3 May 2011

Samar Tahir ID:707649


Part I : Project Scope Part II : Project Swap Scenarios Part III: Key points of Installation
www.huawei.com

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

3 May 2011

Part - I Project Scope


www.huawei.com

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Objectives and Scope - I


Project Name : Saudi Mobily WiMAX & LTE Project 5508500 In order to meet the requirement of Mobily multiple networks deployment, Huawei presents multimode BTS solution which is applicable for WiMAX/TDLTE multi-mode deployment and smooth evolution from WiMAX to LTE Scope :
Huawei Existing City New City Easten&Madinah,Yanbo 415 99 477

1)Huawei 265 WIMAX sites upgrade, and 150 new sites based on Huawei WIMAX coverage cities. 2) 99 new TDL and WIMAX co-sites will be built in the New cities. 3) 477 new TDL and WIMAX co-sites will be built in Easten, Madinah and Yanbo area.

Huawei will introduce a new LTE network with two SAE geographically separated in location within the same access network using single ran solution which will put up with the exceeding data demands of end users.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 3

Objectives and Scope - II


Two new ASN-GWs will be added to the existing network and will be installed in GOSIDammam and Silver-Khobar. Huawei is proposing two possible scenarios for the Target Network Topology. The distribution is done based on geographic location of cities keeping in mind the transmission delay consideration. Both scenarios are as following:

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 4

3 May 2011

Part - II Project Swap Scenarios


www.huawei.com

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Contents
1 2 3 4 5 6 Swap Strategy Swap Scenario analysis Swap Process Rollback Process Risk Analysis Proposed Solution

Page 6

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

1) Swap Strategy for WiMAX


Based on RF proposed Clusters : An efficient Solution
Number of sites to be Swapped (i.e. sites per cut-over night) High Swap a complete network
Cluster swap

Cluster-based Swap is the most practical strategy

Clusterbased Swap

Cluster scale: 7~10 sites


Low Swap site by site

Low

Medium

High

Project complexity and risk

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 7

1) Swap Strategy for MW (Transmission)


Swapping a complete MW Link : An efficient Solution
Number of sites to be Swapped (i.e. sites per cut-over night) High Swap a complete network
Cluster swap

Link-based Swap is the most practical strategy

Link-based Swap

Cluster scale: 6~10 sites


Low Swap site by site

Low

Medium

High

Project complexity and risk

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 8

2) WiMAX Swap Strategy


Swap Strategy----Cluster Mode
Step 1: Install and commission Huawei ASN_GW/ DBS3900

Strategy

Step 2: During MDT : power off existing sites in Cluster (n) Step 3: power on new sites in the cluster (n) Step 4: Drive test the cluster (n)
CSN
Huawei ASN_GW Existing ASN_GW

Cluster Mode

Advantages Risk

Easy Project Management and Schedule Control. Cut-over risk can be controlled easily. Have a chance to roll back. Some modification to existing network for cooperating with new system (different network planning scheme Signal may face interference on boundary region

Step 5: Remove existing equipment

Cluster 1
Existing BTS New DBS3900

Cluster N
New DBS3900 Existing BTS New DBS3900

Existing BTS

New DBS3900

Existing BTS

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 9

2) Microwave Swap Strategy Depending on the Site Scenario


BTS/eNB BTS/eNB

100Mbps, 1+0 150Mbps, 1+0

BTS/eNB BTS/eNB BTS/eNB aGW

BTS/eNB

RTN950 RTN910

Configuration: 1 pcs CSHA card 1 pcs IFU2 card

Configuration: 1 pcs CSH card 3 pcs IFU2 card 1 pcs EM6F card
HUAWEI Confidential

HUAWEI TECHNOLOGIES Co., Ltd.

Page 10

Contents
1 2 3 4 5 9 Swap Principles and Strategy Swap Scenario analysis Swap Process Rollback Process Risk Analysis Proposed Solution

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 11

Scenario Analysis for WiMAX site Swap


Based on the experience of Huawei Swap Project, 4 scenarios for the BTS Swap are provided as follows: Easy swap mean that There is extra space, power and accessibility for new DBS3900. The reverse is hard swap
Scenario Definition Scenario No. Swap Type A B C D TX YES YES No No Antenna Space YES No No No Indoor (space, power) YES YES YES No 5h 5h 6h Down Time GF 2h 3h 4h 6h RT Person 1 3 3 3 Remarks

1 2 3 4

Click- here
For more information
-

Click here
For more information

Click here
For more information
-

Click here
For more information

Note: A means classification A, Easy Swap & high priority; B means classification B, Hard Swap & Second priority;

MDT will apply by cluster, and Down time of cluster should consider by maximum down time of site

Please click here to go to WiMAX and MW Combined Scenarios

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 12

Easy Swap-A, with Extra Transmission, Space & Power: Definition.


