Revision History
Date 2009-923 2009-1116 2010-7-1 2011-520 Revision Version V1.0 Description Initial version Add the introduction to the survey of Yshaped clock signal cable, TNU cable and network cables in the scenario of establish a new RNC and capacity expansion. Explain the survey requirement of the window of the feeder. Add the introduction to the survey of optical Splitter and SCUb interconnection cables. Author Xu Lanxiang, Gao Peng Gao Peng
V1.1
V1.2 V1.3
2012-2-16
Internal
Table of Contents
Chapter 1 Product Description................................................................................................1 1.1 Application Version........................................................................................................1 1.2 Product Overview..........................................................................................................1 1.3 Product structure Introduction.......................................................................................2 1.3.1 Cabinet................................................................................................................2 1.3.2 Subrack...............................................................................................................6 1.3.3 Boards.................................................................................................................7 1.4 Configurations..............................................................................................................11 1.4.1 Overview............................................................................................................11 1.4.2 Hardware Configuration Specifications in BM/TC Combined Mode.................12 1.4.3 Hardware Configuration Specifications in BM/TC Separated Mode.................13 1.4.4 Hardware Configuration Specifications in A over IP Mode................................14 Chapter 2 Survey Procedure.................................................................................................16 2.1 Survey Preparation......................................................................................................16 2.1.1 Getting Engineering Information.......................................................................16 2.1.2 Preparing Documents.......................................................................................16 2.1.3 Preparing Tools and Instruments......................................................................16 2.2 Survey Coordination Meeting......................................................................................16 2.3 Principles of Site Survey.............................................................................................17 2.4 Installation Environment Check...................................................................................17 2.5 Filling Out Survey Report............................................................................................17 2.6 Reviewing Survey Report............................................................................................17 2.7 Filing Documents.........................................................................................................17 Chapter 3 Filling Out Survey Report.....................................................................................19 3.1 Cover...........................................................................................................................19 3.2 Common Office Information........................................................................................19 3.2.1 Global Project Catalog......................................................................................19 3.2.2 Cabinet Layout..................................................................................................20 3.2.3 Survey of Common Materials............................................................................21 3.3 BSC6900 Survey.........................................................................................................21 3.3.1 Equipment Room Environment Survey.............................................................21 3.3.2 Power Distribution Cable Survey......................................................................23 3.3.3 LSZH Cables Requirement...............................................................................23 3.3.4 Trunk Cable Survey...........................................................................................24 3.3.5 Description of the Straight-Through Cables on the Ater Interface....................26 3.3.6 Optical Fiber Survey..........................................................................................27 3.3.7 Optical Splitter Survey.......................................................................................29 3.3.8 Network Cable Survey......................................................................................32 3.3.9 SFP+ High-Speed Cables Survey.....................................................................34 3.3.10 Corrugated PVC Tube/PVC Trough Survey....................................................36 3.3.11 Surveying Inter-TNU Cables...........................................................................36 3.3.12 Clock Cable Survey.........................................................................................41 3.3.13 GPS Antenna Feeder Survey..........................................................................44 3.3.14 Alarm Box Cable Survey.................................................................................45 3.3.15 Survey of LMT.................................................................................................46 3.4 Appendix 1 Site Survey Memo (Optional)...................................................................47 3.5 Appendix 2 Installation Environment Checklist...........................................................47 3.6 Appendix 3 Equipment Room Picture (Optional).........................................................48 Chapter 4 Reference...............................................................................................................49 Reference
2012-2-16 Huawei Technologies Proprietary
Internal
List of Figures
Figure 1-1 Position of the BSC6900 GU in the network...........................................................1 Figure 1-2 BSC6900 GU..........................................................................................................2 Figure 1-3 Cabinet layout requirements...................................................................................3 Figure 1-4 Components of the cabinet.....................................................................................4 Figure 1-5 Structure of the subrack..........................................................................................7 Figure 1-6 Structure of the subrack..........................................................................................7 Figure 3-1 Cabinet layout requirements.................................................................................20 Figure 3-2 Height of antistatic floor........................................................................................22 Figure 3-3 Position of installing rack......................................................................................22 Figure 3-4 48V power cable/GND cable of BSC..................................................................23 Figure 3-5 Outline of E1 75 coaxial cable............................................................................24 Figure 3-6 Outline of E1 75 coaxial cable (Y-Shaped).........................................................24 Figure 3-7 Outline of E1 120 twisted pair cable...................................................................25 Figure 3-8 Outline of E1 120 twisted pair cable (Y-Shaped)................................................25 Figure 3-9 Calculating required trunk cable length for overhead cabling...............................26 Figure 3-10 Calculating required trunk cable length for underfloor cabling............................26 Figure 3-11 Straight-through cables on the Ater interface (upward cabling)...........................27 Figure 3-12 Straight-through cables on the Ater interface (downward cabling)......................27 Figure 3-13 Outline of LC/PC-LC/PC-single-mode/multi-mode optical fiber...........................28 Figure 3-14 Figure 4-10 Outline of LC/PC-FC/PC-single-mode/multi-mode optical fiber.......28 Figure 3-15 Outline of LC/PC-SC/PC-single-mode optical fiber.............................................28 Figure 3-16 Optical Splitter....................................................................................................29 Figure 3-17 Operating principle for an optical combiner.........................................................30 Figure 3-18 Operating principle for an optical splitter.............................................................30 Figure 3-19 Position for installing an optical splitter...............................................................31 Figure 3-20 Position for installing optical fibers for an optical splitter.....................................31 Figure 3-21 Outline of shielded network cable.......................................................................32 Figure 3-22 Outline of unshielded network cable...................................................................32 Figure 3-23 Connecting SCUa boards in MPS and those in an EPS through crossover Ethernet cables...............................................................................................................33 Figure 3-24 Position of crossover Ethernet cables between SCUa boards in BSC6900........34 Figure 3-25 Position of SFP+ high-speed cables between SCUb boards in BSC6900..........35 Figure 3-26 Position of SFP+ high-speed cables between SCUb boards in multi cabinets....36 Figure 3-27 Appearance of Inter-TNU Cables........................................................................37 Figure 3-28 Installation position of the Inter-TNU Cables.......................................................38 Figure 3-29 Inter-TNU Cables of 2.2 m..................................................................................39 Figure 3-30 Inter-TNU Cables of 2.7 m..................................................................................39 Figure 3-31 Inter-TNU Cables of 9.7 m..................................................................................40 Figure 3-32 Outline of a Y-shaped clock cable.......................................................................42 Figure 3-33 Connecting GCUa/GCGa boards in MPS and SCUa boards in an EPS through Yshaped clock cables........................................................................................................42
