Vous êtes sur la page 1sur 66

PPC - 1 LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Single Answer Question The sourcing of vendors in case

of B type of items is :Correct Answer Medium Your Answer Minimum Select The Blank Question In the assignment model, the________ is formed between jobs and machines. Correct Answer Matrix Your Answer Matrix Select The Blank Question Production Planning and Control department acts as a link between companys sales and ________ department. Correct Answer Manufacturing Your Answer Manufacturing Select The Blank Question ________ is used for planning capacity. Correct Answer Standard Time Your Answer Standard Time Select The Blank Question Being capable to adjust their production facilities shortly just after change in demand for products and without incurring heavy expenses, greater flexibility in production is provided by ________. Correct Answer Job & batch production Your Answer Continuous production

True/False Question PERT uses linear programming and probability concepts for planning and controlling activities. Correct Answer True Your Answer True Multiple Choice Single Answer Question Proper Production Planning and Control can reduce cost in :Correct Answer Overtime cost Your Answer Overtime cost Multiple Choice Single Answer Question Detachable ticket, after filling in required information is :Correct Answer Placed in a tray/box Your Answer Placed in a tray/box Select The Blank Question The effectiveness of sequencing model technique ________ if the company has backlog of orders. Correct Answer Increases Your Answer Decreases Multiple Choice Multiple Answer Question Computerisation of line balancing involve following requirements :Correct Answer System software , Application software , User friendly interface Your Answer System software , Application software , User friendly interface True/False Question Curve fitting method of statistical forecasting uses curve line approach. Correct Answer

False Your Answer False True/False Question If set up time for four operations involved is 2 ,1.5, 2 , 2.5 hours respectively, total set up time would be 10 hours. Correct Answer False Your Answer False Match The Following Question Correct Answer Your Answer Bought out materials required for production process but do not become part of finished product. Maintenance, repair, operating [MRO] inventories Maintenance, repair, operating [MRO] inventories Finished goods, ready for sale to customer Finished goods inventory Finished goods inventory Idle resource of any kind having economic value Inventory Inventory Raw materials, parts, components required to produced finished product Production inventory Production inventory Select The Blank Question Rational figure on utilization index can be obtained by carrying out ________ study. Correct Answer Work- sampling Your Answer Work- sampling Multiple Choice Single Answer Question The assignment algorithm was developed by a Hungarian mathematician named :Correct Answer D. Konig Your Answer D. Konig

Multiple Choice Multiple Answer Question The minimum requirements for application software for line balancing are as follows :Correct Answer 1 Ghz processor , 1 Gb hard Disk free memory , Windows or equivalent operating system. Your Answer 1 Ghz processor , 1 Gb hard Disk free memory , Windows or equivalent operating system. Multiple Choice Multiple Answer Question A firm has 6 jobs to be processed on three machines A,B and C in the order ABC. The processing time of each job is given in the table below:- Find the idle time on different machines . Job Processing time [ hours ] Machine A Machine B Machine C J1 25 16 20 J2 26 20 19 J3 24 17 18 J4 22 20 21 J5 24 21 17 J6 28 18 13 Correct Answer 74 , 31 , 58 Your Answer 31 , 58 , 60 Multiple Choice Multiple Answer Question PERT terminology uses words like :Correct Answer Network diagram , Events , Slack Your Answer Network diagram , Events , Slack Multiple Choice Single Answer Question The most common assembly line is a moving conveyor that passes a series of workstations in a uniform time interval called :Correct Answer Cycle time Your Answer Cycle time True/False Question The make-or-buy decision is not related with profit of the factory. Correct Answer False Your Answer True

Select The Blank Question Generally for ________ flow system, Heuristic method is preferred. Correct Answer Intermittent Your Answer Intermittent Multiple Choice Single Answer Question Document raised by sales department to authorise activities of PPC department for items manufactured to customers order is called :Correct Answer Order Acceptance Your Answer Order Acceptance Multiple Choice Multiple Answer Question What factors affect the status of PPC department in the company for achieving informal status? Correct Answer Manufacturing Process , Work is highly repetitive , Number of workmen is not very large Your Answer Manufacturing Process , Work is highly repetitive , Number of workmen is not very large True/False Question Increase in inventory carrying cost increases EOQ. Correct Answer False Your Answer False True/False Question Progressing is only a substitute for poor planning. Correct Answer False Your Answer True Multiple Choice Multiple Answer Question Detachable Card contain following information :Correct Answer

Quantity produced , Operation , Date of completion Your Answer Quantity produced , Operation , Date of completion Multiple Choice Multiple Answer Question Weaknesses of PPC department can be studied on following grounds :Correct Answer Failures in delivery commitment , Cancellation of orders , Complaints from customers Your Answer Failures in delivery commitment , Cancellation of orders , Complaints from customers Multiple Choice Single Answer Question Activity R can not start unless activities P & Q are completed . And activity S can not start unless activity Q is over [ I.e. activity P may not be even over ]. Activity R is therefore succedding to activity P & Q while activity S is succeeding to activity :Correct Answer Q Your Answer Q Multiple Choice Single Answer Question If the annual usage of a material is 1200 units and the reorder point is at 120 Units, find the lead time. Correct Answer 4 months Your Answer 4 months Multiple Choice Multiple Answer Question Due to the following emergent events, the queue time has to compensate for the time for which the job has to undergo an extra time :Correct Answer Tool breakage , Job split up , Change in priorities Your Answer Tool breakage , Job split up , Change in priorities True/False Question Stores issue order for an item is prepared as soon as the route sheet is ready. Correct Answer True

Your Answer True Multiple Choice Single Answer Question Time study is useful method of measurement for :Correct Answer Short cycle time operations Your Answer Long cycle time operations Match The Following Question Correct Answer Your Answer Index method Loading and allocation of different jobs on different machines Loading and allocation of different jobs on different machines Critical Path Analysis Schedule of activities of project Schedule of activities of project Jonsons method Optimal job sequence for 2 machines n jobs Schedule using priority numbers Critical Ratio Scheduling Establishing priorities among jobs Establishing priorities among jobs Select The Blank Question In check list approach, ________ rating indicates that existing PPC system requires some major improvements in indicated areas. Correct Answer Fair Your Answer Fair Multiple Choice Multiple Answer Question Because of following reasons there are limitations in forwarding quotation against sales enquiry :Correct Answer The lot is not as per EOQ , Tools / plants required to execute order are not available. , The item is not within the manufacturing range of a company Your Answer

The lot is not as per EOQ , Tools / plants required to execute order are not available. , The item is not within the manufacturing range of a company Multiple Choice Multiple Answer Question Following are the factors which influence tool life :Correct Answer Type of tool , Material it is required to operate upon , Operators efficiency Your Answer Type of tool , Material it is required to operate upon , Operators efficiency True/False Question C type items would never be vital under VED analysis. Correct Answer False Your Answer False Multiple Choice Multiple Answer Question The Hungarian method is based on following assumptions :Correct Answer Tasks differ in their work contents and facility differ in their capabilities. , Only one task can be assigned to each facility. , As only one task can be assigned to each facility, the matrix must be of nXn order. Your Answer Tasks differ in their work contents and facility differ in their capabilities. , Only one task can be assigned to each facility. , As only one task can be assigned to each facility, the matrix must be of nXn order. Multiple Choice Single Answer Question The ratio between time when a product is required and time when the product is supplied is known as :Correct Answer Critical ratio Your Answer Critical ratio Select The Blank Question ________ inventories help to balance companys supply with market demand. Correct Answer Finished goods

