PROJECT MANAGEMENT GROUP Brief status of EPC projects (As 11.10.11 at 17.00 Hrs) (Total EPC Projects: 5006.

8 MW) S.No. 7 Project (MW) Pipavav-1 (351 MW) Project Status 10/10/11; Gas-In: HT: 25/11/11; Box-up:10/11/11; GT Syn: 25/12/11; ST Syn: 25/12/11; Full load- 01/12 GT & ST Syn. Plan is shifted due to delay in arrangement of supply for charging the switchyard by M/s GETCO and procurement of DM water for Hydro Test. Gas Turbine- GT has been placed on the foundation on 27.09.11. Placed on the GTG foundation on 01.10.11. BHEL Constraints Customer Constraints

Supply of 3 nos. strainers SEA WATER OUTFALL SYSTEM for main piping from HYD. RCC work is under progress. Modifications in the Readiness by 10/11. switchgears panels from L&T. critical for back charging. Readiness of Fire protection system to start up the plant. 12 inch SS Fuel Gas Piping required from Hyderabad (Critical for Gas Turbine Commissioning) expected to be received at site by 25.10.2011. Pending supply from PC Chennai (Critical) DM System for RO DM plant pending supply by RPT

HRSG: Air leak test completed. Hydro test expected by 15.10.11. Main piping erection (HPMS/LPMS/IPMS/HRH and CRH) is near completion. 02 nos. strainer has received at site. Balance 03 nos. of strainer and remaining (loose items for (GT & ST), will be dispatch by 10/11. STACK: erection completed. and insulation

TG: 3 nos. of bearing pedestals grouted on TG deck. Lube oil system installed. Piping work completed. EOT crane commissioned. Condenser Leak test completed. Water fill test completed. Water box boxup is in progress. Switchyard : Field equipment testing completed. Circuit breaker testing

PROJECT MANAGEMENT GROUP Brief status of EPC projects (As 11.10.11 at 17.00 Hrs) (Total EPC Projects: 5006.8 MW) S.No. Project (MW) Project Status completed. Logic testing is in progress. GT bay and Priority bay is ready. 1 Tower is erected and stringing of about 5 KM is started for tapping the supply from line, of which 3 KM is pending. Commitment by GPPC for readiness by 20.10.2011. Cooling Tower- 20/20 cells ready. Civil work completed. Mechanical erection (fans and piping) is in progress. Readiness by 10/11. Sea Water Intake Pump House -Civil work nearing completion. Mechanical erection of log gates and pump in progress. 8 Pipavav-2 (351 MW) H.T.: 1/11/11; Gas-In: 12/11; Supply commitment from Readiness of sea water outfall system to start up the Box-up:12/11; GT Syn -.02/12; ST Hyderabad to be expedited. plant. Syn: 02/12; Full load- 03/12 HYD 1. GT Expected to be STG deck casting completed on Dispatched from Mumbai Port 13.04.11. by 12.10.2011. HRSG : HP/LP/IP Drum lifted on 2. LPT-. Dispatched from 13.01.11. Module erection completed HYD but not received at Site. (327/327) welding is U/P. Ceramic 3. HP front and LP front wool (60/84MT) consumed. Pedestals dispatched but not received at site till today. GT-2 Foundation: RCC completed on 30.10.10. GT 2 FOB 05/11. GT yet to be received at site BFP Building: Foundation ready. Column erection completed. Painting in progress. Readiness by 10/11. BFP Foundation: completed. BHEL Constraints Customer Constraints

PROJECT MANAGEMENT GROUP Brief status of EPC projects (As 11.10.11 at 17.00 Hrs) (Total EPC Projects: 5006.8 MW) S.No. Project (MW) Project Status STACK 2 : Erection completed, insulation in progress. BHEL Constraints Customer Constraints