2012-2-16 Huawei Technologies Proprietary
Internal
Figure 3-34 Lengths of Y-shaped clock cables.......................................................................43 Figure 3-35 Installing 7/8" or 5/4" feeder................................................................................44 Figure 3-36 Installing 1/2" feeder...........................................................................................45 Figure 3-37 Outline of alarm signal cable...............................................................................45
2012-2-16
Internal
List of Tables
Table 1-1 Components of the cabinet.......................................................................................5 Table 1-2 Technical specifications of the BSC6900 cabinet (N68E-22)....................................5 Table 1-3 Classification of BSC6900 GU subracks...................................................................6 Table 1-4 Classification of BSC6900 GU boards......................................................................7 Table 1-5 Configuration modes of the BSC6900 GU..............................................................11 Table 1-6 Typical configuration specifications of a single BSC6900 GU subrack (1)..............12 Table 1-7 Typical configuration specifications of a single BSC6900 GU subrack (2)..............12 Table 1-8 Typical configuration specifications of a single BSC6900 GU subrack (3)..............13 Table 1-9 Typical configuration specifications of a single BSC6900 GU subrack (4)..............13 Table 1-10 Typical configuration specifications of a single BSC6900 GU subrack (5)............14 Table 1-11 Typical configuration specifications of a single BSC6900 GU subrack (6)............14 Table 3-1 Items in global project catalog................................................................................19 Table 3-2 The optical power and the receive sensitivity of the optical module in the BSC......30 Table 3-3 Quantity of TNU cables between the MPS subrack and the EPS subrack..............40 Table 3-4 Quantity of TNU cables between the TC subracks.................................................41 Table 3-5 Quantity of Y-shaped clock cables..........................................................................43 Table 3-6 Available types of feeders.......................................................................................44
2012-2-16
Internal
2012-2-16
Internal
CS core network
NodeB Abis
PS core network
UE
Uu/Um
Figure 1.1Position of the BSC6900 GU in the network The interfaces between the BSC6900 GU and each NE in the UMTS network are as follows: Iub: the interface between the BSC6900 GU and the NodeB Iur: the interface between the BSC6900 GU and the RNC Iu-CS: the interface between the BSC6900 GU and the Mobile Switching Center (MSC) or Media Gateway (MGW) Iu-PS: the interface between the BSC6900 GU and the Serving GPRS Support Node (SGSN)
2012-2-16 Huawei Technologies Proprietary 1
Internal
Iu-BC: the interface between the BSC6900 GU and the Cell Broadcast Center (CBC) These interfaces are standard interfaces, through which equipment from different vendors can be interconnected. The interfaces between the BSC6900 GU and each NE in the GSM network are as follows: Abis: the interface between the BSC6900 GU and the BTS A: the interface between the BSC6900 GU and the Mobile Switching Center (MSC) or Media Gateway (MGW) Gb: the interface between the BSC6900 GU and the Serving GPRS Support Node (SGSN) The A and Gb interfaces are standard interfaces, through which the equipment from different vendors can be interconnected. The BSC6900 GU performs functions such as radio resource management, base station management, power control, and handover control.
Figure 1.1BSC6900 GU Reasonably determine the specific positions of cabinets through full consultation with the customer. The front and rear of the cabinets should be no less than 0.8 m away from a wall or other equipment. There should be a no less than 1m wide aisle in the equipment room. Furthermore, a certain area should be reserved as needed for future expansion. See Figure 1-3.
2012-2-16
Internal
Figure 1.2Cabinet layout requirements Based on functions, cabinets are classified into the main processing rack (MPR), extended processing rack (EPR), and transcoder rack (TCR). MPR: Main Process Rack, only one MPR is configured in the BSC6900. EPR: Extent Process Rack, the number of EPRs to be configured depends on the traffic volume, but only one EPR can be configured in the BSC6900. You can also choose not to configure the EPR. TCR: TransCoder Rack, the number of TCRs to be configured depends on the traffic volume and the configuration modes of subracks. Up to two TCRs can be configured in the BSC6900. You can also choose not to configure a TCR. The components of the BSC6900 cabinet that with internal power distribution (PARC) are the power distribution box, subrack, air defence subrack, independent fan subrack, cable rack, rack, and rear cable trough. Figure 1-4 shows the components of the BSC6900 cabinet.
2012-2-16
Internal
(1) Air inlet (4) Air defence subrack (7) Cable rack
(2) Independent fan subrack (5) Filler panel (8) Rear cable trough
Internal
The subracks are numbered from bottom to top, and the MPS is numbered 0.
Table 1-2 describes the technical specifications of the BSC6900 cabinet (N68E-22).
-48 V
-40 V to -57 V Meets the requirements in ETSI EN300 386 Meets the requirements in Council directive 89/336/EEC
1.1.1 Subrack
Subracks are used to house boards and backplanes to form an independent unit.
The BSC6900 GU subracks are classified into main processing subrack (MPS), extended processing subrack (EPS), and transcoder subrack (TCS), as described in Classification of BSC6900 GU subracks.
2012-2-16 Huawei Technologies Proprietary 1
Internal
EPS TCS
In compliance with the IEC60297 standard, each subrack is 19 inches in width and 12 U in height. Figure 1 shows the structure of the subrack.
power (8) Port for the monitoring signal cable of the (9) Cover plate of the DIP power distribution box switch
2012-2-16
Internal
(2) Backplane
1.1.2 Boards
The BSC6900 GU boards can be classified into the OM board, switching processing board, clock processing board, signaling processing board, service processing board, and interface processing board, as described in Table 1-5. The BSC6900 V900R011 is added with the following new boards: SPUb, XPUb, DPUe, AOUc, FG2c, GOUc, POUc, and UOIc. Other boards are inherited from the BSC6000 R8 and BSC6810 V200R011, and they can be used directly after the BSC6000 or BSC6810 is upgraded to the BSC6900 GU. Table 1.1Classification of BSC6900 GU boards Board Type OM board Board Name OMUa Function Performs configuration management, performance management, fault management, security management, and loading management for the BSC6900. Works as the OM bridge of the LMT/M2000 to provide the BSC6900 OM interface for the LMT/M2000 and to enable the communication between the BSC6900 and the LMT/M2000. Works as the interface to provide the web-based online help.
Application Variant The OMUa board is applicable to the BSC6900 GSM, BSC6900 GU, and BSC6900 UMTS.
2012-2-16
Internal
OMUc
The OMUc board works as a bridge for the communication between the Local Maintenance Terminal (LMT) and the other boards in the BSC6900. Provides MAC/GE switching and enables the convergence of ATM and IP networks. Provides data switching channels. Provides system-level or subrack-level configuration and maintenance. Distributes clock signals for the BSC6900.
The OMUa board is applicable to the BSC6900 GSM, BSC6900 GU, and BSC6900 UMTS. The SCUa board is applicable to the BSC6900 GSM, BSC6900 GU, and BSC6900 UMTS. The SCUb board is applicable to the BSC6900 GSM, BSC6900 GU, and BSC6900 UMTS.
SCUa
SCUb
TNUa
GCUa
Provides the maintenance management function Provides configuration and maintenance of a subrack or of the entire BSC6900 Monitors the power supply, fans, and environment of the cabinet Supports the port trunking function Supports the active/standby switchover Enables inter-subrack connections Provides a total switching capacity of 240 Gbit/s Distributes clock signals and RFN signals for the BSC6900 Provides the TDM switching and serves as the center of the circuit switched domain. Assigns the resources of the TDM network and establishes the network connection. Provides the communication processing on the GE port. Obtains the system clock source, performs the functions of phase-lock and holdover, and provides clock signals. Obtains the system clock source, performs the functions of phase-lock and holdover, and provides clock signals. Receives and processes the GPS signals. Manages user plane and signaling plane resources in the subrack and processes signaling. Differences: The SPUa board processes the signaling on the GSM/UMTS signaling plane. The XPUa board processes the signaling on the GSM signaling plane.