Your Answer Finished goods True/False Question In order to complete a project on time, each critical activity need not be completed in time. Correct Answer False Your Answer False Multiple Choice Single Answer Question Production output in night shift is :Correct Answer Less than I shift production Your Answer Less than I shift production Select The Blank Question ________reflects impact of money tied up in inventory. Correct Answer Inventory turnover Your Answer Inventory turnover Multiple Choice Multiple Answer Question The line of balance is a device for planning and monitoring progress of :Correct Answer Purchase order execution , Project execution , Targeted programs Your Answer Purchase order execution , Project execution , Targeted programs Select The Blank Question Forecasting is function of ________. Correct Answer Marketing department Your Answer Chief Executive officer True/False Question

The Heuristics approach has a base of binary number theory. Correct Answer False Your Answer True Multiple Choice Single Answer Question What shall be the consequence of acceptance of frequent rush orders by sales department? Correct Answer Delivery failure Your Answer Disturbed scheduling PPC-2 LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Multiple Answer Question The commonly used network techniques other than PERT and CPM are as follows :Correct Answer MOSS [ Multi Operation Scheduling System ] , PCS [ Project Control System ] , GERT [ Graphical Evaluation Review Techniques ] Your Answer MOSS [ Multi Operation Scheduling System ] , PCS [ Project Control System ] , GERT [ Graphical Evaluation Review Techniques ] Multiple Choice Single Answer Question In an unbalanced assignment, the tasks can be balanced by adding :Correct Answer Dummy tasks Your Answer Dummy tasks Multiple Choice Single Answer Question One of the causes of inability to meet delivery date originally promised :Correct Answer Lack of availability of material in time Your Answer Lack of availability of material in time

Multiple Choice Multiple Answer Question The main characteristics of mass and flow production are :Correct Answer Continuous flow of material , Low skilled labour , Easy supervision Your Answer Continuous flow of material , Low skilled labour , Easy supervision Multiple Choice Multiple Answer Question In a mass production assembly shop following work measurement techniques are used :Correct Answer Time study , Work sampling , Production study Your Answer Time study , Work sampling , Production study Multiple Choice Single Answer Question As the quantity increases, the procurement cost :Correct Answer Reduces Your Answer Reduces True/False Question Fluctuation due to changes in season are called cyclical fluctuation. Correct Answer False Your Answer True True/False Question A type items are always vital under VED analysis. Correct Answer False Your Answer False Select The Blank Question Random fluctuation is considered for deciding ________. Correct Answer Analytical estimate

Your Answer Seasonal fluctuation True/False Question In assignment matrix, it is a must to determine Jacobean of the determinant. Correct Answer False Your Answer False Select The Blank Question If Kwh consumption per 100 pieces is 8.01 and cost/kwh is Rs 0.80 the cost of power over the year for 40000 pieces with 2000 numbers rejection would be Rs ________. Correct Answer 2692 Your Answer 2692 Select The Blank Question At each ________, work is performed on a product either by adding parts or by completing assembly operations. Correct Answer Work station Your Answer Work station Multiple Choice Multiple Answer Question To operate fixed order quantity system, following parameters are required to be fixed:Correct Answer Standard reorder quantity , Minimum stock , Re-order point Your Answer Minimum stock , Re-order point , Standard reorder quantity Multiple Choice Single Answer Question Why customer is called the king? Correct Answer Customers orders gives us work Your Answer Customers orders gives us work

Select The Blank Question A progress card normally contains ________ squares. Correct Answer Less than 25 Your Answer Less than 25 Select The Blank Question ________ models of OR serve as an ideal aid for determining optimal sequence of jobs. Correct Answer Sequencing Your Answer Sequencing Multiple Choice Single Answer Question Ordering of raw material is based on :Correct Answer Sales forecast Your Answer Sales forecast Select The Blank Question Heuristics approach gave very good results when Wester and Kilbridge applied it to ________ assembly line. Correct Answer TV Your Answer Car Multiple Choice Single Answer Question What can be the consequence of inefficient working of department like sales? Correct Answer Failure on delivery date to customer Your Answer Failure on delivery date to customer True/False Question In PERT, use of dummy activities is not much essential. Correct Answer False

Your Answer False Multiple Choice Multiple Answer Question Work measurement is responsibility of :Correct Answer PPC , Industrial Engineering , Production department Your Answer PPC , Industrial Engineering , Production department Select The Blank Question The batch production requires ________ capital investment as compared to job production. Correct Answer High Your Answer High Select The Blank Question Time waste is the earliest of all wastes and yet the________ to correct because it does not litter the floor. Correct Answer Hazards Your Answer Hazards True/False Question To solve n jobs 2 machines sequencing problem, it is assumed that each machine can perform only one type of operation and can undertake only one job at a time. Correct Answer True Your Answer True True/False Question PERT is suitable in defense projects and R&D where activity times can not be really predicted. Correct Answer True Your Answer True

True/False Question In precedence diagram the length of arrow has very high degree of significance. Correct Answer False Your Answer True Multiple Choice Single Answer Question Earliest possible occurrence time [ I.e. stray time ] of activity [ies ] emanating from the event is represented by :Correct Answer Earliest event time Your Answer Earliest event time Multiple Choice Multiple Answer Question They are type of analytical estimate :Correct Answer Moving average , Exponential smothering , Curve fitting Your Answer Moving average , Exponential smothering , Curve fitting Multiple Choice Single Answer Question The production system characterized by complex set of activities that must be performed in a particular order within a given period and within an estimated expenditure is known as :Correct Answer Project production Your Answer Project production Match The Following Question Correct Answer Your Answer Time taken by each job at each machine Processing time Processing time Time between starting of first job and completion of last job Elapsed time Elapsed time Number of stages the job has to pass

Number of machines Number of machines Time during which the machine is standstill Idle time Idle time Select The Blank Question In the assignment model, the measure of effectiveness of each job for each machine can be represented by means of ________. Correct Answer Matrix Your Answer Matrix Multiple Choice Single Answer Question The ROI of the company can be increased by :Correct Answer Increasing profit & decreasing inventory Your Answer Increasing investment/sales ratio Multiple Choice Multiple Answer Question The software for CPA would require the following parameters:Correct Answer Algorithms , Program code , Database Your Answer Algorithms , Program code , Database Multiple Choice Multiple Answer Question Some of significant characteristics of fixed order quantity system under replenishment systems are as follows :Correct Answer Safety stock is kept to take care of increase in demand during lead time as well as to meet demand when lead time is extended. , Re-order level equals safety stock plus average consumption during lead time , Average inventory equals safety stock plus half of reorder quantity. Your Answer Safety stock is kept to take care of increase in demand during lead time as well as to meet demand when lead time is extended. , Re-order level equals safety stock plus average consumption during lead time , Average inventory equals safety stock plus half of reorder quantity.

