Académique Documents
Professionnel Documents
Culture Documents
3-Jan-12
4-Jan-12
5-Jan-12
6-Jan-12
7-Jan-12
8-Jan-12
9-Jan-12
10-Jan-12 11-Jan-12
ACTIVITY
Site Survey
Site Survey Site Clearing Site Clearing Building Warehouse Building Warehouse Excavations for footings Delivery of Construction Materials I Excavations for footings Fabrication of rebars for footings Fabrication of rebars for ground floor columns Delivery of Construction Materials I Fabrication of forms for ground floor columns Scaffolding works for ground floor Fabrication of rebars for footings Inspection
Fabrication of rebars for ground floor columns Fabrication of forms for ground floor columns Scaffolding works for ground floor Inspection
Start Date Duration End Date 2-Jan-12 2 3-Jan-12 2-Jan-12 1 2-Jan-12 3-Jan-12 1 3-Jan-12 4-Jan-12 2 5-Jan-12 4-Jan-12 1 4-Jan-12 6-Jan-12 5 10-Jan-12 6-Jan-12 5 10-Jan-12 6-Jan-12 4 9-Jan-12 10-Jan-12 2 11-Jan-12 12-Jan-12 1 12-Jan-12
Acitivity Start Date Duration 13-Jan-12 20-Jan-12 Laying the foundation & erection of columns for frame 1 & A 13-Jan-12 4 Laying the foundation &foundation &columns forcolumns for frame 1 & A 17-Jan-12 4 Laying the erection of erection of frame 11 & F Laying the foundation & erection of columns of columns2, 3 frame 11 & F 21-Jan-12 5 Laying the foundation & erection for frame for & 4 Laying the foundation & erection of columns for frame 5, 6 & 7 26-Jan-12 5 Laying the foundation & erection of columns for frame 2, 3 & 4 Laying the foundation & erection of columns for frame 8, 9 & 10 31-Jan-12 5 Laying the foundation & erection of columns for frame 5, 6 & 7 Delivery of construction materials II 31-Jan-12 1 Laying the foundation & erection of columns for frame 8, 9 & 10 Excavation for wall footings 5-Feb-12 1 Delivery of construction materials II Laying the w.f & erecting of CHB walls for ground floor 6-Feb-12 10 Fabrication of rebars for 2nd floor beams 16-Feb-12 6 Excavation for wall footings Fabrication of forms for 2nd floor& erecting of CHB walls for ground floor 16-Feb-12 5 Laying the w.f beams
Fabrication of rebars for 2nd floor beams Fabrication of forms for 2nd floor beams
End date 27-Jan-12 16-Jan-12 20-Jan-12 25-Jan-12 30-Jan-12 4-Feb-12 31-Jan-12 5-Feb-12 15-Feb-12 21-Feb-12 20-Feb-12
3-Feb-12
10-Feb-12
17-Feb-12
24-Feb-12
Activity Start Date Duration End date Installation of rebars & forms for all 2nd floor beams in frame 1 & A 21-Feb-12 3 23-Feb-12 21-Feb-12 Inspection 23-Feb-12 1 23-Feb-12 Installation of Pouring of concrete for all 2nd floor beams in frame 1 & A rebars & forms for all 2nd floor beams in frame 1 & A 24-Feb-12 4 27-Feb-12 Installation of rebars & forms for all 2nd floor beams in frame 11 & F 28-Feb-12 4 1-Mar-12 Inspection Inspection 2-Mar-12 1 &A Pouring of concrete for all 2nd floor beams in frame 12-Mar-12 Pouring of concrete for all 2nd floor beams in Installation& Frebars & forms for all 2nd floor beams in frame 11 & F frame 11 of 3-Mar-12 4 6-Mar-12 Installation of rebars & forms for all 2nd floor beams in frame 2, 3 & 4 7-Mar-12 4 10-Mar-12 Inspection Inspection 11-Mar-12 1 11-Mar-12 Pouring of concrete for all 2nd floor beams in frame 11 & F Pouring of concrete for all 2nd floor beams in frame 2, 3 & 4 12-Mar-12 4 15-Mar-12 Installation of rebars & 6 & 7 3&4 Installation of rebars anf forms for all 2nd floor beams in frame 5, forms for all 2nd floor beams in frame42,19-Mar-12 16-Mar-12