There is extra space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS.

DBS3900 site Swap Scenario A

There have transmission for Huawei DBS3900 to commissioning (use existing IDU or Mobily switch)

Key point

Completing civil work in advance (Outdoor RRU rack, Minor civil work) Lay out jumper, Feeder, fiber cables & power cables in advance. Completing the hardware installation and commissioning (integration) of Huawei DBS3900 in advance
(DBS3900, RRU, DC-Box & Antenna), and

block huaweis cells

Downtime

Site downtime 2 hour deactivate all sectors of sumsungs wimax site remotely Active Huaweis blocked sectors remotely Drive test, confirm service is normal and put site on air. Power off Samsung BTS
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Page 13

Go back Main menu

Hard Swap, with Extra Transmission, indoor space, power: Definition.


There have extra indoor space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS. There have No Extra space for Huawei antennas

DBS3900 site Swap Scenario B

Key point

Completing Civil work in advance (Outdoor RRU rack, Minor civil work) Lay out jumper, Feeder, fiber cables & power cables in advance Completing the hardware installation and commissioning (integration) of Huawei DS3900 in advance
(DBS3900, RRU, DC-Box),and

block huaweis cells

Downtime

site downtime 5 & 3 hour Power off Samsung BTS Remove sumsungs antennas and install huaweis antennas Unblock huaweis cells remotely and do the drive test Confirm service is normal and put site on air
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Page 14

Go back Main menu

DBS3900 site Swap Scenario C


Hard Swap, with Extra indoor space, power: Definition.
There have extra indoor space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS. There have No Extra transmission for Huawei DBS3900 to commissioning & No Extra space for antennas Huawei

Key point

Completing Civil work in advance (Outdoor RRU rack, Minor civil work) Completing the hardware installation and commissioning of Huawei DS3900 locally in advance
(DBS3900, RRU, DC-Box)

Lay out jumper, Feeder, fiber cables & power cables in advance

Downtime

site downtime 5 & 4 hour Power off sumsungs BTS Remove sumsungs antennas and install Huaweis antennas Cutover transmission from Samsung BTS to Huawei DBS3900 integrate this site locally and unblock cells Do Drive Test and confirm service is normal, then put site on air
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Page 15

Go back Main menu

DBS3900 site Swap Scenario D


Hard Swap: Definition.
There is no extra footprint for Huawei DBS3900 installation. Completing Civil work in advance (Outdoor RRU rack, Minor civil work) Lay out jumper, Feeder, fiber cables & power cables in advance Completing the hardware installation
(BBU and DCDU within MDT time)

Key point

Downtime

site downtime 6 hour Sumsungs team Power off sumsungs BTS and remove their equipment Remove sumsungs antennas and install Huaweis antennas Install huaweis BBU and DCDU in space position and power on huaweis DBS3900 Do commissioning and integration locally unblock cells Do Drive Test and confirm service is normal, then put site on air
Go back Main menu

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 16

MW Swap Scenario:
Scenario Description
Install and then dismantle(Temp frequency available) Scenario 1

Please click here to go to WiMAX and MW Combined Scenarios

Advantage
This solutions is available . All the Installation and alignment can be done without MDT. It can be roll back This solutions is available when there is no Temp frequency. It can be roll back This solution is available when there is no space available on the original infrastructure and no space to erect a new structure on the tower. The outage downtime is short in solution. The link only stays down during the cutover. After re-routing, it can release some spaces on the congested infrastructure for future swap.

Risks
Small risk when MDT

Remarks
Click here
For more information

Scenario 2

Install and then dismantle(Temp frequency unavailable)

Alignment time depending on the size of new antenna . Medium risk. Link outage vary from case to case, depending on the size of the newly install antenna and path distance. And it can not be roll back. High risk.

Click here
For more information

Scenario 3

Direct swap then install new link

Click here
For more information

Scenario 4

Re-rout

Need new licensed frequency and LOS risk.

Click here
For more information

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 17

MW Swap Scenario 1:
To have enough space to install new Microwave antenna and use temp frequency

Swap Solution:
Swap Process (in daytime, First times)

up

New antenna candidate place: another side

existing antenna

To Install a new MW link, It is including IDU, ODU, antenna, all of used cable; Power on the new link and mute the ODU, then configure the frequency with temp frequency and make the alignment. Configuration the service after finish the alignment . Power off the new link.

down

Go back Main menu

Next Page

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

MW Swap Scenario 1
To have enough space to install new Microwave antenna and use temp frequency

Swap Process (in midnight MDT time.)


Power off the original microwave equipment link frequency as perdesign again; and monitor it.

