Académique Documents
Professionnel Documents
Culture Documents
76297144.docx Page 1
The final is an open book/open notes examination. The final includes ten questions, and is
worth a total of 300 points. The sample problems here represent the types of problems that may
appear on the final. There are solutions to the problems at the end. There will also be
discussion problems. have provided a list of the topics from which the discussion questions will
be taken.
On problems, please show all calculations when you complete the final.
ProbIems:
TCO B) Three-point estimate: Problem
TCO B) Contingency Pricing: Problem
TCO G) Crashing: Problem
TCO C) WBS: Problem
TCO E) Resource Allocation/Leveling: Problem
TCO F, G) Earned Value/PMS: Problem
TCO C) General Budget development, sensitivity: Problem
Discussion topics:
TCO D) Accounting, PMS, and Project Control
TCO A) Budgeting processes and techniques
TCO E) Resource Allocation Matrix
TCO F) Project Control Process
TCO F, G) EVM and EAC: Discussion:
PM592 Final Exam Study Guide
76297144.docx Page 2
TerminaI Course Objectives
A
Given the WBS and work packages develop an understanding oI budgeting processes using top-down and
bottom-up techniques.
B
Given the WBS and work packages, analyze the various cost estimating processes and investigate
approaches used to justiIy and allocate contingency Iunds.
C
Given the project plan, develop budget estimates in appropriate categories including but not limited to
labor, non-labor, overhead, and general administrative, and determine the costs to which the total project
budget is most sensitive.
D
Given the project budget, develop a project cost accounting and management inIormation system Ior
monitoring and controlling the project.
E
Given the WBS and work packages together with resources available and required, develop a
Responsibility Assignment Matrix (RAM) and utilize resource leveling techniques to achieve optimum
use oI human resources and uniIorm cash Ilow.
F
Given a project in progress, use earned value techniques to determine whether control actions are to be
taken, develop recommendations to achieve a satisIactory outcome, and describe a reporting plan.
G
Given a project in progress, establish Estimates To Completion (ETC) and Estimates At Completion
(EAC) using alternative assumptions, and recommend a course oI action based on your Iindings.
PM592 Final Exam Study Guide
76297144.docx Page 3
(TCO B) Estimating Procedures:
(a) A project requires the use of material A in several tasks over the 12 month period
expected to complete the work. Based on recent experience the most likely price for the
material is $29.00/lb. There are, however, price fluctuations over time based on suppliers used
and material availability. The most optimistic price estimate is $22.00/lb., and the most
pessimistic estimate is $51.00/lb.
What is the expected price of the materiaI?
(b) n addition to price fluctuations, it is also uncertain how much of material A will be
required for the project. Design uncertainties, and waste at the project site, will affect the
amount of material actually needed. The most likely amount required is 720 lbs. However, as
little as 600 lbs. and as much as 980 lbs. might be required.
What is the expected amount of materiaI A needed for the project?
(c) Using the estimates from & 2, what is the expected cost for materiaI A over the
Iife of the project using the simpIe and compIex formuIas?
PM592 Final Exam Study Guide
76297144.docx Page 4
PM592 Final Exam Study Guide
76297144.docx Page 5
Answer:
Normal
Time
Normal
cost
Crash
Time
Crash
Cost
Crash Cost /
Day
Actual
Days
Actual Crash
$
a)
Activity days) total) days) total) total) total)
A 6 $300 2 $400
B 3 250 2 280
C 6 400 4 550
D 5 150 2 270
PM592 Final Exam Study Guide
76297144.docx Page 8
WBS DeveIopment:
A company intends to establish a manufacturing facility by buying an existing factory from a
company in the same industry. A state-of-the art manufacturing line with supporting utilities will
be established in the refurbished factory.
Securing the building will involve negotiating the purchase and refurbishing and upgrading the
building structure.
Utilities that have to be upgraded or new systems installed include: upgrade of the electrical
system, installation of a new compressed air system, and increase in the capacity of the plant
wastewater treatment system.
Establishing the manufacturing line will require development of production equipment
specifications, procurement, and installation of machines and materials handling systems. A
systems test plan will be developed concurrently with preparation of the equipment
specifications. To check out the manufacturing line, a systems test of the complete line will be
performed by operating it to produce product. A separate project team is handling procurement
and stocking of components and materials that will be needed for the systems test of the new
line as well as when it becomes fully operational.