The TNUb board is applicable to the BSC6900 GSM and the BSC6900 GU.
GCGa
SPUa
XPUa
The GCUa board is applicable to the BSC6900 GSM, BSC6900 GU, and BSC6900 UMTS. The GCGa board is applicable to the BSC6900 UMTS and BSC6900 GU. The SPUa board is applicable to the BSC6900 GSM, BSC6900 UMTS and BSC6900 GU. The XPUa board is applicable to the BSC6900 GSM and BSC6900 GU.
2012-2-16
Internal
SPUb
XPUb
DPUb
Manages user plane and signaling plane resources in the subrack and processes signaling. Differences: The SPUb board processes the signaling on the GSM/UMTS signaling plane. The processing capability of the SPUb board is 75% to 100% higher than that of the SPUa board. The XPUb board processes the signaling on the GSM signaling plane. The processing capability of the XPUb board is 75% to 100% higher than that of the XPUa board. Processes CS services and PS services within the system. Differences: The DPUb board processes the services on the UMTS user plane, encodes and decodes the GSM speech services and data services, and converts the speech frame format over the IP speech channel and the speech channel in HDLC transmission optimization. The DPUa board processes GSM voice services and GSM data services. The DPUc board encodes and decodes the GSM speech services and converts the speech frame format over the IP speech channel and the speech channel in HDLC transmission optimization. The DPUd board processes the GSM data services. Processes CS services and PS services within the system. The DPUe board processes the services on the UMTS user plane. The DPUf board processes GSM voice services and GSM data services. The DPUg board processes GSM PS services.
The SPUb board is applicable to the BSC6900 GSM, BSC6900 GU, and BSC6900 UMTS. The XPUb board is applicable to the BSC6900 GSM and BSC6900 GU. The DPUb board is applicable to the BSC6900 GSM, BSC6900 GU, and BSC6900 UMTS.
DPUa
DPUc
DPUd
DPUe
DPUf
DPUg
AEUa
Provides 32 channels of ATM over E1s/T1. Extracts the clock signals and sends the signals to the GCUa or GCGa board.
The DPUa board is applicable to the BSC6900 GSM and BSC6900 GU. The DPUc board is applicable to the BSC6900 GSM and BSC6900 GU. The DPUd board is applicable to the BSC6900 GSM and BSC6900 GU. The DPUe board is applicable to the BSC6900 UMTS and BSC6900 GU. The DPUf board is applicable to the BSC6900 GSM and BSC6900 GU. The DPUf board is applicable to the BSC6900 GSM and BSC6900 GU. The AEUa board is applicable to the BSC6900 UMTS and BSC6900 GU.
2012-2-16
Internal
AOUa
Provides two channels over the channelized optical STM-1/OC-3 ports based on ATM protocols. Supports ATM over E1/T1 over SDH or SONET. Provides 126 E1s or 168 T1s. Extracts the clock signals and sends the signals to the GCUa or GCGa board.
The AOUa board is applicable to the BSC6900 UMTS and BSC6900 GU.
EIUa
Provides 32 channels over E1/T1 electrical ports. Transmits, receives, encodes, and decodes the 32 E1s/T1s. The E1 transmission rate is 2.048 Mbit/s; the T1 transmission rate is 1.544 Mbit/s.
The EIUa board is applicable to the BSC6900 GSM and BSC6900 GU. The FG2a board is applicable to the BSC6900 GSM, BSC6900 GU, and BSC6900 UMTS. The GOUa board is applicable to the BSC6900 GSM, BSC6900 GU and BSC6900 UMTS. The OIUa board is applicable to the BSC6900 GSM and BSC6900 GU. The PEUa board is applicable to the BSC6900 GSM, BSC6900 GU, and BSC6900 UMTS. The POUa board is applicable to the BSC6900 UMTS and BSC6900 GU.
FG2a
Provides eight channels over FE electrical ports or two channels over GE electrical ports. Supports IP over FE/GE.
GOUa
OIUa
Provides one channel over the STM-1 optical port. Provides one channelized STM-1 with the rate of 155.52 Mbit/s.
PEUa
Provides 32 channels of IP over E1s/T1. Extracts the clock signals and sends the signals to the GCUa or GCGa board.
POUa
UOIa
Provides two channels over the channelized optical STM-1/OC-3 ports based on IP protocols. Supports IP over E1/T1 over SDH/SONET. Provides the load bearer capability of 126 E1s or 168 T1s. Extracts the clock signals and sends the signals to the GCUa or GCGa board. Provides four channels over the unchannelized STM-1/OC-3c optical ports. Supports ATM/IP over SDH/SONET.
Extracts the clock signals and sends the signals to the GCUa or GCGa board.
The UOIa board is applicable to the BSC6900 UMTS and BSC6900 GU.
2012-2-16
Internal
AOUc
Provides four channels over the channelized optical STM-1/OC-3 ports based on ATM protocols. Supports ATM over E1/T1 over SDH or SONET. Provides 252 E1s or 336 T1s. Extracts the clock signals and sends the signals to the GCUa or GCGa board.
The AOUc board is applicable to the BSC6900 UMTS and BSC6900 GU.
FG2c
Provides 12 channels over FE electrical ports or 4 channels over GE electrical ports. Supports IP over FE/GE.
GOUc
POUc
Provides four channels over the channelized optical STM-1/OC-3 ports based on IP/TDM protocols. Supports IP over E1/T1 over SDH/SONET. Provides the load bearer capability of 252 E1s or 336 T1s. Extracts the clock signals and sends the signals to the GCUa or GCGa board.
The FG2ac board is applicable to the BSC6900 GSM, BSC6900 GU, and BSC6900 UMTS. The GOUc board is applicable to the BSC6900 GSM, BSC6900 GU, and BSC6900 UMTS. The POUc board is applicable to the BSC6900 GSM, BSC6900 GU, and BSC6900 UMTS.
UOIc
Provides eight channels over the unchannelized STM-1/OC-3c optical ports. Supports IP over SDH/SONET. Extracts the clock signals and sends the signals to the GCUa or GCGa board.
1.1 Configurations
1.1.1 Overview
In the BSC6900 GU, the MPS or EPS can be either a GSM subrack or a UMTS subrack. Based on the TCS configuration, the BSC6900 GU supports three types of configuration modes: BM/TC combined, BM/TC separated, and A over IP. The system specifications vary according to the boards configured in the BSC6900 GU. The MPS and EPS are generally called basic module (BM), and the TCS is called transcoder (TC) for short. Configuration modes of the BSC6900 GU6 describes the configuration modes of the BSC6900 GU based on the TCS configuration. Table 1.1Configuration modes of the BSC6900 GU
Configuratio n Mode BM/TC combined Description The BSC is not configured with the TCS. The boards that implement the TC functions are inserted into the slots in the MPS or EPS. This mode is applicable to the scenario Huawei Technologies Proprietary Characteristic With the same capacity, less cabinets and less subracks are required in the BSC, thus increasing the hardware integration. The TCS can be 1
BM/TC 2012-2-16
BSC6900 Site Survey Design Guide Configuratio n Mode separated Description where the BSC is configured in a remote equipment room. In this mode, the BSC is configured with a separate TCS, which is placed in the TCR on the MSC side. The BSC6900 GU is not configured with a TCS. The TC functions are implemented by the MGW. Characteristic
Internal
A over IP
configured in the TCR on the MSC side, thus saving the transmission resources between the BSC and the MSC. The BSC is directly connected to the Huawei core network without a TC, thus reducing the CAPEX of the operator. In addition, the number of speech coding and decoding times is decreased to improve the speech quality. The A over IP mode meets the needs for network evolution.
