Académique Documents
Professionnel Documents
Culture Documents
PROJECT
CONTRACTOR
PT WAHANA NUSANTARA
RASUNA TOWER
JL.H.R RASUNA SAID KAV C 22
1 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58
EXISTING EXCAVATION & SHORING PLAN EXISTING EXCAVATION & SHORING SECTION SITE PLAN STORM WATER PLAN SITEWORKS DETAIL EXISTING RAFT PLANTS AND DETAILS - SHEET 1 EXISTING RAFT PLANTS AND DETAILS - SHEET 2 EXISTING RAFT VERIFICATION PLAN COLUMN SCHEDULE COLUMNJ DETAILS COREWALL ELEVATIONS - SHEET 1 OF 2 COREWALL ELEVATIONS - SHEET 1 OF 2 COREWALL REINFORCEMENT SCHEDULE COREWALL DETAILS - SHEET 1 COREWALL DETAILS - SHEET 2 COREWALL DETAILS - SHEET 3 COREWALL DETAILS - SHEET 4 COREWALL DETAILS - SHEET 5 BASEMENT 3 GENERAL ARRANGEMENT PLAN BASEMENT 2 BOTTOM REINFORCEMENT PLAN BASEMENT 2 TOP REINFORCEMENT PLAN BASEMENT 1 GENERAL ARRANGEMENT PLAN BASEMENT RETAINING WALL ELEVATOR SH1 BASEMENT RETAINING WALL ELEVATOR SH2 BASEMENT RETAINING WALL SECTION AND DETAILS BASEMENT RAMP PLANS & DETAILS BASEMENT RAMP BEAM SCHEDULE COREWALL LINK BEAM SCHEDULE L2 REINFORCEMENT PLAN L3 REINFORCEMENT PLAN LEVEL 4 - 7 FLOOR PLAN LEVEL 8 FLOOR PLAN LEVEL 9 -15 FLOOR PLAN LEVEL 16 FLOOR PLAN LEVEL 17 - 22 FLOOR PLAN LEVEL 23 REINFORCEMENT PLAN LEVEL 24 - 27 REINFORCEMENT PLAN LEVEL 28 REINFORCEMENT PLAN LEVEL 29 REINFORCEMENT PLAN LEVEL 30 REINFORCEMENT PLAN LEVEL 31 REINFORCEMENT PLAN LEVEL 32 REINFORCEMENT PLAN LEVEL 33 REINFORCEMENT PLAN LEVEL 34 REINFORCEMENT PLAN LEVEL 35-45 REINFORCEMENT PLAN LEVEL 46 REINFORCEMENT PLAN LEVEL 47-57 REINFORCEMENT PLAN L1 ROOF BEAM SCHEDULE SHEET 1 L1 ROOF BEAM SCHEDULE SHEET 2 TYPICAL BEAM ELEVATIONS PODIUM BEAM SCHEDULE - SHEET 1 PODIUM BEAM SCHEDULE - SHEET 2 L3 POST TENSIONED BEAM ELEVATIONS STAIR ELEVATIONS & DETAILS - SHEET 2
C-001 C-002 C-005 C-006 C-007 S-001 S-002 S-003 S-010 S-013 S-015 S-016 S-017 S-018 S-019 S-020 S-021 S-022 S-023 S-031 S-038 S-046 S-047 S-048 S-051 S-052 S-055 S-071 S-072 S-073 S-074 S-075 S-076 S-077 S-078 S-079 S-080 S-081 S-082 S-083 S-084 S-085 S-086 S-087 S-088 S-089 S-090 S-102 S-103 S-104 S-105 S-106 S-107 S-110
C01 C02 C05 C06 C07 S01 S02 S03 S10 S13 S15 S16 S17 S18 S19 S20 S21 S22 S23 S31 S38 S46 S47 S48 S51 S52 S55 S71 S72 S73 S74 S75 S76 S77 S78 S79 S80 S81 S83 S84 S85 S86 S87 S88 S89 S90 S91 S102 S103 S104 S105 S106 S107 S110
Page 1 of 5
NO.
DRAWING TITLE
DRAWING.NO DRAWING.REV
STATUS
EXISTING EXCAVATION & SHORING PLAN Check by : Jakarta, 20 Februari 2011 Dibuat oleh :
Page 2 of 5
CONTRACTOR
Page 3 of 5
REMARK
Page 4 of 5
PROJECT
CONTRACTOR
RASUNA TOWER
JL.H.R RASUNA SAID KAV C 22 PT. TATAMULIA NUSANTARA INDAH
WEEK 1
WEEK 2
WEEK 3
WEEK 4
WEEK 5
WEEK 6
25 DAYS
EQUIPMENT HAMMER DRILL MACHINE GBH 7 -46 - 15 UNIT CLEANING BRUSH - 15 UNIT COMPRESOR - 1 UNIT
SITE MANAGEMENT SUPERVISOR - 2 PERSON QA/QC - 2 PERSON SAVETY WATCHMAN - 1 PERSON SURVEYOR - 1 PERSON TOTAL MAN POWER
15
15
15
15
NOTE : NO OF CHEMICAL ANCHOR 13000 POINTS TEAM COMPOSITION : DRILLIING WORKER ( INC CHEMICAL ANCHOR TECHNICIAN ) OUTPUT PER TEAM : 15 PCS / MAN / DAY 535 PCS / DAY ( 3 SHIFT )