Multiple Choice Multiple Answer Question Important considerations in scheduling are :Correct Answer Degree of centralization , Relative job priority , Load chart Your Answer Degree of centralization , Relative job priority , Load chart Multiple Choice Multiple Answer Question Methods for recording actual progress of work for shop orders are :Correct Answer Progress card , Display board , Network updating Your Answer Progress card , Display board , Network updating Select The Blank Question The unit cost of manufacturing is largest in case of ________. Correct Answer Job production Your Answer Job production Match The Following Question Correct Answer Your Answer HML Analysis Price orientation Price orientation SDE Analysis Procurement difficulties Procurement difficulties ABC analysis Usage value Usage value VED Analysis Criticality Criticality True/False Question The non-mathematical rationale of the assignment method is one of minimizing opportunity costs. Correct Answer

True Your Answer False True/False Question Moving average method lags behind the latest trend. Correct Answer True Your Answer True True/False Question The G group of GOLF analysis involves moderate delivery time and availability of credit usually in the range of 30 to 60 days. Correct Answer True Your Answer False Multiple Choice Multiple Answer Question Following difficulties are faced by SDE analysis :Correct Answer More delivery period , Geographical location of supplier , Reliability of suppliers Your Answer More delivery period , Geographical location of supplier , Reliability of suppliers Multiple Choice Single Answer Question The work measurement and time study belong to the school of management which was pioneered by :Correct Answer Fedric Winslow Taylor Your Answer Fedric Winslow Taylor Multiple Choice Single Answer Question Stock of finished goods are based on :Correct Answer Sales forecast Your Answer Sales forecast

Multiple Choice Single Answer Question The data in respect of spindle nose pertains to :Correct Answer Tooling Your Answer Raw material data Multiple Choice Multiple Answer Question In linear programming method of line balancing, there are three types of constraints namely :Correct Answer Cycle time constraint , Step or task constraint , Precedence constraints Your Answer Cycle time constraint , Step or task constraint , Precedence constraints Select The Blank Question Buying for C quantities should be made in ________ quantities . Correct Answer Large Your Answer Large

PPC-3 LIST OF ATTEMPTED QUESTIONS AND ANSWERS True/False Question Purchase department must keep PPC informed regarding lead time of different items specially where lead times are extended. Correct Answer True Your Answer True True/False Question In order to complete a project on time, each critical activity need not be completed in time. Correct Answer False

Your Answer False Select The Blank Question Because of uncertainty of activity timings, PERT acquired a shape of ________ model. Correct Answer Probabilistic Your Answer Probabilistic True/False Question Flexibility and product variety are not inter-related with each other. Correct Answer False Your Answer False Multiple Choice Multiple Answer Question The G group of GOLF analysis covers items procurement from Government suppliers such as :Correct Answer STC , MMTC , Public Sector Undertaking Your Answer STC , MMTC , Public Sector Undertaking Select The Blank Question Buying for C quantities should be made in ________ quantities . Correct Answer Large Your Answer Small Select The Blank Question Of all the work measurement techniques the most widely used techniques is________. Correct Answer Time study Your Answer Time study Multiple Choice Single Answer Question

Keeping available time per day constant, if the desired production rate per day is to be doubled ,cycle time will be reduced by :Correct Answer 0.5 Your Answer 0.5 Select The Blank Question In alternate routing, the delayed job may be routed to a ________ machine where rate of production is faster. Correct Answer Costlier Your Answer New Multiple Choice Single Answer Question Mass & flow production and process production are categorized under :Correct Answer Continuous production Your Answer Continuous production Multiple Choice Single Answer Question The earliest start time of an activity equals to earliest event time of :Correct Answer Tail event Your Answer Head event Multiple Choice Single Answer Question If efficiency is more, the manufacturing time required for completion of job would be generally :Correct Answer Less Your Answer Less Match The Following Question Correct Answer Your Answer Move order

Transport material from and to required work centers Transport material from and to required work centers Materials Order Allocation of material required in connection with shop order Allocation of material required in connection with shop order Work Order Birds eye view of production programme Order from contractor to execute job Production Order Reserve material required in connection with sales order Reserve material required in connection with sales order Multiple Choice Single Answer Question Development of additional vendors/suppliers depends upon :Correct Answer Sales forecast Your Answer Sales forecast Multiple Choice Single Answer Question The assignment method is also called as :Correct Answer Hungarian Method Your Answer Hungarian Method Multiple Choice Multiple Answer Question Material control function embraces a following techniques :Correct Answer Make -or -buy decision , Paretos analysis , Replenishment system Your Answer Make -or -buy decision , Replenishment system Multiple Choice Multiple Answer Question Overtime can be avoided in many ways and they are :Correct Answer Unrealistic delivery date , Acceptance of too many rush order , Excessive machine breakdown Your Answer Acceptance of too many rush order , Excessive machine breakdown , Insufficient manpower or machines

Select The Blank Question Lead time is ________ for different items. Correct Answer Different Your Answer Different Multiple Choice Multiple Answer Question The tooling data is prepared in respect of following measuring instruments :Correct Answer Vernier caliper , Micrometer screw gauge , Strain gauge Your Answer Vernier caliper , Micrometer screw gauge , Strain gauge True/False Question The LOB technique is most appropriate for assembly operations involving number of distinct components. Correct Answer True Your Answer True Select The Blank Question If number of work stations is 8 and work content of all stations is 32 , the cycle time would be ________. Correct Answer 4 Your Answer 4 Multiple Choice Multiple Answer Question The minimum requirements for application software for line balancing are as follows :Correct Answer 1 Ghz processor , 1 Gb hard Disk free memory , Windows or equivalent operating system. Your Answer 1 Ghz processor , 1 Gb hard Disk free memory , Windows or equivalent operating system. Multiple Choice Multiple Answer Question

Detachable Card contain following information :Correct Answer Quantity produced , Operation , Date of completion Your Answer Quantity produced , Operation , Sequence of operation Multiple Choice Single Answer Question The assembly work content [ Wi ] of the ith station having n work stations is given by :Correct Answer Wi from i=1 to n Your Answer Wi / n True/False Question Production Planning and Control makes the supervisor ineffective. Correct Answer True Your Answer False Select The Blank Question ________ are grouped so that their total time is preferably equal to or little lesser than the time available each work station. Correct Answer Tasks Your Answer Assembly lines Multiple Choice Single Answer Question The work measurement and time study belong to the following school of management :Correct Answer Scientific School of management Your Answer Scientific School of management Multiple Choice Multiple Answer Question Economic indicator for forecasting fertilizer requirements are :Correct Answer Land under cultivation , Trends of rainfall , Credit offered by banks Your Answer Land under cultivation , Trends of rainfall , Credit offered by banks

Multiple Choice Single Answer Question As the quantity increases, the procurement cost :Correct Answer Reduces Your Answer Also increases Multiple Choice Multiple Answer Question To minimize total throughout time we are required to minimize :Correct Answer Queuing , Idle time , Inventory Your Answer Queuing , Idle time Multiple Choice Multiple Answer Question Following are the factors which influence tool life :Correct Answer Type of tool , Material it is required to operate upon , Operators efficiency Your Answer Type of tool , Material it is required to operate upon , Operators efficiency Multiple Choice Single Answer Question What are the customers expectation from the supplier? Correct Answer Consistent good quality of products Your Answer Consistent good quality of products Multiple Choice Multiple Answer Question While communicating to customer on delays in delivery following information should be given :Correct Answer Information on identification of job , Reasons for delays , Revised date of delivery Your Answer Reasons for delays , Revised date of delivery , Derailed production records Select The Blank Question Job production requires ________ capital investment. Correct Answer Lowest