4,875
NA
200 600 NA NA
300 900 NA NA
NA
NOTE The traffic volume is calculated on the basis of Huawei traffic model. The N/A in the table indicates that the data is not available at present. You can calculate the capacity specifications in any typical subrack combination mode by using the preceding data.
Typical configuration specifications of a single BSC6900 GU subrack (2)8 lists the typical configuration specifications of a single subrack when the BSC6900 GU in BM/TC combined mode is configured with the BSC6900R11 boards.
2012-2-16
Internal
6,500
NA NA
NOTE The traffic volume is calculated on the basis of Huawei traffic model. The N/A in the table indicates that the data is not available at present. You can calculate the capacity specifications in any typical subrack combination mode by using the preceding data.
4,875
NA NA
NOTE The traffic volume is calculated on the basis of Huawei traffic model. The N/A in the table indicates that the data is not available at present. You can calculate the capacity specifications in any typical subrack combination mode by using the preceding data.
Typical configuration specifications of a single BSC6900 GU subrack (4)10 lists the typical configuration specifications of a single subrack when the BSC6900 GU in BM/TC separated mode is configured with the BSC6900R11 boards. Table 1.2Typical configuration specifications of a single BSC6900 GU subrack (4)
Subrack Traffic volume (Erl) 2012-2-16 MPS(UMTS) 13,400 EPS(UMTS) 13,400 MPS(GSM) 6,500 EPS(GSM)
6,500
1
Internal EPS(GSM)
PS (UL + DL) data throughput (Mbit/s) Number of NodeBs Number of cells Number of TRXs Number of active PDCHs (MCS-9)
NA NA
NOTE The traffic volume is calculated on the basis of Huawei traffic model. The N/A in the table indicates that the data is not available at present. You can calculate the capacity specifications in any typical subrack combination mode by using the preceding data.
4,875
NA NA
NOTE The traffic volume is calculated on the basis of Huawei traffic model. The N/A in the table indicates that the data is not available at present. You can calculate the capacity specifications in any typical subrack combination mode by using the preceding data.
Typical configuration specifications of a single BSC6900 GU subrack (6)2 lists the typical configuration specifications of a single subrack when the BSC6900 GU in A over IP mode is configured with the R11 boards. Table 1.2Typical configuration specifications of a single BSC6900 GU subrack (6)
Subrack Traffic volume (Erl) PS (UL + DL) data 2012-2-16 MPS(UMTS) 13,400 1,340 EPS(UMTS) 13,400 1,340 MPS(GSM) 6,500 NA EPS(GSM)
13,000
NA 1
BSC6900 Site Survey Design Guide Subrack throughput (Mbit/s) Number of NodeBs Number of cells Number of TRXs Number of active PDCHs (MCS-9) MPS(UMTS) 360 1,200 NA NA EPS(UMTS) 540 1,200 NA NA MPS(GSM) NA 1,024 1,024 4,096
Internal EPS(GSM) NA
NOTE The traffic volume is calculated on the basis of Huawei traffic model. The N/A in the table indicates that the data is not available at present. You can calculate the capacity specifications in any typical subrack combination mode by using the preceding data.
2012-2-16
Internal
Internal
name of the equipment room and the traffic route to the equipment room with the opposite side. If possible, determine the exact survey time, get an authorization of access to the equipment room, and learn the customer's some other special survey requirements. The form of the coordination meeting varies from project to project. For a general project or if the customer is at a lower level, a small talk is enough. For a vital complicated project or if the customer is at a higher level, a technical conference or a meeting in other kinds is required.
2012-2-16
Internal
2.1 Cover
Fill in the contract business information, the survey report information, the customer information, and the survey party information. Ask the customer's contact person to confirm the customer information in the form of signature. 1) The contract business information includes the customer name, contract No., quotation No., and site name. 2) The survey report information includes the total number of pages in the survey report, the number of pages in the text, and the number of pages in the appendix. For survey and delivery reference, add the names of the offices that feature the same survey items. 3) The customer information includes the name, telephone, fax and email of the contact person on behalf of the customer, the name, detailed address and telephone of the equipment room, and the contact person's signature. 4) The survey party information includes the name, telephone and fax of the representative office, the name, telephone and email of the contact person on behalf of the representative office, the survey date, and the contact person's signature. Caution: The name, telephone, fax and email of the contact person on either side are mandatory in the electronic copy of the survey report to return to Huawei HQ. The person in charge of survey design or the product manager in the local office serves as the contact person on Huawei's side.
2012-2-16
BSC6900 Site Survey Design Guide Office name Equipment type Quantity Project type Original configuration capacity New configuration capacity Survey phase
Internal
anti-seismic Cabinet. Name of the office to host the equipment. If the office contains multiple equipment rooms, enter the name of each individual equipment room separately. Name and type of the equipment, such as BSC6900. Quantity of each type of equipment. If there are different types of equipment in an equipment room, enter the quantity of each individual type of equipment separately. Including three options: new, expansion, and relocation Original subrack quantity and trunk capacity (including E1 port quantity and optical port quantity) before expansion New subrack quantity and trunk capacity (including E1 port quantity and optical port quantity) Including four options: current, next, previous, and --, which respectively indicate that the item is surveyed in this round, is to be surveyed in the next round, has been surveyed in the previous round, and does not need to be surveyed
Figure 1.1Cabinet layout requirements If there is so large a quantity of equipment that you need to assign it to different rooms, give full consideration to the original cabling and prevent any conflict
2012-2-16
Internal
between the AC and DC power cables. With an eye on future expansion, assign the power supply cabinet as near as possible to the AC unit. List any condition that has impact on later installation in the remarks area. Clearly elaborate any matter not covered here as needed. Warning:
Select the type of the cabinet to deliver first. Identify the new equipment in bold type and the original in italic type. Leave an empty cell between the cabinets that are not closely adjacent to each other and make a remark on the non-adjacency.
2012-2-16
Internal
Caution: If the equipment room is being decorated, get all details of the floor design and arrangement to prevent delivery error. In the case of installation on an antistatic floor, measure the height of the antistatic floor. That is, indicate the vertical distance between the ground and the upper surface of the antistatic floor. Be sure to measure in person the height at the point where to install the rack. If underfloor cabling is applied, check whether there is any cable or hole adverse to the installation below the cabinet position.
Figure 1.1Height of antistatic floor In the case of installation on a cement ground, ensure that the bearing capacity of the ground is enough. An BSC cabinet requires the ground to possess a bearing capacity of no less than 450 kg/m2. In the case of installation on the other unconventional floors, select Others from the Installation Mode list and make a comment in the remarks area. II Cabling Mode Two modes are available for cabling, overhead cabling and underfloor cabling. Which mode to choose is up to the customer. If it is decided to route the trunk cables, clock cables, power busbars and Ethernet cables in different modes, indicate the cabling mode of the trunk cables here. Show the cabling modes of the other cables separately in the cabling diagram. In the case of overhead cabling, measure the height of the cabling rack. That is, indicate the vertical distance between the ground/floor and the cabling rack. Make sure that there is enough vertical space to erect the cabinet (N68E-22 is 2.2 m high).