Inspection Pouring of concrete for all 2nd floor beams in frame 2, 3 & 4 Installation of rebars anf forms for all 2nd floor beams in frame 5, 6 & 7
26-Feb-12
2-Mar-12
7-Mar-12
12-M
Mar-12
17-Mar-12
22-Mar-12
Activity Start Date Duration End Date 25-Mar-12 20-Mar-12 Inspection 20-Mar-12 1 20-Mar-12 Pouring of concrete for all 2nd floor beams in frame 5, 6 & 7 21-Mar-12 Inspection 24-Mar-12 4 Pouring of concrete for & 10 Installation of rebars and forms for all 2nd floor beams in frame 8, 9 all 2nd floor beams in frame 5, 6 & 7 28-Mar-12 25-Mar-12 4 Inspection 29-Mar-12 1 Installation of rebars and forms for all 2nd floor beams in frame 8, 9 & 10 29-Mar-12 Pouring of concrete for all 2nd floor beams in frame 8, 9 & 10 30-Mar-12 Inspection 2-Apr-12 4 Fabrication of forms for 2nd floor slab 3-Apr-12 2 4-Apr-12 Pouring of concrete for all 2nd floor beams in frame 8, 9 & 10 Fabrication and installation of rebars for 2nd floor slab 5-Apr-12 4 8-Apr-12 Fabrication of forms for 2nd floor slab Inspection 9-Apr-12 1 9-Apr-12 Fabrication and installation of rebars for 2nd floor slab Pouring of concrete for 2nd floor slab 10-Apr-12 1 10-Apr-12 Fabrication & installation of forms for stairs(1st to 2nd floor) 11-Apr-12 Inspection 11-Apr-12 1
Pouring of concrete for 2nd floor slab Fabrication & installation of forms for stairs(1st to 2nd floor)
30-Mar-12
4-Apr-12
9-Ap
pr-12
14-Apr-12
Activity Start Date Duration End Date 9-Jul-12 Scaffolding works for 3rd floor 9-Jul-12 2 10-Jul-12 Fabrication of rebars for for 3rd floor columns 11-Jul-12 works for 3rd13-Jul-12 3 Scaffolding floor Inspection 16-Jul-12 1 16-Jul-12 Fabrication of rebars for for 3rd floor columns Installation of forms for all columns in 3rd floor 17-Jul-12 2 18-Jul-12 Inspection Pouring of concrete for all 3rd flor columns in frame 1 & A 19-Jul-12 4 22-Jul-12 Installation of forms for all columns in 3rd26-Jul-12 floor Pouring of concrete for all 3rd flor columns in frame 11 & F 23-Jul-12 4 3rd flor columns in frame 31-Jul-12 Pouring of concrete for all 3rd flor columns in Pouring2, 3 & 4 frame of concrete for all 27-Jul-12 5 1&A Pouring of concrete for all 3rd flor columns inPouring of concrete for all 3rd flor columns in frame 11 & F frame 5, 6 & 7 1-Aug-12 5 5-Aug-12 Pouring of concrete for all 3rd flor columns in frame 8, 9 & 10 for all 3rd flor columns in frame 2, 3 & 4 6-Aug-12 5 10-Aug-12 Pouring of concrete Fabrication of rebars for 4th floor beams Pouring of concrete for all 3rd flor columns in frame 5, 6 & 7 11-Aug-12 6 16-Aug-12
Pouring of concrete for all 3rd flor columns in frame 8, 9 & 10 Fabrication of rebars for 4th floor beams
14-Jul-12
19-Jul-12
24-Jul-12
29-Jul-12
3-Aug
ug-12
8-Aug-12
Activity Start Date Duration End Date Fabrication & installation of rebars for stairs(1st to 2nd floor) 12-Apr-12 1 12-Apr-12 12-Apr-12 13-Apr-12 Pouring of concrete for stairs(1st to 2nd floor) 13-Apr-12 1 Removing of forms for all columns in ground floor 14-Apr-12 1 14-Apr-12 Fabrication & installation of rebars for stairs(1st to 2nd floor) Delivery of construction materials III 14-Apr-12 1 14-Apr-12 Removing of forms for all 2nd floor beams, floor slabs and stairs(1st to 2nd floor) for stairs(1st to 2nd floor) 15-Apr-12 1 15-Apr-12 Pouring of concrete Scaffolding works for 2nd floor 16-Apr-12 2 17-Apr-12 Removing of forms for all columns in ground floor Fabrication of rebars for 2nd floor columns 15-Apr-12 3 17-Apr-12 Inspection 18-Apr-12 III 1 18-Apr-12 Delivery of construction materials Installation of forms for all 2nd floor columns 19-Apr-12 3 21-Apr-12 Removing of forms for all 2nd floor beams, floor slabs and stairs(1st to 2nd floor) Pouring of concrete for all 2nd floor columns in frame 1 & A 22-Apr-12 4 25-Apr-12