Prepare a work breakdown structure listing for this project with activities corresponding to a two-
level task and sub-task hierarchy. Format the WBS listing with activity item indents and WBS
codes such as a numbering scheme) that will clearly identify the level of each activity. Provide
columns showing the WBS code and activities.
A work breakdown structure listing for this project is:
WBS Code Activity
PM592 Final Exam Study Guide
76297144.docx Page 9
Resource AIIocation/LeveIing:
The following information is extracted from a project to design an office complex:
Activity Duration Predecessors Resources
A 4 days -- 1 Real Estate Consultant
B 3 days A 1 Legal Advisor
C 5 days A 1 Architect
D 3 days A 1 Architect
E 3 days B 1 Real Estate Consultant
F 2 days D 1 Legal Advisor
The Owner has stipulated that in order to provide continuity throughout the project, the same
individual must handle all activities under his or her discipline. He understands that schedule
and cost are tradeoffs but has stated that cost and quality are more important than schedule.
Activities on this project cannot be split.
a. dentify any resource conflicts in the above project. State the activities involved,
the time frame of the conflicts), and which individuals) are involved.
b. Given the owner's stipulation regarding project continuity, and the need to
minimize project duration, how can this conflict be resolved? What will be the effect on the
project? Be sure to explain your logic in making your changes.
(This part is as important as the calculations as this is the type decision a project manager gets
paid to do.)
PM592 Final Exam Study Guide
76297144.docx Page 10
6: (TCOs F & G) Earned VaIue and EAC
The following data were obtained from a project to build a pressure vessel:
Activity Duration Predecessors Budgeted Cost
A 4 weeks --- $18,650
B 3 weeks --- $6,430
C 6 weeks B $24,600
D 2 weeks A, C $12,000
E 3 weeks B $15,500
F 5 weeks D, E $26,000
At the end of week 4, the status of the project is as follows:
Activity % CompIete ActuaI Cost
A 90% $17,200
B 100% $5,370
C 0% $0
D 0% $0
E 25% $4,800
F 0% $0
a). Calculate the Cost and Schedule Variances for tasks A, B, C, D, E and F.
b). Calculate the EAC for the Project.
c). Write a brief analysis of the status of the project at this time. Use the results of your
analysis to help explain why you arrived at your conclusions.
PM592 Final Exam Study Guide
76297144.docx Page 11
Discussion topics:
The discussion questions will require the student to demonstrate an understanding of the
concepts and why they are important. A list as an answer will not receive a satisfactory grade.
Generalizations are also not complete answers. Just like reporting project management a
factual response will receive the best reception. See the text and the lectures to review these
topics
(TCO F, G) EVM and EAC: Discussion:
The earned value process is very important to project control. Understand and be able to
discuss what it is and why it is of value.
(TCO D) Accounting, PMIS, and Project ControI:
The when monitoring and controlling a project we must have data. Understand why, how this
data is created, how it is communicated, and what is important about the systems involved.
(TCO A) Budgeting processes and techniques:
This will be a discussion question that will ask you to discuss the budgeting processes and
techniques that we have coved and explain how and why they are used, what the benefits and
drawbacks are.
(TCO E ) Resource AIIocation Matrix:
One of the important tools in project management is the resource allocation matrix RAM).
Understand what it is, what good ways to create it are, what it is used for, and why it is valuable.
(TCO F) Project Monitoring and ControI:
This will be a discussion question relative to project monitoring and control, what it is, what are
the requirements to make it happen, and why all this is important.
PM592 Final Exam Study Guide
76297144.docx Page 13
Budget: The project shows an overall negative cost variance of $280, which is insignificant. The
EAC of $106,281 compares to an original budget of $103,180, and indicates the project will
complete approximately 3% over budget if no action is taken.
7 (TCO C) GeneraI Budget deveIopment, sensitivity
Material Cost
tem Qty Amt @ Extended Cost
Equipment 1 $10,000 $10,000
Material 100 $25 $2,500
Controls 1 $400 $400
Material $12,900
Labor Cost
tem Qty $/ Hr Hours Extended Cost
Technicians 5 $40 80 $16,000
Labor $16,000
Overhead Cost
tem Rate Base Cost Extended Cost
Engineering 15% $12,900 $1,935
nspection 3% $16,000 $480
Overhead Subtotal $2,415
G and A 5% $ 31,315 $1,566
Overhead Total $3,981
Grand total $32,880
Sensitivity: The labor cost are the greatest and is sensitive to the number of techs required and
the amount of time.