Vous êtes sur la page 1sur 5

OWNER

PROJECT

CONTRACTOR

PT WAHANA NUSANTARA

RASUNA TOWER
JL.H.R RASUNA SAID KAV C 22

PT. TATAMULIA NUSANTARA INDAH

SCHEDULE SHOP DRAWING STRUCTURE


NO. DRAWING TITLE DRAWING.NO DRAWING.REV SCHEDULE APPROVAL PLAN ACTUAL R0 R1 DATE DATE DATE 8/5/2011 8/5/2011 22/4/2011 27/4/2011 27/4/2011 28/6/2011 24/6/2011 24/6/2011 28/7/2011 28/7/2011 28/7/2011 28/7/2011 28/7/2011 28/7/2011 28/7/2011 28/7/2011 28/7/2011 28/7/2011 20/8/2011 4/9/2011 4/9/2011 16/9/2011 1/8/2011 1/8/2011 1/8/2011 1/8/2011 1/8/2011 1/8/2011 17/10/2011 28/10/2011 3/11/2011 5/12/2011 13/12/2011 7/2/2012 15/2/2012 3/4/2012 11/4/2012 13/5/2012 20/5/2012 28/5/2012 6/6/2012 14/6/2012 24/6/2012 1/7/2012 8/7/2012 15/10/2012 25/10/2012 11/3/2013 11/3/2013 15/10/2011 15/10/2011 STATUS

1 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58

EXISTING EXCAVATION & SHORING PLAN EXISTING EXCAVATION & SHORING SECTION SITE PLAN STORM WATER PLAN SITEWORKS DETAIL EXISTING RAFT PLANTS AND DETAILS - SHEET 1 EXISTING RAFT PLANTS AND DETAILS - SHEET 2 EXISTING RAFT VERIFICATION PLAN COLUMN SCHEDULE COLUMNJ DETAILS COREWALL ELEVATIONS - SHEET 1 OF 2 COREWALL ELEVATIONS - SHEET 1 OF 2 COREWALL REINFORCEMENT SCHEDULE COREWALL DETAILS - SHEET 1 COREWALL DETAILS - SHEET 2 COREWALL DETAILS - SHEET 3 COREWALL DETAILS - SHEET 4 COREWALL DETAILS - SHEET 5 BASEMENT 3 GENERAL ARRANGEMENT PLAN BASEMENT 2 BOTTOM REINFORCEMENT PLAN BASEMENT 2 TOP REINFORCEMENT PLAN BASEMENT 1 GENERAL ARRANGEMENT PLAN BASEMENT RETAINING WALL ELEVATOR SH1 BASEMENT RETAINING WALL ELEVATOR SH2 BASEMENT RETAINING WALL SECTION AND DETAILS BASEMENT RAMP PLANS & DETAILS BASEMENT RAMP BEAM SCHEDULE COREWALL LINK BEAM SCHEDULE L2 REINFORCEMENT PLAN L3 REINFORCEMENT PLAN LEVEL 4 - 7 FLOOR PLAN LEVEL 8 FLOOR PLAN LEVEL 9 -15 FLOOR PLAN LEVEL 16 FLOOR PLAN LEVEL 17 - 22 FLOOR PLAN LEVEL 23 REINFORCEMENT PLAN LEVEL 24 - 27 REINFORCEMENT PLAN LEVEL 28 REINFORCEMENT PLAN LEVEL 29 REINFORCEMENT PLAN LEVEL 30 REINFORCEMENT PLAN LEVEL 31 REINFORCEMENT PLAN LEVEL 32 REINFORCEMENT PLAN LEVEL 33 REINFORCEMENT PLAN LEVEL 34 REINFORCEMENT PLAN LEVEL 35-45 REINFORCEMENT PLAN LEVEL 46 REINFORCEMENT PLAN LEVEL 47-57 REINFORCEMENT PLAN L1 ROOF BEAM SCHEDULE SHEET 1 L1 ROOF BEAM SCHEDULE SHEET 2 TYPICAL BEAM ELEVATIONS PODIUM BEAM SCHEDULE - SHEET 1 PODIUM BEAM SCHEDULE - SHEET 2 L3 POST TENSIONED BEAM ELEVATIONS STAIR ELEVATIONS & DETAILS - SHEET 2

C-001 C-002 C-005 C-006 C-007 S-001 S-002 S-003 S-010 S-013 S-015 S-016 S-017 S-018 S-019 S-020 S-021 S-022 S-023 S-031 S-038 S-046 S-047 S-048 S-051 S-052 S-055 S-071 S-072 S-073 S-074 S-075 S-076 S-077 S-078 S-079 S-080 S-081 S-082 S-083 S-084 S-085 S-086 S-087 S-088 S-089 S-090 S-102 S-103 S-104 S-105 S-106 S-107 S-110

C01 C02 C05 C06 C07 S01 S02 S03 S10 S13 S15 S16 S17 S18 S19 S20 S21 S22 S23 S31 S38 S46 S47 S48 S51 S52 S55 S71 S72 S73 S74 S75 S76 S77 S78 S79 S80 S81 S83 S84 S85 S86 S87 S88 S89 S90 S91 S102 S103 S104 S105 S106 S107 S110

Page 1 of 5

NO.

DRAWING TITLE

DRAWING.NO DRAWING.REV

SCHEDULE APPROVAL PLAN ACTUAL R0 R1 DATE DATE DATE

STATUS

EXISTING EXCAVATION & SHORING PLAN Check by : Jakarta, 20 Februari 2011 Dibuat oleh :

Ir. Tri Mulyawan, MT Project Manager

Didiek Arif Rahman Hakim, ST Chief Engineer

Page 2 of 5

CONTRACTOR

PT. TATAMULIA NUSANTARA INDAH

HEDULE SHOP DRAWING STRUCTURE


REMARK

Page 3 of 5

REMARK

Jakarta, 20 Februari 2011 Dibuat oleh :

Didiek Arif Rahman Hakim, ST Chief Engineer

Page 4 of 5

CLINET AND CONSTRUCTUIN MANAGEMENT

PROJECT

CONTRACTOR

RASUNA TOWER
JL.H.R RASUNA SAID KAV C 22 PT. TATAMULIA NUSANTARA INDAH

EQUIPMENT, MANPOWER AND WORKING SCHEDULE

CHEMICAL ANCHOR FOR RIB BEAM BASEMENT 4 ANCHORE

WEEK 1

WEEK 2

WEEK 3

WEEK 4

WEEK 5

WEEK 6

CHEMICAL ANCHOR WOKS

25 DAYS

EQUIPMENT AND MAN POWER

EQUIPMENT HAMMER DRILL MACHINE GBH 7 -46 - 15 UNIT CLEANING BRUSH - 15 UNIT COMPRESOR - 1 UNIT

MAN POWER DRILLIING WORKER ( INC CHEMICAL ANCHOR TECHNICIAN )

SITE MANAGEMENT SUPERVISOR - 2 PERSON QA/QC - 2 PERSON SAVETY WATCHMAN - 1 PERSON SURVEYOR - 1 PERSON TOTAL MAN POWER

15

15

15

15
NOTE : NO OF CHEMICAL ANCHOR 13000 POINTS TEAM COMPOSITION : DRILLIING WORKER ( INC CHEMICAL ANCHOR TECHNICIAN ) OUTPUT PER TEAM : 15 PCS / MAN / DAY 535 PCS / DAY ( 3 SHIFT )

Vous aimerez peut-être aussi