Scaffolding works for 2nd floor Fabrication of rebars for 2nd floor columns Inspection Installation of forms for all 2nd floor columns Pouring of concrete for all 2nd floor columns in frame 1 & A
17-Apr-12
22-Apr-12
27-Apr-12
Activity Start Date Duration End Date Pouring of concrete for all 2nd floor columns in frame 11 & F 26-Apr-12 4 29-Apr-12 26-Apr-12 Pouring of concrete for all 2nd floor columns in frame 2, 3 & 4 30-Apr-12 5 4-May-12 Pouring of concrete for all 2nd floor columns in frame Pouring7 concrete for all 2nd floor columns in frame 11 & F 5, 6 & of 5-May-12 5 9-May-12 Pouring of concrete for all 2nd floor columns in frame 8, 9 & of concrete for all 2nd floor columns in frame 2,14-May-12 10-May-12 5 3&4 Pouring 10 Fabrication of rebars for 3rd floor beams 15-May-12 6 6&7 Pouring of concrete for all 2nd floor columns in frame 5,20-May-12 Installation of rebars & forms for all 3rd floor beams in frame 1 & A 21-May-12 3 23-May-12 Pouring of concrete for all 2nd floor columns in frame 8, 9 & 10 Inspection 24-May-12 1 24-May Fabrication of rebars for 3rd floor beams Pouring of concrete for all 3rd floor beams in frame 1 & A 25-May-12 4 28-May-12 Installation of 11 & & Installation of rebars & forms for all 3rd floor beams in framerebarsF forms for all 3rd floor beams in frame31-May-12 29-May-12 3 1&A Inspection Inspection 1-Jun-12 1 1-Jun-12
Pouring of concrete for all 3rd floor beams in frame 1 & A Installation of rebars & forms for all 3rd floor beams in frame 11 & F Inspection
3-May-12
10-May-12
17-May-12
24-May-12
31-May-12
7-Jun-12
Activity Start Date Duration End Date Pouring of concrete for all 3rd floor beams in frame 11 & F 2-Jun-12 4 5-Jun-12 Installation rebars & forms for all 3rd floor beams in frame 2, 3 & 4 6-Jun-12 4 9-Jun-12 2-Jun-12 Inspection 10-Jun-12 1 10-Jun-12 Pouring of concrete for all 3rd floor beams in frame 11 & F Pouring of concrete for all 3rd floor beams in frame 2, 3 & 4 11-Jun-12 4 14-Jun-12 Installation rebars & forms for all 3rd floor beams in frame 2, 3 & 4 Installation rebars & forms for all 3rd floor beams in frame 5, 6 & 7 15-Jun-12 4 18-Jun-12 Inspection Inspection 19-Jun-12 1 19-Jun-12 Pouring of concrete for all 3rd floor beams in frame 5, 6 & 7 Pouring of concrete for all 3rd floor beams in frame 2, 3 & 4 20-Jun-12 4 23-Jun-12 Installation in 27-Jun-12 Installation of rebars for all 3rd floor beams in frame 8, 9 & 10 rebars & forms for all 3rd floor beams 4 frame 5, 6 & 7 24-Jun-12 Inspection 28-Jun-12 1 28-Jun-12 Inspection Pouring of concrete for all 3rd floor beams in frame 8, 9 & 10Pouring of concrete for all 3rd floor beams in frame 5, 6 & 7 29-Jun-12 4 2-Jul-12
Installation of rebars for all 3rd floor beams in frame 8, 9 & 10 Inspection Pouring of concrete for all 3rd floor beams in frame 8, 9 & 10
7-Jun-12
12-Jun-12 17-Jun-12 22
22-Jun-12 27-Jun-12
2-Jul-12
7-Jul-12
Activity Removing of scaffolding in ground floor Installation of forms for slab in 3rd floor Fabrication & installation of of rebars for slab in 3rd floor Delivery of construction materials IV Inspection Pouring of concrete for 3rd floor slab Installation of forms & rebars for stairs(2nd to 3rd floor) Pouring of concrete for stairs(2nd to 3rd floor) Removing of forms for all columns in 2nd floor Erection of CHB walls in 2nd floor