Your Answer High Multiple Choice Multiple Answer Question To operate fixed order quantity system, following parameters are required to be fixed:Correct Answer Minimum stock , Re-order point , Standard reorder quantity Your Answer Minimum stock , Re-order point , Breakeven point Match The Following Question Correct Answer Your Answer End piece allowance Material insufficient to produce one piece Material insufficient to produce one piece Stock allowance Quantity to meet requirement of spares Quantity to meet requirement of spares Machining allowance Extra material requirement Extra material requirement Spoilage allowance Process rejection Process rejection Select The Blank Question Work sampling is ________ Correct Answer Done at random interval Your Answer Done continuously without interval Select The Blank Question The information on the nature of tooling required for an item can be obtained from its ________. Correct Answer Route sheet Your Answer Route sheet

Multiple Choice Multiple Answer Question The main characteristics of jobbing production are :Correct Answer Small production runs , Discontinuous flow of materials , Disproportionate manufacturing cycle time Your Answer Small production runs , Discontinuous flow of materials , Disproportionate manufacturing cycle time Multiple Choice Single Answer Question Let us suppose that activity P & Q can not start until activity R& S are completed. Activities P &Q are therefore :Correct Answer Succeeding Your Answer Succeeding Multiple Choice Single Answer Question Critical ratio equals to one indicates that :Correct Answer Job is just on schedule and requires to be watched closely. Your Answer Job is just on schedule and requires to be watched closely. True/False Question Random fluctuation is addition of cyclical fluctuation and seasonal fluctuation. Correct Answer False Your Answer True True/False Question Labour efficiency factor is applied after capacity requirement of equipment is calculated. Correct Answer False Your Answer True Select The Blank Question ________ is the specific instant of time that marks start and end of activity.

Correct Answer Event Your Answer Event True/False Question Increase in inventory carrying cost increases EOQ. Correct Answer False Your Answer True True/False Question A company where different personnel give conflicting delivery promises need to improve its scheduling and processing function. Correct Answer True Your Answer True True/False Question A type items are always vital under VED analysis. Correct Answer False Your Answer True

PPC-4 LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Multiple Answer Question Purchase cost include :Correct Answer Excise , Packing and forwarding , Octroi Your Answer Excise , Octroi True/False Question

Inspection operations is a part of process plan for a part. Correct Answer True Your Answer True Multiple Choice Single Answer Question Why customer is called the king? Correct Answer Customers orders gives us work Your Answer Customers orders gives us work True/False Question To solve n jobs 3 machines sequencing problem, the largest of time of any job on the second machine must be smaller than or equal to the smallest time of any job on first machine or third machine. Correct Answer True Your Answer True True/False Question Line staff can assist PPC by manufacturing some of their needs in their own shops rather than making PPC to tool room or purchase. Correct Answer True Your Answer False Multiple Choice Single Answer Question Ordering of raw material is based on :Correct Answer Sales forecast Your Answer Material availability Multiple Choice Multiple Answer Question The queue time is intended to compensate for the time for which the job has to :Correct Answer Wait near the machines for its turn until other jobs ahead of it are completed. , Lie after

its completion till is picked up and moved to next machine/work center. , Spend extra time due to emergent situations Your Answer Wait near the machines for its turn until other jobs ahead of it are completed. , Lie after its completion till is picked up and moved to next machine/work center. , Wait until inspection and storage is completed. Multiple Choice Multiple Answer Question In an organization, poor material handling system may result in the following :Correct Answer Damage to material/product , Delays in supply of material , Accidents while handling Your Answer Damage to material/product , Delays in supply of material , Accidents while handling True/False Question LOB is a manual planning and scheduling technique similar in nature to MRP [Material Resource Planning]. Correct Answer True Your Answer False Multiple Choice Multiple Answer Question Standard time accounts for :Correct Answer Contingency allowance , Operators rating/efficiency , Tool change time Your Answer Contingency allowance , Tool change time , Job splitting time True/False Question As per a study on materials management practices, a typical firm spends almost half of its rupee sales on goods purchased from vendors. Correct Answer True Your Answer False Select The Blank Question ________ analysis mainly helps to identify non-existing items for which store keeps bin cards, wastes computer memory or wastes computer stationary while preparing stores ledger.

Correct Answer MNG Analysis Your Answer SOS Analysis Multiple Choice Single Answer Question If more variety is to be manufactured, the manufacturing facilities would have to be :Correct Answer Commonised Your Answer Expanded True/False Question Work measurement is not useful for choosing between two alternate methods of production. Correct Answer False Your Answer False True/False Question On completion of work the job card is returned to production planning and control department for reference and record. Correct Answer False Your Answer True True/False Question Curve fitting method of statistical forecasting uses curve line approach. Correct Answer False Your Answer True Select The Blank Question ________ is a production line made up of operations that form or change the physical or sometimes chemical characteristics of a product. Correct Answer Fabrication line

Your Answer Assembly line Multiple Choice Single Answer Question Keeping procurement cost and carrying cost constant, if annual usage of certain product becomes 4 times, the EOQ would be :Correct Answer Doubled Your Answer Halved Multiple Choice Single Answer Question LOB technique was devised by US army in the year :Correct Answer 1952 Your Answer 1955 True/False Question Transit time for manufactured items should be considered only when it is insignificant. Correct Answer False Your Answer False Multiple Choice Multiple Answer Question 5 jobs are to be processed on machines M1 and M2 , first on M1 and then on M2. The processing times in hours are as follows.Find the sequence for 5 jobs that will minimize total elapsed time .also find idle time & total elapsed time. Job Processing time [ hours ] Machine M1 Machine M2 1 5 2 2 1 6 8 9 7 6 3 8 5 10 4 Correct Answer 2-4-3-5-1 , Minimum time 28 hours , Idle time = 1 & 2 Hours for M1 & M2 respectively. Your Answer 2-4-3-5-1 , Minimum time 28 hours , Idle time = 1 & 2 Hours for M1 & M2 respectively. Multiple Choice Multiple Answer Question SDE analysis is based on problems of procurement namely :Correct Answer Non-availability , Scarcity , Longer lead time Your Answer Non-availability , Scarcity , Longer lead time

Multiple Choice Multiple Answer Question In a mass production assembly shop following work measurement techniques are used :Correct Answer Time study , Work sampling , Production study Your Answer Time study , Production study , Analytical estimating Multiple Choice Multiple Answer Question Due to the following emergent events, the queue time has to compensate for the time for which the job has to undergo an extra time :Correct Answer Tool breakage , Job split up , Change in priorities Your Answer Tool breakage , Job split up , Store inventory Select The Blank Question Given the following data :- procurement cost per order = Rs 30 ; frequency of ordering per year =4 ; number of suppliers = 3 . Form the above data, total procurement cost would be Rs ________. Correct Answer 360 Your Answer 40 Multiple Choice Multiple Answer Question In replenishment system, the fixed order quantity system is also called by following names :Correct Answer Fixed order system , Min-max system , Re-order point system Your Answer Fixed order system , Min-max system , Re-order point system Multiple Choice Single Answer Question Given a decision for designing a line layout, major problem is subdividing a work so that smooth flow can result. The subdivision process is called :Correct Answer Line balancing Your Answer Line balancing