Indicates only the vertical distance between the cabinet top and the cabling rack. Cabling rack height = h + cabinet height
Figure 1.1Position of installing rack III Net Height of the Equipment Room The net height of the equipment room refers to the vertical distance between the ground/floor and the beam bottom. Make sure that it is sufficient to erect the cabinet. IV Side Door Quantity Consult the list of contracts or those concerned to determine how many cabinets to install. If a PDF is involved, check whether the PDF is of the same type as a BSC cabinet because this impacts the number of required side panels.
2012-2-16 Huawei Technologies Proprietary 5
Internal
Determine the side door quantity on the principle that each row of cabinets needs 2 side doors. If it is decided to combine several cabinets of the same type in a row, no side door is required between the cabinets. For example, a single cabinet needs 2 side doors. Two separate cabinets of the same type require 4 side doors. Two combined cabinets demand 2 side doors. In the case of expansion, determine the quantity of the side doors as needed.
2. OT terminal
Figure 1.148V power cable/GND cable of BSC A power distribution cable is available normally with two core diameters: 25 mm2 and 35 mm2. Calculate the required cross-sectional area of the power distribution cable using the following formula: S=I L / (K U) Wherein, I: Total current (A) in the conductor. It is normally 55 A for the BSC6900. L: Total length (m) of the conductor loop (distance x 2) U: Voltage drop (V) in the conductor. It is normally 2.6 V unless otherwise specified. K: Electrical conductivity (K-copper = 57, K-aluminum = 34) Work out the required core diameter. If S exceeds 25 mm2, select 35mm2 power distribution cables. The calculation shows that the required core diameter varies with the length of the conductor loop between the PDF and the PDB of a cabinet. The 25mm2 cables apply when the length of the conductor loop is less than 65 m. The 35mm2 cables apply when the length of the conductor loop is greater than 65 m and less than 95m. If the length of the conductor loop is greater than 95m, the PDF should be installed near the BSC (satisfied the length of the conductor loop is less than 95m). If there is no PDF in the contract, the contract changing process must be considered. Specify any special requirement for a special power distribution cable color other than the default colors like blue, black and green-and-yellow in the remarks area.
Internal
In surveying process, adopting the LSZH cables affects the quantity of cables of inter-SCU cables, inter-TNU cables, Y-shaped clock cables.
2. Main label (identifying cable code, version, and vendor information) 4. Shell (metal shell of the DB44 connector)
Figure 1.1Outline of E1 75 coaxial cable The purpose of a 75 coaxial cable is to transfer E1 trunk signals between an AEUa/PEUa/EIUa and the DDF or another NE. A 75 coaxial cable takes the 2 x 8 core structure. Every two coaxial cables form one group, and either of them contains 8 micro-coaxial cables. The 16 micro-coaxial cables in each group constitute 8 E1 transceiver systems. Figure 4-6 shows the outline of an E1 75 coaxial trunk cable (Y-Shaped).
(1) DB-44 connector (2) Main label (identifying the code, version, and manufacturer information of the cable) (3) Label (identifying a coaxial cable) (4) Metal case of the DB-44 connector
Figure 1.2Outline of E1 75 coaxial cable (Y-Shaped) The Y-shaped BSC 75 coaxial cable is a trunk cable. It is an optional configuration. The number of the Y-shaped 75coaxial cables to be installed depends on the site requirements. This cable is used to transmit E1 trunk signals. It connects the active/standby AEUa/PEUa/EIUa board to the DDF or other NEs. The Y-shaped 75 coaxial cable used in the BSC has two DB-44 connectors at one end and has a structure of 2 x 8 cores. That is, the 75-ohm coaxial cable is composed of two cables, each of which contains 8 micro coaxial cables. All of the 16 micro coaxial cables form eight E1 RX/TX links Survey the Y-shaped BSC 75 coaxial cable as the ordinary 75 coaxial cable. Figure 4-7 shows the outline of an E1 120 twisted pair cable.
2012-2-16
Internal
2. Main label (identifying cable code, version, and vendor information) 4. Shell (metal shell of the DB44 connector)
Figure 1.3Outline of E1 120 twisted pair cable The purpose of a 120 twisted pair cable is to transfer E1 trunk signals between an AEUa/PEUa/EIUa and the DDF or another NE. It has a ready DB44 connector at one end. At the other end, a connector needs to be made on the site. Figure 4-8 shows the outline of an E1 120 twisted pair cable (Y-Shaped).
(1) DB-44 connector (2) Main label (identifying the code, version, and manufacturer information of the cable) (3) Label (identifying a twisted pair cable) (4) Metal case of the DB-44 connector Figure 1.4Outline of E1 120 twisted pair cable (Y-Shaped). The Y-shaped BSC 120 twisted pair cable is a trunk cable. It is an optional configuration. The number of the 120 twisted pair cables to be installed depends on the site requirements. This cable is used to transmit E1 trunk signals. It connects the active and standby AEUa/PEUa/EIUa boards to DDF or other NEs. Survey the Y-shaped BSC 120 twisted pair cable as the ordinary 120 twisted pair cable. A T1 100 twisted pair cable appears like an E1 120 twisted pair. It is largely used in North America. As the system has found few applications in the area up to now, Huawei has not released any specifications on the delivery of the T1 100 twisted pair cables. Specify any requirement for a T1 100 twisted pair cable in the remarks area. The 75 trunk cables normally fall into three categories according to the core diameter: 2.2mm cable, 3.4mm cable, and 3.9mm cable. By default, the 2.2 mm 75 trunk cables are delivered. The 120 trunk cables normally fall into two categories according to the core diameter: 0.4 mm cable and 0.5 mm cable. By default, the 0.4 mm 120 trunk cables are delivered. Specify any special requirement in the remarks area. II Length Cable length (for overhead cabling): cable length inside the cabinet (3 m) + vertical distance between the cabinet top and the cabling rack + cabling distance along the cabling rack between the cabinet and the DDF + vertical distance between the DDF top and the cabling rack. See Figure 4-9. Measure each section of length, and sum these lengths up to get the required cable length.
2012-2-16
Internal
Figure 1.1Calculating required trunk cable length for overhead cabling Cable length (for underfloor cabling): cable length inside the cabinet (3 m) + vertical distance between the cabinet bottom and the ground + cabling distance between the cabinet and the DDF + vertical distance between the DDF bottom and the ground. See Figure 4-10. Measure each section of length, and sum these lengths up to get the required cable length.
2012-2-16
Internal
Figure 1.1Straight-through cables on the Ater interface (upward cabling) The length of a cable (downward cabling): The cabling length of the trunk cables in a cabinet (TCS) + distance between the cabinet and the floor * 2 + cabling distance on the cable ladder + the cabling length of the trunk cables in a cabinet (BM). The different distances should be measured that shown in the following figure. The total value is the length of a cable.
Figure 1.2Straight-through cables on the Ater interface (downward cabling) Note: The straight-through cables on the Ater interface can be laid in different cabinets or in the same cabinet. For example, when the BMs and the TCSs are installed in the same cabinet, the length of the straight-through cables on the Ater interface is fixed. 2.2 m long cables are used to interconnect adjacent subracks in the same cabinet. 2.7 m long cables are used to interconnect interphase subracks in the same cabinet.