Start Date Duration End Date 29-Jun-12 2 30-Jun-12 29-Jun-12 1-Jul-12 2 2-Jul-12 3-Jul-12 3 5-Jul-12 Removing of scaffolding in ground floor 3-Jul-12 1 3-Jul-12 Installation of forms for slab in 3rd floor 4-Jul-12 1 4-Jul-12 Fabrication & installation of of rebars for slab in 3rd 5-Jul-12 1 5-Jul-12 6-Jul-12 1 Delivery of construction materials IV 6-Jul-12 Inspection 7-Jul-12 1 7-Jul-12 8-Jul-12 1 Pouring of concrete for 3rd floor slab 8-Jul-12 8-Jul-12Installation8 forms & rebars for stairs(2nd to 3rd of 15-Jul-12
Pouring of concrete for stairs(2nd to 3rd floor) Removing of forms for all columns in 2nd floor Erection of CHB walls in 2nd floor
4-Jul-12
9-Jul-12
14-Jul-12
19-Jul-12
Activity Start Date Duration End Date Installation of rebars & forms for all 4th floor beams in frame 1 & A 17-Aug-12 3 19-Aug-12 17-Aug-12 22-Aug-12 27-Aug-12 Inspection 20-Aug-12 1 20-Aug-12 Pouring of concrete for all 4th floor beams in frame 1 & A of rebars & forms for all 4th floor beams in frame 1 & A 21-Aug-12 4 24-Aug-12 Installation Installation of rebars & forms for all 4th floor beams in frame 11 & F 25-Aug-12 3 27-Aug-12 Inspection Inspection 28-Aug-12 1 28-Aug-12 Pouring of concrete for all 4th floor beams in frame 1 & A Pouring of concrete for all 4th floor beams in frame 11 & F 29-Aug-12 4 1-Sep-12 Installation of rebars & forms for all 4th floor beams in frame 11 & F Installation of rebars & forms for all 4th floor beams in frame 2, 3 & 4 2-Sep-12 4 5-Sep-12 Inspection Inspection 6-Sep-12 1 6-Sep-12 Pouring of concrete for all 4th floor beams in frame10-Sep-12 Pouring of concrete for all 4th floor beams in frame 2, 3 & 4 7-Sep-12 4 11 & F Installation of rebars & forms for all 4th floor beams in frame 5, 6 & 7 11-Sep-12 4 14-Sep-12 Installation of rebars & forms for all 4th floor beams in frame 2, 3 & 4
Inspection Pouring of concrete for all 4th floor beams in frame 2, 3 & 4 Installation of rebars & forms for all 4th floor beams in frame 5, 6 & 7
1-Sep-12
6-Sep
p-12
11-Sep-12
16-Sep-12
21-Sep-12
Activity Start Date Duration End Date Inspection 15-Sep-12 1 15-Sep-12 Pouring of concrete for all 4th floor beams in frame 5, 6 & 7 16-Sep-12 4 19-Sep-12 15-Sep-12 23-Sep-12 20-Sep-12 Installation of rebars & forms for all 4th floor beams in frame 8, 9 & 10 20-Sep-12 4 Inspection 24-Sep-12 1 24-Sep-12 Inspection Pouring of concrete for all 4th floor beams in frame 8, 9 & 10 25-Sep-12 4 28-Sep-12 Pouring of concrete for all Removing of all forms of beams, slab and stairs(2nd to 3rd floor) in 3rd floor 4th floor beams in frame 5, 6 & 7 1 29-Sep-12 29-Sep-12 Installation of rebars & forms for all 4th floor beams 29-Sep-12 9 & 10 in frame 8, Installation of forms for 4th floor slab 2 30-Sep-12 Inspection Fabrication & installation of rebars for 4th floor slab 30-Sep 3 2-Oct-12 Delivery of construction materials V 1 1-Oct-12 Pouring of concrete for all 4th floor beams in1-Oct-12 9 & 10 frame 8, Inspection 2-Oct-12 1 2-Oct-12 Removing of all forms of beams, slab and stairs(2nd to 3rd floor) in 3rd floor
Installation of forms for 4th floor slab Fabrication & installation of rebars for 4th floor slab Delivery of construction materials V Inspection
25-Sep-12
30-Sep-12
5-Oct-12