True/False Question In CPM, use of dummy activities is much essential . Correct Answer False Your Answer False Multiple Choice Multiple Answer Question The commonly used network techniques other than PERT and CPM are as follows :Correct Answer MOSS [ Multi Operation Scheduling System ] , PCS [ Project Control System ] , GERT [ Graphical Evaluation Review Techniques ] Your Answer MOSS [ Multi Operation Scheduling System ] , PCS [ Project Control System ] , GERT [ Graphical Evaluation Review Techniques ] Match The Following Question Correct Answer Your Answer Work element Smallest portion of work identified during the breakdown analysis of the job. Smallest portion of work identified during the breakdown analysis of the job. Production line Arrangement of workstations where each workman performs a pre-determined task on an incomplete unit which passes down the line of subsequent unit until it is finished. Arrangement of workstations where each workman performs a pre-determined task on an incomplete unit which passes down the line of subsequent unit until it is finished. Work Station Assigned location, zone, place or stage in assembly where designated work is performed on part component of product. Assigned location, zone, place or stage in assembly where designated work is performed on part component of product. Station work content Time required to perform the designated amount of work at a given work station and is obtained by adding up time of work elements allotted to the work station. Time after which a finished product comes off the production line. Multiple Choice Multiple Answer Question Steps involved in process planning include the following :Correct Answer Enlist feature influencing selection of manufacturing process , Prepare sequence of basic operation , Write down route sheet

Your Answer Prepare sequence of basic operation , Write down route sheet , Indent requirement of tooling and fixtures Multiple Choice Single Answer Question Effective capacity per period is calculated as :Correct Answer Multiplication of net capacity with labour efficiency Your Answer Multiplication of net capacity by utilization index Select The Blank Question Orders with ________ slack time remaining per operation are run first. Correct Answer Shortest Your Answer Longest Match The Following Question Correct Answer Your Answer Time taken by each job at each machine Processing time Job time Time between starting of first job and completion of last job Elapsed time Processing time Number of stages the job has to pass Number of machines Number of machines Time during which the machine is standstill Idle time Job priority Select The Blank Question LOB has advantage that it is more ________ oriented than MRP. Correct Answer Customer Your Answer Practical

Multiple Choice Single Answer Question A company has 10 machines, working in two shifts. Utilization index is 0.75 and shop efficiency is 80%. Effective capacity hours for loading and scheduling are :Correct Answer 576 Your Answer 576 Multiple Choice Single Answer Question The cost involved in subcontracting some of the operations of item outside the home plant is called :Correct Answer Outside operations cost Your Answer Outdoor cost Multiple Choice Multiple Answer Question LOB deals with :Correct Answer Identification of crucial operations in a job , Establishment of schedules of crucial operations , Attraction of attention of those who do not conform to the schedule. Your Answer Identification of crucial operations in a job , Establishment of schedules of crucial operations , Attraction of attention of those who do not conform to the schedule. Select The Blank Question ________items should be excluded from ABC Analysis. Correct Answer Non-moving Your Answer Seasonal Multiple Choice Single Answer Question To keep facilities busy, waiting time due to non-availability of work should be kept at :Correct Answer Minimum . Your Answer Minimum . Multiple Choice Single Answer Question

Installed capacity :Correct Answer Can be equal to or less than licensed capacity Your Answer Can be equal to or less than licensed capacity Multiple Choice Single Answer Question Scheduling can be considered as a process of :Correct Answer Fitting shop order into uncommitted time available for a machine Your Answer Determining time required for each operation Select The Blank Question Short term forecasts are for ________. Correct Answer Material Planning Your Answer Material Planning Select The Blank Question The ________ makes scheduling process simpler but does not provide economy in manufacture. Correct Answer First-come-first scheduled Your Answer First-come-first scheduled Select The Blank Question Good quality and ________are the two main requirements to secure maximum business from a customer. Correct Answer Competitive rates Your Answer Competitive rates Select The Blank Question Generally for ________ flow system, Heuristic method is preferred. Correct Answer Intermittent

Your Answer Continuous Multiple Choice Single Answer Question Sequencing helps management to determine the most economical job sequence the one that consumes minimum :Correct Answer Elapsed time Your Answer Lead time

QT-1 LIST OF ATTEMPTED QUESTIONS AND ANSWERS Select The Blank Question Terminology for Service Distribution is ________ Correct Answer FCFS or LCFS Your Answer Poisson M Multiple Choice Single Answer Question The information required to study an input process is :Correct Answer Mean arrival rate Your Answer Pattern of arrival Select The Blank Question Another name of Un-occupied Cells is ________. Correct Answer Water Cells Your Answer Water Cells Multiple Choice Multiple Answer Question What is the application of quantitative techniques in maintenance management? Correct Answer To decide optimum stocking policies of spares , Predict useful life of parts , To decide optimum replacement policy of parts Your Answer To decide optimum stocking policies of spares , Predict useful life of parts , To decide optimum replacement policy of parts True/False Question If a mixed strategy game is bigger than 22 size, dominance rule is used to reduce the game. Correct Answer True Your Answer True

Multiple Choice Multiple Answer Question Types of the Service Facilities are :Correct Answer Single queue: Single server , Single queue: Multiple server , Single queue: Multiple server (Parallel) Your Answer Single queue: Single server , Single queue: Multiple server , Single queue: Multiple server (Parallel) Multiple Choice Multiple Answer Question Which are the typical areas of application of probability theory? Correct Answer Market research , Inventory control , Price movements Your Answer Market research , Inventory control , Price movements True/False Question Smallest element in each row is subtracted from each element in the column. Correct Answer False Your Answer False Multiple Choice Single Answer Question Graphical method is used to solve problems involving how many unknowns? Correct Answer Two Your Answer Two True/False Question Stepping stone method is to evaluate unoccupied cells to achieve an optimal solution. Correct Answer True Your Answer False Select The Blank Question Dummy source is also termed as ________. Correct Answer

Destination Your Answer Destination Multiple Choice Multiple Answer Question Terminologies of Graphical Method are :Correct Answer Constraints , Graph of linear equality/inequality , Half Space Your Answer Constraints , Graph of linear equality/inequality , Half Space Match The Following Question Correct Answer Your Answer Adaptive decisions The outcomes of each decision alternative are not predictable The outcomes of each decision alternative are not predictable Mechanistic decisions The outcomes of each decision alternative are known The outcomes of each decision alternative are known Analytical decisions The outcomes of each decision alternative can be computed The outcomes of each decision alternative can be computed Judgmental decisions The outcomes of each decision alternative is unknown The outcomes of each decision alternative is unknown Multiple Choice Multiple Answer Question Which are applications of quantitative techniques in financial management? Correct Answer Interpretation of financial statements , To determine optimum equipment replacement policies , To develop capital investment plans Your Answer Interpretation of financial statements , To determine optimum equipment replacement policies , To develop capital investment plans Multiple Choice Multiple Answer Question Various Quantitative Techniques are :Correct Answer Replacement Theory , Queuing Theory , Linear Programming Your Answer Linear Programming , Replacement Theory , Queuing Theory

