x (0.90 x 2.70)] =
16.50m2
1

Economia constructiilor si legislatie


S = 64.80 + 64.80 + 39.80 + 16.00 + 19.30 + 47.60 + 47.60 + 52.40 + 28.30 + 132.00
+16.50 = 529.10 m2
B.

CF04A

Tencuieli interioare driscuite executate manual la tavane drepte din


beton cu mortar ciment-var M25-T cu grosimea totala de 1.5 cm

1. Grupa 1
(5.85 x 5.95) [(0.20 x 0.10) + 2 x (0.20 x 0.20) + (0.45 x 0.15)] = 34.60 m2
2. Grupa 2
(5.85 x 5.95) [(0.20 x 0.10) + 2 x (0.20 x 0.20) + (0.45 x 0.15)] = 34.60 m2
3. Cabinet medical
(4.00 x 3.05) [(0.20 x 0.30) + (0.20 x 0.20)] = 12.10 m2
4. Oficiu
2.30 x 4.00 = 9.20 m2
5. Cancelarie
(3.30 x 4.00) (0.20 x 0.20) = 13.15 m2
6. Grup sanitar B.
(4.00 x 1.95) [(2.05 x 0.15) (0.20 x 0.20)] = 7.45 m2
7. Grup sanitar F
(4.00 x 1.95) (2.05 x 0.15) = 7.50 m2
8. Centrala termica
(4.75 x 4.00) [(0.20 x 0.20) + (0.45 x 0.20)] = 18.85 m2
9. Depozit
(3.05 x 1.80) [(0.20x0.20) + (0.30 x 0.20)] = 5.40 m2
10. Hol
[2 x (6.00 x 1.70) + (4.05 x 4.40) + (3.20 x 1.80) +(4.05 x 1.50)] [2 x (0.10 x 0.45) +
(0.20 x 0.45) + (0.20 x 0.45) + (0.20 x 0.45) + (0.20 x 0.20)] = 44.10 m2
11. Hol acces principal
2.45 x 4.05 = 9.90 m2
S = 34.60 + 34.60 + 12.10 + 9.20 + 13.15 + 7.45 + 7.50 + 18.85 + 5.40 + 44.10 +9.90 =
196.85 m2
C.

CG35A

Strat support pentru pardoseli, sapa de egalizare pe baza de ciment de


7mm grosime, aplicata manual

S = 1 + 2 + 3 + 4 + 5 + 6 + 7 + 9 + 1 0 + 11 = 178.00 m2
D.

CG37A

Parchet din parchet lamelar

S = 1 + 2 + 5 = 34.60 + 34.60 + 13.15 = 82.35 m2

Economia constructiilor si legislatie


E.

CG21A

Pardoseli din beton turnate pe loc, cu beton simplu clasa C8/10 in


grosime de 10 cm, in camp continuu driscuit

S = 8 = 18,85 m2
F.

CG16A

Pardoseli din placi de gresie ceramic cu suprafata placilor pina la 100


cm2 inclusiv

S = 3 + 4 + 6 + 7 + 9 + 10 + 11 = 12,10 + 9.20 + 7.45 + 7.50 + 5.40 + 44.10 + 9.90 =


95.65 m2
G.

CI06A

Placaj din faianta smaltuita cu dimensiuni ale placilor de 30x30cm,


fixate cu mortar de ciment cu adaos de aracet

S = 3 + 6 + 7 = 39,80 + 47,60 + 47,60 = 135,00 m2


H.

CN07B

Vopsitorii cu var lavabil in trei straturi pe tencuieli driscuite

S = (529,10 + 196,85) 135,00 = 590,95 m2


I.

CK23C

Ferestre din mase plastic cu suprafata tocului peste 2.50 m2

1. Grupa 1
(2.70 x 2.10) + 2 x (0.90 x2.70) = 10,53 m2
2. Grupa 2
(2.70 x 2.10) + 2 x (0.90 x2.70) = 10,53 m2
3. Cabinet medical
(0.90 x 2.55) + (1.80 x 1.80) = 5,55 m2
4. Oficiu
1.80 x 1.80 = 3.24 m2
5. Cancelarie
1.80 x 1.80 = 3.24 m2
6. Grup sanitar B.
0.90 x 0.60 = 0.54 m2
7. Grup sanitar F
0.90 x 0.60 = 0.54 m2
8. Centrala termica
0.90 x 2.70 + 1.80 x 1.80 = 5,67 m2
9. Depozit
0,90 x 2,55 = 2,295 m2
10. Hol
2 x (0.90 x 2.70) + (0.90 x 2.55) = 7,155 m2
11. Hol acces principal
3

Economia constructiilor si legislatie


2 x (0.90 x 2.70) = 4,86 m2
S = 54,15 m2
J.

CK25A

Usi confectionate din profile din mase plastic intr-un canat cu


suprafata tocului pina la 7mp inclusiv

S = 11 x (0.90 x 2.10) + 2 x (0.80 x 2.10) = 24,15 m2


K.

CK25D

Usi confectionate din profile din mase plastic in doua canate cu


suprafata tocului pina la 7mp inclusive

S = 4 x (1.80 x 2.70) = 19,44 m2


L.

CI14A

Glafuri din gresie ceramic

S = 2 x [(2 x 0.90) + 2.70)] + 3 x 1.80 + 7 x 0.90 = 20.70 ml