Activity Start Date Duration End Date Pouring of concrete for 4th floor slab 3-Oct-12 1 3-Oct-12 3-Oct-12 Installation of forms and rebars for stairs(3rd to 4th floor) 4-Oct-12 1 4-Oct-12 Pouring of concrete for 4th floor slab Pouring of concrete for stairs(3rd to 4th floor) 5-Oct-12 1 5-Oct-12 Installation of forms and rebars for stairs(3rd to 4th floor) Removing of scaffoldings in 2nd floor 6-Oct-12 2 7-Oct-12 Erection of CHB walls in 3rd floor Pouring of6-Oct-12 for stairs(3rd to 4th floor) concrete 8 13-Oct-12 Removing of forms for all columns in 3rd floor 8-Oct-12of scaffoldings in 2nd floor 1 8-Oct-12 Removing Scaffolding works for 4th floor 9-Oct-12 of CHB walls10-Oct-12 2 in 3rd floor Erection Fabrication of rebars for 4th floor columns 11-Oct-12 2 12-Oct-12 Removing of forms for all columns in 3rd floor Inspection 14-Oct-12 1 14-Oct-12 Scaffolding works for 4th floor Installation of forms for all columns in 4th floor 15-Oct-12 2 16-Oct-12
Fabrication of rebars for 4th floor columns Inspection Installation of forms for all columns in 4th floor
5-Oct-12
7-Oct-12
9-Oct-12
11-Oct-12 13
13-Oct-12 15-Oct-12
17-Oct-12 19-Oct-12
Activity Start Date Duration Pouring of concrete for all 4th floor columns in frame 1 & A 17-Oct-12 17-Oct-12 4 Pouring of concrete for all 4th floor columns in frame 11 & F 21-Oct-12 4 Pouring of concrete for in frame 1 Pouring of concrete for all 4th floor columns in frame 2, 3 & 4 all 4th floor columns25-Oct-12 & A 5 Pouring of concrete for7all 4th floor columns in frame 11 & F Pouring of concrete for all 4th floor columns in frame 5, 6 & 30-Oct-12 5 Pouring of concrete9 & all 4th floor columns in 4-Nov-12 & 4 for 10 frame 2, 3 Pouring of concrete for all 4th floor columns in frame 8, 5 Pouring of concrete for all 4th floor columns in 9-Nov-12 & 7 frame 5, 6 Fabrication of rebars for 5th floor beams 6 Pouring of concreteframe 4th floor columns in 15-Nov-12& 10 for all 1 & A frame 8, 9 Installation of rebars & forms for all 5th floor beams in 3 Fabrication of rebars for 5th floor beams Inspection 18-Nov-12 1 Installation of rebars & forms Pouring of concrete for all 5th floor beams in frame 1 & A for all 5th floor beams in frame 1 & A 19-Nov-12 4 Inspection Installation of rebars & forms for all 5th floor beams in frame 11 & F 23-Nov-12 3 Pouring of concrete for all 5th floor beams in frame 1 & A Inspection 26-Nov-12 1
Installation of rebars & forms for all 5th floor beams in frame 11 & F Inspection
End Date 20-Oct-12 24-Oct-12 31-Oct-12 24-Oct-12 29-Oct-12 3-Nov-12 8-Nov-12 14-Nov-12 17-Nov-12 18-Nov-12 22-Nov-12 25-Nov-12 26-Nov-12
7-Nov-12
14-Nov-12
21-Nov-1
-12
28-Nov-12
5-Dec-12
Activity Start Date Duration End Date Pouring of concrete for all 5th floor beams in frame 11 & F 27-Nov-12 4 30-Nov-12 27-Nov-12 Installation of rebars & forms for all 5th floor beams in frame 2, 3 & 4 1-Dec-12 4 4-Dec-12 Pouring Inspection 5-Dec-12 of concrete for all 5th floor beams in frame 11 & F 1 5-Dec-12 Installation of rebars & forms 4 all 5th floor beams in frame 2, 3 & 4 for 9-Dec-12 Pouring of concrete for all 5th floor beams in frame 2, 3 & 4 6-Dec-12 Inspection Installation of rebars & forms for all 5th floor beams in frame 5, 6 & 7 10-Dec-12 4 13-Dec-12 Pouring of for 14-Dec-12 Inspection 14-Dec-12 concrete 1 all 5th floor beams in frame 2, 3 & 4 Installation of rebars & forms 4 all 5th floor beams in frame 5, 6 & 7 for 18-Dec-12 Pouring of concrete