Multiple Choice Single Answer Question A variable used to convert a greater than or equal to constraint into equality by subtracting it from left hand side of the constraint is :Correct Answer Surplus Variable Your Answer Slack Variable Multiple Choice Multiple Answer Question Terms related to NCWM, VAM & LCM are :Correct Answer Allocation of units , Upper left hand corner , High Penalty cost Your Answer Allocation of units , Upper left hand corner , High Penalty cost Multiple Choice Multiple Answer Question Resource Management involves Correct Answer Man , Machines , Materials Your Answer Man , Machines , Materials Select The Blank Question Expected gain resulting from mixed strategy equals ________of possible outcomes. Correct Answer Weighted average Your Answer Weighted average Multiple Choice Multiple Answer Question Which are the typical areas of application of forecasting? Correct Answer Materials control , Loading and scheduling , Budgeting Your Answer Materials control , Loading and scheduling , Budgeting Select The Blank Question The ________ is a method for deciding how to meet some desired objective which may be profit maximisation or cost minimization, subject to constraints on the amounts of commodities required or resources available.

Correct Answer Linear programming Your Answer Linear programming Multiple Choice Multiple Answer Question Different Terms related to Simplex Method are :Correct Answer Algorithm , Iteration , Slack variable Your Answer Algorithm , Iteration , Slack variable Multiple Choice Single Answer Question A variable used to convert less than or equal to constraint into equality constraint by adding it to the left side of the constraint is :Correct Answer Slack Variable Your Answer Slack Variable Select The Blank Question Minimax value sets ________ limit on game. Correct Answer Upper Your Answer Upper Select The Blank Question Number of customers in the queue plus those being serviced is ________. Correct Answer System Length Your Answer System Length True/False Question Problem Formulation involves construction of a mathematical model from the given data. Correct Answer True Your Answer True

Select The Blank Question Transportation Tableau gives ________. Correct Answer Data on shipping costs Your Answer Data on shipping costs Select The Blank Question SOPs provide necessary base to select optimal solution is known as ________. Correct Answer Mechanistic Decisions Your Answer Mechanistic Decisions Select The Blank Question ________ is an extra row in tableau, with zero cost in each of its cells, used to balance an unbalanced problem Correct Answer Dummy source Your Answer Dummy source True/False Question Check for improvement potential is a procedural step for MODI method. Correct Answer True Your Answer True Multiple Choice Single Answer Question Infeasible Solution :Correct Answer No solution satisfies all constraints Your Answer No solution satisfies all constraints Multiple Choice Multiple Answer Question Saddle points equals to :Correct Answer Assigning task to facility , Maximin

Your Answer Assigning task to facility , Maximin True/False Question Graphical method is restricted to two variables. Correct Answer True Your Answer True True/False Question Service time can be either fixed & balanced layouts or it can be variable. Correct Answer True Your Answer False Select The Blank Question Definition of Dummy source is ________. Correct Answer Extra row or column in tableau, with zero cost in each of its cells, used to balance an unbalanced problem Your Answer Extra row or column in tableau, with zero cost in each of its cells, used to balance an unbalanced problem Multiple Choice Multiple Answer Question Words related to LCM are :Correct Answer Least , Method , Cost Your Answer Least , Method , Cost Multiple Choice Single Answer Question Which of the following is example of programmed decision? Correct Answer Sanctioning or regretting leave to an employee Your Answer Sanctioning or regretting leave to an employee

True/False Question In a mixed strategy game players play more than one strategy to optimize the gain. Correct Answer True Your Answer True Multiple Choice Single Answer Question Games theory is applied when :Correct Answer Competing strategies are to be decided Your Answer Competing strategies are to be decided Multiple Choice Multiple Answer Question Rules concerning Constraints are :Correct Answer Less than or equal to are reduced to equations by adding slack variable , Greater than or equal to are converted to equation by adding slack variable , Equal to are augmented by adding artificial variable Your Answer Less than or equal to are reduced to equations by adding slack variable , Greater than or equal to are converted to equation by adding slack variable , Equal to are augmented by adding artificial variable Multiple Choice Single Answer Question A systematic procedure to obtain an initial feasible solution allocating units to the cells of the transportation table beginning in the upper left hand corner is :Correct Answer North West Corner Method Your Answer North West Corner Method True/False Question Infeasibility is the condition in which the Linear Programming problem permits no feasible combination of the decision variables. Correct Answer True Your Answer True

Multiple Choice Single Answer Question Balanced Transportation Problem is :Correct Answer A special type of LP problem that involves transportation or physical distribution of goods or services from supply points to demand points Your Answer Transportation problem in which total capacity at supply point doesnt equal the total demand at the destinations Multiple Choice Single Answer Question Which technique replaces the age old intuitive and subjective approach of decision making by an analytical and an objective approach? Correct Answer Quantitative technique Your Answer Quantitative technique Match The Following Question Correct Answer Your Answer Procedure of allocating units to cells North West Corner Method North West Corner Method Procedure of allocating units to cost Least Cost Method Least Cost Method Extra row or column in a tableau Dummy source or Destination Dummy source or Destination Satisfies supply & demand conditions An Initial Feasible Solution An Initial Feasible Solution Multiple Choice Single Answer Question Which of the following is not a statistical technique? Correct Answer Critical path analysis Your Answer Critical path analysis Multiple Choice Single Answer Question

Which of the following is example of personal decision? Correct Answer Works managers decision to quit his post Your Answer Works managers decision to quit his post

QT -2 LIST OF ATTEMPTED QUESTIONS AND ANSWERS Select The Blank Question Expected gain to a player, if he and & his opponent use their best strategy is called ________of game. Correct Answer Value Your Answer Value Select The Blank Question Decision Making under Un-certainty is called as ________. Correct Answer Uncertain Situations Your Answer Uncertain Situations Multiple Choice Single Answer Question If Pij represent element in each column, than minimax value of game is :Correct Answer Min (max pij) Your Answer Min (max pij) Select The Blank Question Cash flows & determining Optimal investment proposal is ________. Correct Answer Investment Theory Your Answer Investment Theory

Multiple Choice Single Answer Question Graphical method is restricted to :Correct Answer Two Variables Your Answer Two Variables Multiple Choice Multiple Answer Question Combination of strategies of players determines :Correct Answer Outcomes , Payoff Your Answer Outcomes , Payoff Multiple Choice Single Answer Question In a pure strategy game if there are two maximin values, then the no optimal strategies for players and is :Correct Answer Two Your Answer No optimal strategy Multiple Choice Multiple Answer Question Game can have :Correct Answer Mixed strategies , Pure strategies Your Answer Mixed strategies , Pure strategies Multiple Choice Multiple Answer Question In solution of an assignment problem a row with zero costs is added and all the elements are multiplied by 1, then the problem is of nature :Correct Answer Unbalance assignment. , Maximization. Your Answer Unbalance assignment. , Maximization. True/False Question Value of the subgame related to highest point in the feasible region is solution for 2xn game.