2012-2-16
10
Internal
Note: A patch cord is the tail of an optical path. It consists of an optical tail and two end connectors. I Optical Fiber Type and Interface Type The optical fibers fall into two types: single-mode fibers and multi-mode fibers. By default, the singlemode optical fibers are delivered. There are three common types of fiber connectors: SC/PC connectors, FC/PC connectors, and LC/PC connectors. The boards in the BSC6900 provide LC/PC ports to match LC/PC connectors. Therefore, each optical fiber for the BSC6900 has an LC/PC connector at one end. The type of the connector at the other end depends on the peer device (ODF or another NE). The BSC6900 is equipped with three types of optical fibers: LC/PC-LC/PC-single-mode/multi-mode optical fibers, LC/PC-FC/PC-singlemode/multi-mode optical fibers, and LC/C-SC/PC-single-mode optical fibers. Figure 4-13 shows the outline of an LC/PC-LC/PC-single-mode/multi-mode optical fiber.
Figure 1.1Outline of LC/PC-LC/PC-single-mode/multi-mode optical fiber Figure 4-14 shows the outline of an LC/PC-FC/PC-single-mode/multi-mode optical fiber.
Figure 1.2Figure 4-10 Outline of LC/PC-FC/PC-single-mode/multi-mode optical fiber Figure 4-15 shows the outline of an LC/PC-SC/PC-single-mode optical fiber.
Figure 1.3Outline of LC/PC-SC/PC-single-mode optical fiber If BSC6900 configured as GO or GU mode, the Ater interface should be surveyed. The Ater interface maybe connects directly between two racks, or connects by the ODF. If the Ater interface connects directly, the connector type is LC/PC. If connects by the ODF, the connector type is decided by the ODFs type. II Survey of Patch Cords Use single-mode optical fibers as patch cords for the Iub, Iu-CS, Iu-PS, Iur, Iu-BC, Abis, Ater, A and Pb interfaces, except when the peer devices require multi-mode optical fibers. The LC/PC-FC/PC single-mode optical fibers are available in the following standard lengths: 10 m, 15 m, 20 m, 25 m, 30 m and 50 m. The LC/PC-SC/PC single-mode optical fibers are available in the following standard lengths: 10 m, 15 m, 20 m, 25 m, 30 m and 50 m. The LC/PC-LC/PC single-mode optical fibers are available in the following standard lengths: 1.5 m, 5 m, 10 m, 15 m, 20 m, and 30 m. The LC/PC-FC/PC multi-mode optical fibers are available in the following standard lengths: 10 m. The LC/PC-SC/PC multi-mode optical fibers are available in the following standard lengths: 10 m. The LC/PC-LC/PC multi-mode optical fibers are available in the following standard lengths: 5 m and 10 m. The quantity of the optical fibers depends on the list of contracts and the actual engineering demand.
2012-2-16 Huawei Technologies Proprietary 11
Internal
III Description of the Straight-Through Optical Fibers on the Ater Interface If the straight-through optical fibers between the BM and the TCS are used on the Ater interface, mark the left grid, when the BSC6900 configured as GO or GU mode. The number of required optical fibers is the half of the number of E1 cables when the ODF is used. The length is determined based on the requirements in the survey report. The default length is 9.7m. For the survey length and quantity, refer to section Description of the Straight-Through Cables on the Ater Interface"Description of the StraightThrough Cables on the Ater Interface."
1. Connect the end with two LC/PC connectors to the active and standby optical interface boards in the BSC, and the other end with one LC/PC connector to an NE at the peer end or ODF through a fiber adapter. The type of connector at the peer end depends on site requirements. 2. Use two optical splitters to work as a pair of optical fibers, and attach temporary labels to both ends of each fiber in the pair.
The TX -and RX ends of each device must be connected correctly. Otherwise, -optical signals cannot be received or transmitted. An optical splitter is a passive duplex component with three ends- and can split and combine optical signals. The following figure shows the exterior of -an optical splitter.
1. LC/PC connector
2. Optical Splitter
3. Single/Multi-Mode Fiber
Optical
2012-2-16
12
Internal
The dimensions (H x W x D) of an optical splitter are 9 mm x 90 mm x 16 mm (3.54 in. x 35.4 in. x 6.24 in.) The length of a single-mode or multi-mode optical cable is 1 meter, and the total length of an optical splitter is 2 meters. An optical splitter splits one input of optical signal to two at a ratio of 1:2. The insertion loss of a single-mode optical splitter, multi-mode optical splitter, and fiber adapter does not exceed 3.8 dB, 4.2 dB, and 0.3 dB, respectively. During a survey, you need to take into account the loss of the optical power because insertion loss occurs in an optical splitter and fiber adapter. The loss of the optical power must meet the following condition: Original optical power loss + Insertion loss of the optical splitter + Insertion loss of the fiber adapter < Minimum output optical power of the optical module in the BSC Maximum receive sensitivity of the optical module at the peer end The following table lists the optical power and the receive sensitivity of the optical module in the BSC: Table 1.1The optical power and the receive sensitivity of the optical module in the BSC
Boar d Transmiss ion Distance Mod e Minimu m Output Optical Power -19.0 dBm -15.0 dBm -5.0 dBm Maximum Output Optical Power -14.0 dBm Maximum Receive Sensitivit y -30.0 dBm Con nec tor Code of the Optical Module 3406028 7 3406027 6 3406028 1
2 km
15 km
40 km
LC
-8.0 dBm
-31.0 dBm
LC
0. dBm
-37.0 dBm
LC
An optical splitter is required when the previous boards work in active/standby mode and transmission devices do not work in active/standby mode. The total length of an optical splitter is 2 meters. During a site survey, make the following decisions: Whether optical splitters are required Number of required optical splitters Whether single-mode or multi-mode splitters are required An optical combiner can combine two inputs of optical signals into one, as shown in Operating principle for an optical combiner.
2012-2-16
13
Internal
Figure 1.2Operating principle for an optical combiner An optical splitter can split one input of optical signal into two, as shown in Operating principle for an optical splitter.
Figure 1.3Operating principle for an optical splitter The following figure shows the position for installing an optical splitter.
Figure 1.4Position for installing an optical splitter The following figure shows the position for installing optical fibers for an optical splitter.
2012-2-16
14
Internal
Figure 1.5Position for installing optical fibers for an optical splitter When an optical splitter is connected to other devices, a fiber adapter is required. No site survey is required for fiber adapters because they are selected and delivered based on the common optical fibers to be used in the live network.
Internal
Figure 1.2Outline of unshielded network cable Shielded Ethernet is used under IP networking delivered by defining length. Use unshielded Ethernet cables (ordinary Ethernet cables) to connect the SCUa boards and OM networking. I Survey of Shielded Ethernet Cables for IP interface boards When the interface board is used for IP networking, shielded Ethernet should be surveyed. Specific RJ45 connector is used for shielded Ethernet and is ready before delivery. Survey the length and quantity of each interface according to actual networking. Caution: The connectors of the shielded Ethernet cables are made using a special tool and are difficult to prepare on the site. Therefore, be sure to make an accurate survey of the shielded cables. In case of any error, Huawei has only to make a redelivery.