for all 5th floor beams in frame 5, 6 & 7 15-Dec-12 Inspection Installation of rebars & forms for all 5th floor beams in frame 8, 9 & 10 19-Dec-12 4 22-Dec-12 Inspection 23-Dec-12 concrete 1 all 5th floor beams in frame 5, 6 & 7 Pouring of for 23-Dec-12 Pouring of concrete for all 5th floor beams in frame 8, 9 & 10 24-Dec-12 4 27-Dec-12 Installation of rebars & forms for all 5th floor beams in frame 8, 9 & 10 Removing of all forms of beams, slabs and stairs(3rd to 4th floor) 28-Dec-12 1 28-Dec-12 Inspection
Pouring of concrete for all 5th floor beams in frame 8, 9 & 10 Removing of all forms of beams, slabs and stairs(3rd to 4th floor)
2-Dec-12
7-D
Dec-12
1-Jan-13
Activity Start Date Duration End Date Installation of forms for 5th floor slab 28-Dec-12 2 29-Dec-12 28-Dec-12 Fabrication & installation of rebars for 5th floor slab 29-Dec-12 3 31-Dec-12 Delivery of construction materials VI 29-Dec-12 Installation of 30-Dec-12 floor slab 1 forms for 5th Fabrication & installation1 rebars for 5th floor slab of 2-Jan-13 Inspection 2-Jan-13 Pouring of concrete for 5th floor slab 3-Jan-13 Delivery of construction materials VI 1 3-Jan-13 Installation of forms for & rebars for stairs(4th to 5th floor) 4-Jan-13 1 4-Jan-13 Inspection Pouring of concrete for stairs(4th to 5th floor) 5-Jan-13 Pouring of1 5-Jan-13 floor slab concrete for 5th Removing of scaffolding in 3rd floor 6-Jan-13for & rebars for stairs(4th to 5th floor) 2 7-Jan-13 Installation of forms Erection of CHB walls in 4th floor 6-Jan-13 of concrete for13-Jan-13to 5th floor) 8 stairs(4th Pouring Removing of all forms of columns in 4th floor 8-Jan-13 1 8-Jan-13 Removing of scaffolding in 3rd floor Scaffolding for 5th floor 9-Jan-13 2 10-Jan-13
Erection of CHB walls in 4th floor Removing of all forms of columns in 4th floor Scaffolding for 5th floor
2-Jan-13
7-J
-Jan-13
12-Jan-13
17-Jan-13
Activity Start Date Duration End Date Fabrication & installation of rebars & forms for 5th floor columns 11-Jan-13 3 13-Jan-13 Inspection 14-Jan-13 1 11-Jan-13 14-Jan-13 18-Jan-13 Pouring of concrete for all 5th floor columns in frame 1 & A 15-Jan-13 4 18-Jan-13 Fabrication & installation of rebars & forms for 5th floor columns Pouring of concrete for all 5th floor columns in frame 11 & F 19-Jan-13 4 22-Jan-13 Inspection Pouring of concrete for all 5th floor columns in frame 2, 3 & 4 23-Jan-13 5 27-Jan-13 Pouring & 7 Pouring of concrete for all 5th floor columns in frame 5, 6 of concrete for all 5th floor columns in frame 15& A 1-Feb-13 28-Jan-13 Pouring of 10 Pouring of concrete for all 5th floor columns in frame 8, 9 &concrete for all 5th floor columns in frame 11 & F 6-Feb-13 2-Feb 5 Fabrication of rebars for roof all roof deck beams in frame concrete for all 5th floor columns in frame 2, 36& 4 7-Feb-13 12-Feb-13 Pouring of 1 & A Inspection 13-Feb-13 13-Feb-13 Pouring of concrete for all 5th floor columns in frame 5, 61& 7 Pouring of concrete for all roof deck beams in frame 1 & A 14-Feb-13 4 17-Feb-13 Pouring of concrete for all 5th floor columns in frame 8, 9 & 10 Installation of rebars and forms for all roof deck beams in frame 11 & F all roof deck beams in frame 13& A 18-Feb-13 20-Feb-13 Fabrication of rebars for roof
Inspection Pouring of concrete for all roof deck beams in frame 1 & A Installation of rebars and forms for all roof deck beams in frame 11 & F
25-Jan-13
1-Feb-13
8-Feb
eb-13
15-Feb-13
22-Feb-13
1-Mar-13