Correct Answer True Your Answer True Multiple Choice Single Answer Question Graphical method deals with problem of :Correct Answer Both Maximization & Minimization Your Answer Both Maximization & Minimization Multiple Choice Single Answer Question A systematic procedure to obtain an initial feasible solution allocating units to the cells of the transportation table beginning in the upper left hand corner is :Correct Answer North West Corner Method Your Answer North West Corner Method True/False Question Variable used to convert a greater than equal to constraint into equality by subtracting it from left hand side of the constraint is Surplus Variable. Correct Answer True Your Answer True Select The Blank Question Equation of constraints & ________ sets up Simplex method. Correct Answer Objective Function Your Answer Objective Function Select The Blank Question Finding out the quantity of components to be used at ________. Correct Answer Minimum Cost Your Answer Maximum Cost

Multiple Choice Single Answer Question Value of a game having saddle point equals :Correct Answer Saddle point Your Answer Saddle point Multiple Choice Single Answer Question Systematic procedure to obtain initial feasible solution by allocating as many units as possible to the lowest cost cell in the transportation table is :Correct Answer Least Cost Method Your Answer Least Cost Method True/False Question Personal decisions can affect the organisation and organisational decisions can affect the person. Correct Answer True Your Answer True True/False Question Column with the highest negative index number is called a Key Column. Correct Answer True Your Answer True Match The Following Question Correct Answer Your Answer Transportation Tableau Data on shipping costs Data on shipping costs Transportation Problem Transportation of goods or services Transportation of goods or services Balanced Transportation Problem Supply points equals total demand

Supply points equals total demand Un-balanced Transportation Problem Supply points does not equal demand Supply points does not equal demand Multiple Choice Single Answer Question Optimal Solution is :Correct Answer That point or points in the feasible region that gives the optimal values of the objective function Your Answer That point or points in the feasible region that gives the optimal values of the objective function Multiple Choice Multiple Answer Question Elements of Transportation Model are :Correct Answer Plants , Warehouses , Supply & Demand Your Answer Plants , Warehouses , Supply & Demand Multiple Choice Multiple Answer Question Purchase Management involves :Correct Answer Purchase Orders , Vendor Evaluation , Negotiation of Supplier Prices Your Answer Purchase Orders , Vendor Evaluation , Negotiation of Supplier Prices True/False Question When number of zeros in final assignment matrix are more than required ones, the problem has alternative optimal solution. Correct Answer True Your Answer True Match The Following Question Correct Answer Your Answer Decision making under uncertainty Uncertain situations

Uncertain situations Decision making under certainty Deterministic models Deterministic models Decision making under conflict Competitive strategies Competitive strategies Decision making under risk Stochastic models Stochastic models Select The Blank Question Value of pure strategy game to player II is ________. Correct Answer Negative Minimax Your Answer Negative Minimax Select The Blank Question Dummy source is also termed as ________. Correct Answer Destination Your Answer Determination Multiple Choice Single Answer Question An extra variable added to obtain an initial feasible solution to a Linear Programming problem is called :Correct Answer Artificial Variable Your Answer Slack Variable Multiple Choice Single Answer Question Graphical method can deal with :Correct Answer Any number of constraints Your Answer Two constraints Multiple Choice Multiple Answer Question

Procedural steps in VAM are :Correct Answer Calculation of difference bet 2 element , Selection of row or column , Allocation of number of units Your Answer Calculation of difference bet 2 element , Selection of row or column , Allocation of number of units Multiple Choice Multiple Answer Question Objects too can form queues as :Correct Answer Semi-finished job await next operation , Broken down to be repaired , Blunt tools awaiting to be reground Your Answer Semi-finished job await next operation , Broken down to be repaired , Blunt tools awaiting to be reground True/False Question The graphical method is simple to understand & easy to use Correct Answer True Your Answer True True/False Question Minimax vale of the game sets upper limit to the value of the game. Correct Answer True Your Answer True Select The Blank Question Definition of Dummy source is ________. Correct Answer Extra row or column in tableau, with zero cost in each of its cells, used to balance an unbalanced problem Your Answer Extra row or column in tableau, with zero cost in each of its cells, used to balance an unbalanced problem True/False Question

If a mixed strategy game is bigger than 22 size, dominance rule is used to reduce the game. Correct Answer True Your Answer True Select The Blank Question ________ is the last step of Graphical Method of LP. Correct Answer Calculate the total profit / loss Your Answer Calculate the total profit / loss Multiple Choice Multiple Answer Question Rules concerning Constraints are :Correct Answer Less than or equal to are reduced to equations by adding slack variable , Greater than or equal to are converted to equation by adding slack variable , Equal to are augmented by adding artificial variable Your Answer Less than or equal to are reduced to equations by adding slack variable , Equal to are augmented by adding artificial variable , Non-negativity restrictions Select The Blank Question To solve a maximization problem, all elements in the matrix are subtracted from ________ element in the matrix. Correct Answer Largest Your Answer Largest Multiple Choice Multiple Answer Question Shadow prices help to identify high cost resources which need :Correct Answer Management attention for minimizing waste , Developing cost saving methods , Searching for substitute materials to reduce costs Your Answer Management attention for minimizing waste , Developing cost saving methods , Searching for substitute materials to reduce costs

Multiple Choice Single Answer Question Which criteria is used to classify the managerial decisions into four categories as mechanistic decisions, analytical decisions, judgmental decisions and adaptive decisions? Correct Answer Complexity of problem and degree of certainty about the outcome Your Answer Complexity of problem and degree of certainty about the outcome Select The Blank Question The ________ represents consequences of the interactions of the decision alternatives and the chance events. Correct Answer Outcomes Your Answer Outcomes Multiple Choice Single Answer Question Which of the decision theory model indicates the situations where consequences of each act of decision maker are influenced by acts of opponent? Correct Answer Competitive strategies Your Answer Competitive strategies True/False Question When there is alternative optimal solution to an assignment problem, total cost of each alternative is different. Correct Answer False Your Answer False True/False Question A redundant constraint is necessary for the solution to the problem & therefore can be omitted at the time of formulation of the problem. Correct Answer False Your Answer True

Multiple Choice Multiple Answer Question MRP II is associated with :Correct Answer Men , Machine , Material Your Answer Men , Machine Multiple Choice Multiple Answer Question Saddle points equals to :Correct Answer Assigning task to facility , Maximin Your Answer Assigning task to facility , Maximin , Weighted average and possible outcome Multiple Choice Multiple Answer Question Nomenclatures related to Transportation Problem are :Correct Answer S,P,W Your Answer S,W,M QT-3

LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Single Answer Question A mixed strategy is decision of player to select :Correct Answer Different strategies Your Answer Different strategies Multiple Choice Single Answer Question How many different basic models are used to classify the decision theory on the basis of ability to predict the consequences of each alternative? Correct Answer Four Your Answer Four