I Survey of Ordinary Unshielded Ethernet Cables The ordinary unshielded Ethernet cables are delivered in rolls and connectors should be made on sites. The ordinary unshielded Ethernet can find use in many applications. They connect the inter-SCUa boards between subracks. They connect OMUa boards to the customer's switch. They connect the LMTs to the customer's LAN. They link the BSC6900 with the M2000 with a maintenance WAN. When you doing the survey, the length of Ethernet cables is the sum of all scenarios (for the newly deployed BSC, the interconnecting straight through cables between SCUa boards in MPR cabinet are not included.). In consideration of shrinkage, leave a margin of 15% of the required quantity of the RJ-45 connectors and 20% of the required network cable length. In the BSC6900, the SCUa boards in the MPS and those in the EPS(s) are interconnected through unshielded Ethernet cables. The SCUa boards are connected in a star mode. The unshielded Ethernet cables connect the 10/100/1000BASE-T ports of the SCUa boards in the MPS with the corresponding 10/100/1000BASE-T ports of the SCUa boards in each EPS. The SCUa boards in different EPSs are not connected with one another. When a new BSC is established, if only there is a MPR cabinet, it is not necessary to survey the network cables. In the case of capacity expansion or the new BSC has other cabinets, all the cables of 2.2 m, 2.7 m, and 9.7 m should be surveyed.
Caution: The MPS is installed with the OMU board. The survey of the interSCUa unshielded straight through cables in the MPS is not required. The EPS subrack has no OMU board. The survey of the inter-SCUa unshielded straight through cables is required. For the newly deployed BSC, the survey of the EPS cables in the MPR is not required, because the cables are fully configured by default. For an expanded BSC cabinet, if the EPS is added in the MPR, the corresponding survey is required.
2012-2-16
16
Internal
In RAN11 and later versions, straight through cables are used to interconnect the SCUs between subracks.
Figure 4-18 shows how to connect the SCUa boards in the MPS and those in an EPS.
Figure 1.1Connecting SCUa boards in MPS and those in an EPS through crossover Ethernet cables Figure 4-19 shows the position of the unshielded Ethernet cables in the BSC6900.
Internal
capacity expansion or establish a multiple cabinets BSC, the cables should be surveyed. The cable of 3 m is used for the connection two subracks in the same cabinet. The cable of 10 m is used for the connection between subracks in different cabinets. The follow figure shows how to connect SFP+ high-speed cables in single cabinet.
Figure 1.1Position of SFP+ high-speed cables between SCUb boards in BSC6900 The follow figure shows how to connect SFP+ high-speed cables in multi cabinets.
2012-2-16
18
Internal
Figure 1.2Position of SFP+ high-speed cables between SCUb boards in multi cabinets
Internal
Generally, TNU crossover cables for new BSCs are delivered after pre-installation. Cables that connect TNUs in the same subrack do not need to be surveyed. But these cables must be surveyed for BSC expansion projects. LSZH cables that are required by the telecom operators in European regions must be surveyed no matter whether they are used for new BSC projects or expansion projects. The length and quantity must be recorded in the survey report. Note: Install cables in subracks orderly. The central subrack is the subrack that is at the bottom of the first cabinet. I Introduction to the Cable The Inter-TNU Cables are used for full interconnection between the BSC6900 TNUs of a BM cabinet or a TC cabinet. The follow figure shows the appearance of the Inter-TNU Cables.
(1) DB14 (3) Main label (identifies the cable number, version, and vendor information)
The two DB14 connectors on one end of the Inter-TNU Cable connect to the active/standby mode TNU boards of a service subrack, and the other two DB14 connectors on the opposite end connect to the active/standby mode TNU boards of another service subrack. Installation position of the Inter-TNU Cables shows the installation position of the Inter-TNU Cables on the panel.
Pin14
A
2012-2-16 Huawei Technologies Proprietary 20
Internal
Figure 1.2Installation position of the Inter-TNU Cables The standard lengths of the Inter-TNU Cables are 2.2 m, 2.7 m, and 9.7 m. The length and quantity of the Inter-TNU Cables are determined based on the site survey. I How to Calculate the Length and Quantities Select the length of the Inter-TNU Cable according to the following: The 2.2 m cables are for the interconnection between TNUs of adjacent subracks within a cabinet. The 2.7 m cables are for the interconnection between TNUs of non-adjacent subracks within a cabinet. The 9.7 m cables are for the interconnection between TNUs of two different cabinets. When a new BSC is established, if only there is a MPR cabinet, it is not necessary to survey the interTNU cables. In the case of capacity expansion or the new BSC has other cabinets, all the cables of 2.2 m, 2.7 m, and 9.7 m should be surveyed. Inter-TNU Cables of 2.2 m4 shows the 2.2 m cabling between TNUs of adjacent subracks within a cabinet.
2012-2-16
21
Internal
Figure 1.1Inter-TNU Cables of 2.2 m Inter-TNU Cables of 2.7 m5 shows the 2.7 m cabling between TNUs of non-adjacent subracks within a cabinet.
Figure 1.2Inter-TNU Cables of 2.7 m Inter-TNU Cables of 9.7 m shows the 9.7 m cabling between the TNU boards of different cabinets.
2012-2-16
22
Internal
Figure 1.3Inter-TNU Cables of 9.7 m The quantities of subracks and cables required are shown as follows. The full TNU interconnection is required between the MPS subrack and EPS subrack. For the quantity and type of the cables, refer to Quantity of TNU cables between the MPS subrack and the EPS subrack. Table 3.1Quantity of TNU cables between the MPS subrack and the EPS subrack
Quantity of Subracks Required Quantity and Length of Inter-TNU CABLES
Single MPS
Inter-TNU required
Cables
are
not
MPS + EPS
In a Adjacent Two 2.2 m Inter-TNU Cables same Non-adjacent Two 2.7 m Inter-TNU Cables cabinet In different cabinets Two 9.7 m Inter-TNU Cables
MPS + two EPSs (in two cabinets, with one cabinet having two subracks and the other having one subrack)
Two subracks in one Two 2.2 m cables + four 9.7 m cabinet are adjacent cables Two subracks in one Two 2.7 m cables + four 9.7 m cabinet are not adjacent cables
Use 2.2 m or 2.7 m cables if they are in one cabinet; use 9.7 m MPS + three EPSs (may be placed in two or cable if they are in different three cabinets based on the relevant rule) cabinets. (NOTE: 12 cables are required in total.)
2012-2-16
23
Internal
The full TNU interconnection is also required between the TC subracks. For the quantity of cables required, refer to Table 4-3. Table 3.2Quantity of TNU cables between the TC subracks
Quantity of Subracks Required Quantity and Length of Inter-TNU CABLES
One TCS
Inter-TNU Cables are not required Total quantity of Inter-TNU Cables required two. Length: Use 2.2 m or 2.7 m cables if the TCs are in one cabinet, and use 9.7 m cables if the TCs are in different cabinets. The detailed methods are similar to the MPS and EPS interconnection solution. Total quantity of Inter-TNU Cables required six. Length: Use 2.2 m or 2.7 m cables if the TCs are in one cabinet, and use 9.7 m cables if the TCs are in different cabinets. The detailed methods are similar to the MPS and EPS interconnection solution. Total quantity of Inter-TNU Cables required twelve. Length: Use 2.2 m or 2.7 m cables if the TCs are in one cabinet, and use 9.7 m cables if the TCs are in different cabinets. The detailed methods are similar to the MPS and EPS interconnection solution.