Power on the new microwave link and configure the After finish step 2, connect Lan cable(fiber) to Winmax

Go back Main menu

Previous Page

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

MW Swap Scenario 2:
To have enough space to install new Microwave antenna and use existing link frequency, namely have no temp frequency

Swap Solution:
Swap Process (in daytime, First times) To Install a new MW link, It is including IDU, ODU, antenna, all of used cable; Power on the new link and mute the ODU, then configure the frequency with original frequency and service. Power off the new link.

up

New antenna candidate place: another side

existing antenna

down

Go back Main menu

Next Page

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

MW Swap Scenario 2
To have enough space to install new Microwave antenna and use existing link frequency, namely have no temp frequency

Swap Process (in daytime MDT time, the second times,


Downtime is from 5 hours to more than 8 hours, It depends on the antenna size.) Power off the original microwave equipment link

Power on the new microwave link and make alignment; After finish step 2, connect Lan cable(fiber) to Winmax and monitor it.
Go back Main menu Previous Page

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

MW Swap Scenario 3
No enough space to install new Microwave antenna and mounting pole

Swap Solution:
Swap Process (in daytime, First times)
To install a new IDU and other indoor equipment and used cable. And prepare ODU&antenna. Test hardware and finish site configuration of IDU separately in each site.

Go back Main menu

Next Page

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

MW Swap Scenario 3
No enough space to install new Microwave antenna and mounting pole on tower. Swap Process (in midnight, the second times, Downtime is from 5 hours to more than 8 hours, It depends on the antenna size. ) Power off the original microwave equipments and dismantle existing link. Then install new antenna&ODU rapidly; Power on new microwave equipments and make alignment; Configure the service and connect lan(fiber) cable to Wimax, especially check new MW link status.
Go back Main menu Previous Page

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Site Swap Scenario 4


No enough space to install new Microwave antenna on the existing radios tower leg to the existing far-end site, but has spaces on other tower legs which can be utilized to divert the traffic to adjacent chains.

Swap Solution:
Swap Process (in daytime, First times)
To install a new mounting pole for microwave antenna on other tower legs. To install a new MW link including IDU, ODU, antenna, all of used cable; MW pre-commissioning with new frequency to ensure operation availability; To Configure the Ethernet service and ping each other between Near site and far-site.
Go back Main menu Next Page

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Site Swap Scenario 4


No enough space to install new Microwave antenna on the existing radios tower leg to the existing far-end site, but has spaces on other tower legs which can be utilized to divert the traffic to adjacent chains. Swap Process (in midnight, the second times) Power off the original microwave equipments; Power on new microwave equipments; Configure the existing frequency to Huawei microwave equipment.

Go back Main menu

Previous Page

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 25

Combined Scenarios for WiMAX and MW


Swap Type Serial No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 A1 A2 A3 A4 B1 B2 B3 B4 C1 C2 C3 C4 D1 D2 D3 D4 Scenario A A A A B B B B C C C C D D D D WiMAX Scenario Definition TX YES YES YES YES YES YES YES YES No No No No No No No No Antenna Space YES YES YES YES No No No No No No No No No No No No Indoor (space, power) YES YES YES YES YES YES YES YES YES YES YES YES No No No No Scena rio 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 MW Scenario Definition Temp Freq YES No N/A N/A YES No N/A N/A No No N/A N/A No No N/A N/A Antenna Space YES YES No No YES YES No No YES YES No No YES YES No No Re-Routing Required No No No Yes No No No Yes No No No Yes No No No Yes

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

1. Scenario A1
Definition: There is extra indoor space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. Also for MW the temp freq is available as well as the space on tower for installation of antennas before MDT. Key points: 1) Install WiMAX BTS and MW before MDT. 2) Commission WiMAX BTS before MDT. 3) Finish LOS for MW before MDT using Temp frequency. 4) Install WiMAX antennas and out door equipment before MDT. 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment. 6) Test Service. 7) Dismantle the existing MW and WiMAX BTS during MDT. Details: For Details on WiMAX Equipment Handling in Scenario A1 , please click here. For Details on MW Equipment Handling in Scenario A1 , please click here.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

2. Scenario A2
Definition: There is extra indoor space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. MW Temp freq is not available but the space on tower for installation of MW antennas is available. Key points: 1) Install WiMAX BTS and MW before MDT. 2) Commission WiMAX BTS before MDT. 3) Install WiMAX antennas and out door equipment before MDT. 4) Finish LOS during MDT using the existing frequency. 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment. 6) Test Service. 7) Dismantle the existing MW and WiMAX BTS during MDT. Details: For Details on WiMAX Equipment Handling in Scenario A2 , please click here. For Details on MW Equipment Handling in Scenario A2 , please click here.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

3. Scenario A3
Definition: There is extra indoor space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. Key points: 1) Install WiMAX BTS before MDT. 2) Commission WiMAX BTS before MDT. 3) Install WiMAX antennas and out door equipment before MDT. 4) Install MW during MDT. (Replacing existing MW) 5) Finish LOS during MDT using the existing frequency. 6) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment. 7) Test Service. 8) Dismantle the existing WiMAX BTS during MDT. Details: For Details on WiMAX Equipment Handling in Scenario A3 , please click here. For Details on MW Equipment Handling in Scenario A3 , please click here.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