Multiple Choice Multiple Answer Question How do the quantitative techniques help a decision maker in three ways? Correct Answer Aid decision making , Automate decision making and reduce it to a routine affair , Guide decision making Your Answer Aid decision making , Automate decision making and reduce it to a routine affair , Guide decision making True/False Question A game in which algebraic sum of gains of both the players after the play is not zero is called two person non zero sum game. Correct Answer True Your Answer True True/False Question To construct a pay off matrix the decision alternatives are placed column head wise. Correct Answer False Your Answer False Multiple Choice Single Answer Question The simplex method though is an algebraic procedure but it is based on :Correct Answer Geometrical Concept Your Answer Geometrical Concept Multiple Choice Single Answer Question Which of the following is not a statistical technique? Correct Answer Critical path analysis Your Answer Critical path analysis Multiple Choice Multiple Answer Question Rules concerning Objective Function are :-

Correct Answer Must contain all variables in the constraints , Coefficient of slack variables are assumed to be zero , Coefficient of artificial variables are taken as M Your Answer Must contain all variables in the constraints , Negativity restrictions True/False Question Risk represent the probability estimate of nonoccurrence of each outcome. Correct Answer False Your Answer True Match The Following Question Correct Answer Your Answer Intersecting element is The element at the intersection of other than key key row & key column The element at the intersection of other than key key row & key column Key Column is The column with the largest negative index number The column with the largest negative index number Key row is The row with the smallest of the replacement ratios of the constraint rows The row with the smallest of the replacement ratios of the constraint rows Key element is The element at the intersection of key row & key column The element at the intersection of key row & key column Multiple Choice Multiple Answer Question Constraints in traveling salesman problem are :Correct Answer Salesman should not visit the city twice. , No assignment can be made along diagonal. Your Answer Salesman should not visit the city twice. , No assignment can be made along diagonal. Select The Blank Question The ________ is a method for deciding how to meet some desired objective which may be profit maximisation or cost minimization, subject to constraints on the amounts of commodities required or resources available. Correct Answer Linear programming

Your Answer Linear programming Select The Blank Question Smallest replacement ratios row of the constraint rows is ________. Correct Answer Key row Your Answer Key row Multiple Choice Multiple Answer Question Terms related to NCWM, VAM & LCM are :Correct Answer Allocation of units , Upper left hand corner , High Penalty cost Your Answer Allocation of units , Upper left hand corner , High Penalty cost Multiple Choice Single Answer Question Which technique replaces the age old intuitive and subjective approach of decision making by an analytical and an objective approach? Correct Answer Quantitative technique Your Answer Quantitative technique Select The Blank Question LP is one of the most popular techniques of ________. Correct Answer Operation Research Your Answer Operation Research Multiple Choice Single Answer Question The variables with positive non-zero values are called :Correct Answer Basic Variables Your Answer Basic Variables Select The Blank Question

Managerial decisions can be classified on basis of frequency of occurrence of problem as basic decisions and ________. Correct Answer Routine decisions Your Answer Routine decisions Multiple Choice Multiple Answer Question Terms relating to LP are :Correct Answer Constraints , Objective Function , Non-Negativity Condition Your Answer Constraints , Objective Function , Non-Negativity Condition Multiple Choice Single Answer Question Expected gain to a player I he and his opponent use their best strategies is known as :Correct Answer Value of game Your Answer Value of game Multiple Choice Multiple Answer Question Terminologies of simplex method are :Correct Answer Key Row , Key Column , Key Element Your Answer Key Row , Key Column , Key Element Select The Blank Question The ________ is concerned with situations of conflicts between two or more opposed sets of interests to devise optimum strategies prior to commencement of action. Correct Answer Games theory Your Answer Games theory True/False Question Quantitative techniques are usually associated with high costs. Correct Answer True

Your Answer True Multiple Choice Single Answer Question Last Step of Graphical Method of LP is :Correct Answer Calculate the total profit / loss Your Answer Calculate the total profit / loss True/False Question Mechanistic decisions involve problems with limited number of decision variables. Correct Answer True Your Answer True Multiple Choice Multiple Answer Question Terms related to VAM are :Correct Answer Initial feasible solution , High Penalty cost , High cost cells Your Answer Initial feasible solution , High Penalty cost , High cost cells Multiple Choice Multiple Answer Question Study of Process Capability is not related to :Correct Answer Reliability Engineering , Statistical Process Control , Correlation & Regression Analysis Your Answer Reliability Engineering , Correlation & Regression Analysis , Probability Theory Multiple Choice Multiple Answer Question Queue Characteristics are :Correct Answer Input distribution , Output distribution , Service discipline Your Answer Service discipline , Single queue: Multiple server (Series) Multiple Choice Single Answer Question A customer may keep on switching from one Queue to another due to more service

counters. This tendency is called :Correct Answer Jockeying Your Answer Jockeying True/False Question A two person game offering 2 strategies to each player is called 22 game. Correct Answer True Your Answer True Multiple Choice Multiple Answer Question Elements of Queuing System are :Correct Answer Single Server , Multiple Servers (Series) , Multiple Servers (Parallel) Your Answer Single Server , Multiple Servers (Series) , Multiple Servers (Parallel) Select The Blank Question The ________ are those in which the outcome of the first decision affects the desirability of the choices at the next decision. Correct Answer Multi stage decisions Your Answer Multi stage decisions Multiple Choice Single Answer Question Graphical method is restricted to :Correct Answer Two Variables Your Answer Two Variables True/False Question Check for improvement potential is a procedural step for MODI method. Correct Answer True Your Answer True

Select The Blank Question A game in which gain of person is loss of the other player is called ________ game. Correct Answer Zero sum Your Answer Zero sum Select The Blank Question A ________ is an aid to decision making under risk, especially in a situation where the decision maker must make a sequence of decisions. Correct Answer Decision tree Your Answer Payoff matrix Multiple Choice Single Answer Question Maximum element among the minimum elements selected for each raw is called :Correct Answer Maximum Your Answer Maximum True/False Question Quantitative techniques consider tangible as well as intangible factors. Correct Answer False Your Answer False Select The Blank Question Minimax value sets ________ limit on game. Correct Answer Upper Your Answer Upper Select The Blank Question The ________ aims to achieve orderly flow of batches of a product at a sequence of unconnected work. Correct Answer

Line of balance Your Answer Line of balance Multiple Choice Single Answer Question Balanced Transportation Problem is :Correct Answer Supply points equals total demand Your Answer Supply points equals total demand Match The Following Question Correct Answer Your Answer Procedure of allocating units to cost Least Cost Method Least Cost Method Extra row or column in a tableau Dummy source or Destination Dummy source or Destination Satisfies supply & demand conditions An Initial Feasible Solution An Initial Feasible Solution Procedure of allocating units to cells North West Corner Method North West Corner Method True/False Question By application of dominance rule final solution is affected. Correct Answer False Your Answer False Multiple Choice Single Answer Question A customer may join the Queue, wait upto certain time & then leave the Queue without getting service. This action is called :Correct Answer Reneging Your Answer Reneging

True/False Question Infeasibility is the condition in which the Linear Programming problem permits no feasible combination of the decision variables. Correct Answer True Your Answer True True/False Question There is one queue & one server in the service facility is Single Queue: Single Server. Correct Answer True Your Answer True Select The Blank Question ________ is the last step of Graphical Method of LP. Correct Answer Calculate the total profit / loss Your Answer Calculate the total profit / loss

Vous aimerez peut-être aussi