Two TCS
Three TCS
Four TCS
The MPS connects to the TCS through the ATER interface without the TNU interconnection.
Note: To enhance the system reliability and increase the interconnection bandwidth globally, the full interconnection module is used for the TNU boards between the BSC6900 subracks. If n subracks are fully interconnected, the quantity of cables for interconnection is n (n-1).
The Y-shaped clock cables are mandatory for the BSC6900. They transfer location information and synchronous clock signals from the GCUa boards in the MPS to the SCUa boards in the EPS(s). The GCUa boards and the SCUa boards in the MPS are already connected through the backplane. Therefore, no Y-shaped cable is required between them. Figure 3-27 shows the outline of a Y-shaped cable. Caution: The MPS is installed with the OMU board. The survey of the Yshaped cables in the MPS is not required. The EPS subrack has no OMU board. The survey of the Y-shaped cables is required.
Huawei Technologies Proprietary 24
2012-2-16
Internal
For the newly deployed BSC, the survey of the EPS cables in the MPR is not required, because the cables are fully configured by default. For an expanded BSC cabinet, if the EPS is added in the MPR, the corresponding survey is required.
2. RJ45 connector
Figure 1.1Outline of a Y-shaped clock cable Figure 3-28 shows how to connect the GCUa/GCGa boards in the MPS and the SCUa boards in an EPS through Y-shaped clock cables.
Figure 1.2Connecting GCUa/GCGa boards in MPS and SCUa boards in an EPS through Y-shaped clock cables Length
The Y-shaped clock cables are delivered ready made. They are available in three fixed lengths: 2.2 m, 2.7m, and 9.7 m. If a required length is greater than 9.7 m, enter the actual required length in the form. Use 2.2m cables to connect the MPS and the neighboring EPS within the MPR. Use 2.7m cables to connect the MPS and the non-neighboring EPS within the MPR. Use 9.7m cables to connect the MPS and the EPS(s) in the EPR, if any combined with the MPR. See Figure 3-29. When a new BSC is established, if only there is a MPR cabinet, it is not necessary to survey the Y-shaped clock signal cables. In the case of capacity expansion or the new BSC has other cabinets, all the cables of 2.2 m, 2.7 m, and 9.7 m should be surveyed.
2012-2-16
25
Internal
The active and standby GCUa boards in the MPS respectively have one Y-shaped clock connected with the SCUa boards in each EPS. Therefore, the number of Y-shaped clock cables is equal to the number of EPSs multiplied by 2. Table 3-4 lists how many and how long Y-shaped clock cables are required in each configuration scenario. Table 1.1Quantity of Y-shaped clock cables
Number of Subracks 1MPS 1MPS + 1EPS (within the MPR) 1MPS + 2EPS 1MPS + 3EPS in the EPR) 1MPS + 4EPS in the EPR) 1MPS + 5EPS in the EPR) (within the MPR) (2 EPSs in the MPR and the rest 1 EPS (2 EPSs in the MPR and the rest 2 EPS (2 EPSs in the MPR and the rest 3 EPS Quantity and Length of Y-Shaped Clock Cables N/Y. 2 2.2m cables 2 2.2m cables 2 2.2m cables 9.7m cables 2 2.2m cables 9.7m cables 2 2.2m cables 9.7m cables + 2 2.7m cables + 2 2.7m cables + 2 + 2 2.7m cables + 2 x 2 + 2 2.7m cables + 3 x 2
II Survey of BITS Clock Cables Skip this survey unless the BSC6900 uses BITS clock cables. The BITS clock cables are physically normal E1 cables. The BSC6900 supports the following types of BITS clock cables: 75-SYV-75-2-2 (3.9mm, default), 120-0.5mm (default), and 120-0.4mm. Each BITS clock cable has a ready SMB connector to be connected with a GCUa at one end. At the other end, an SMB or BNC connector needs to be made on the site. Specify any requirement for a ready connector at the other end in the remarks area with the connector type.
2012-2-16 Huawei Technologies Proprietary 26
Internal
III Survey of Line Clock Cables Skip this survey unless the BSC6900 uses line clock cables. The length of a line clock cable is equal to the cabling distance between a line clock interface board and the connected GCUa. If the line clock interface boards and the GCUa boards are within the same subrack (for example, MPS), they communicate through the backplane and no line clock cable is required between them. Each line clock cable has a ready SMB connector at one end. At the other end, a fitted SMB connector needs to be attached on the site.
Figure 1.2Installing 7/8" or 5/4" feeder Figure 3-31 shows how to install a 1/2" feeder.
2012-2-16
27
Internal
Figure 1.3Installing 1/2" feeder Enter the actual required GPS feeder length in the form. The length determines whether to use a 1/2", 7/8", or 5/4" feeder. Use a 1/2" feeder if the length is less than 100 m. Use a 7/8" coaxial cable if the length is between 100 m and 300 m. Use a 5/4" coaxial cable if the length is greater than 300 m. The Order Configuration Department will deliver the appropriate types of feeders, jumpers and coaxial connectors according to the actual required length. There are two types of window of the feeder: 7/8" and 5/4". 7/8" feeder window is corresponding to 1/2" and 7/8" feeders; and 5/4" feeder window is corresponding to 5/4" feeders. According to the actual situation, tell whether to use a feeder window. If the window of the feeder is not supplied by the customer, it should be surveyed to be delivered. The Order Configuration Department will deliver the appropriate type of feeder window. If the customer already supplies the window of the feeder, please confirm that the type of the window of the feeder is corresponding to the type of the feeders.
Figure 1.1Outline of alarm signal cable II Power cable The alarm box supports two power inputs 220V AC and 48V DC. If it is decided to use the DC power input, lead a special power cable from the BSC6900 to the special trough of the alarm box. The power cables are available in a standard length of 30 m. The alarm signal cables are available in a standard length of 30 m to 60 m. Enter the actual required length in the form. If a required length is greater than the standard length, the Order Configuration Department will deliver an additional length.
2012-2-16 Huawei Technologies Proprietary 28
Internal
If it is decided to use the AC power input, use a default 6m-long AC power cable. Normally no additional length is available. If the alarm box is more than 6 m away from the AC power source, add a socket near the alarm box. Make a survey of the alarm signal cables. Judge the required alarm cable length according to the cabling distance. Note that the alarm cables cannot be routed together with AC power cables and other interference sources. It is recommended to use the 220V AC power input. III Others Make a survey of the other alarm box accessories, such as PVC protection trough. The PVC protection trough is used to protect the alarm signals below the floor. In the case of underfloor cabling, it is acceptable not to enclose the whole length of alarm cables in a PVC protection trough. The length routed upward or downward along a wall can be packed in PVC protection troughs, 2 m in each trough. The PVC will not deliver any more, if need PVC, please purchase it. Make a survey of the alarm box cables if the BSC6900 is separately delivered. Skip this survey if it is decided to deliver the BSC6900 together with the M2000. In the latter case, the survey of the alarm box cables is concurrent with that of the M2000.
2012-2-16
29
Internal
2012-2-16
30
Internal
After the installation environment check, send a copy of Preparation Guide for the Installation to the customer. Explain the items in the Site Preparation Checklist to the customer. Ask the customer to make a preparation by the Site Preparation Checklist and send their feedback as soon as possible.
2012-2-16
31