4. Scenario A4
Definition: There is extra indoor space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. MW LOS during MDT is not successful. Key points: 1) Install WiMAX BTS before MDT. 2) Commission WiMAX BTS before MDT. 3) Install WiMAX antennas and out door equipment before MDT. 4) Install MW during MDT. (Replacing existing MW) 5) Cannot Finish LOS during MDT using the existing frequency or MW Design has been changed due to capacity planning or have losses in the link. Need Re-Routing. 6) Finish Re-Routing. 7) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment. 8) Test Service. 9) Dismantle the existing WiMAX BTS during MDT. Details: For Details on WiMAX Equipment Handling in Scenario A4 , please click here. For Details on MW Equipment Handling in Scenario A4 , please click here.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

5. Scenario B1
Definition: There is extra indoor space , power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT. Also for MW the temp freq is available as well as the space on tower for installation of MW antennas before MDT. Key points: 1) Install WiMAX BTS (indoor + RRU) and MW before MDT. 2) Commission WiMAX BTS before MDT. 3) Finish LOS for MW before MDT using Temp frequency. 4) Install WiMAX antennas during MDT after dismantling existing antennas. 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment. 6) Test Service. 7) Dismantle the existing MW during MDT. Details: For Details on WiMAX Equipment Handling in Scenario B1 , please click here. For Details on MW Equipment Handling in Scenario B1 , please click here.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

6. Scenario B2
Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT. MW Temp freq is not available but the space on tower for installation of MW antennas is available. Key points: 1) Install WiMAX BTS (excluding antennas) and MW before MDT. 2) Commission WiMAX BTS before MDT. 3) Finish LOS during MDT using the existing frequency. 4) Install WiMAX antennas during MDT. 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment. 6) Test Service. 7) Dismantle the existing MW and WiMAX BTS during MDT. Details: For Details on WiMAX Equipment Handling in Scenario B2 , please click here. For Details on MW Equipment Handling in Scenario B2 , please click here.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

7. Scenario B3
Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX freq is not available and the space on tower for installation of MW antennas is also not available. Key points: 1) Install WiMAX BTS before MDT. 2) Commission WiMAX BTS before MDT using existing transmission. 3) Install WiMAX out door equipment before MDT. 4) Install MW during MDT. (Replacing existing MW). 5) Install WiMAX antennas during MDT (Replacing Existing Antennas). 6) Finish LOS during MDT using the existing frequency. 7) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment. 8)Test Service. 9) Dismantle the existing WiMAX BTS during MDT. Details: For Details on WiMAX Equipment Handling in Scenario B3 , please click here. For Details on MW Equipment Handling in Scenario B3 , please click here. Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT. MW Temp

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

8. Scenario B4

Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. MW LOS during MDT is not successful. Key points: 1) Install WiMAX BTS before MDT. 2) Commission WiMAX BTS before MDT using existing transmission. 3) Install WiMAX out door equipment before MDT. 4) Install MW during MDT. (Replacing existing MW) 5) Install WiMAX antennas during MDT. (Replacing existing antennas) 6) Cannot Finish LOS during MDT using the existing frequency or MW Design has been changed due to capacity planning or have losses in the link. Need Re-Routing 7)Finish Re-Routing. 8) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment. 9) Test Service. 10) Dismantle the existing WiMAX BTS during MDT. Details: For Details on WiMAX Equipment Handling in Scenario B4 , please click here. For Details on MW Equipment Handling in Scenario B4 , please click here.
HUAWEI Confidential

HUAWEI TECHNOLOGIES Co., Ltd.

9. Scenario C1
Definition: There is extra indoor space , power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. Also for MW the temp freq is available as well as the space on tower for installation of MW antennas before MDT. Key points: 1) Install WiMAX BTS (indoor + RRU) and MW before MDT. 2) Finish LOS for MW before MDT using Temp frequency. 3) Commission WiMAX BTS during MDT by swapping transmission with existing BTS. 4) Install WiMAX antennas during MDT after dismantling existing antennas. 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment. 6)Test Service. 7) Dismantle the existing MW and BTS during MDT. Details: For Details on WiMAX Equipment Handling in Scenario C1 , please click here. For Details on MW Equipment Handling in Scenario C1 , please click here.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

10. Scenario C2
Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. MW Temp freq is not available but the space on tower for installation of MW antennas is available. Key points: 1) Install WiMAX BTS (excluding antennas) and MW before MDT. 2) Finish LOS during MDT using the existing frequency. 3) Commission WiMAX BTS during MDT by swpping transmission with existing BTS. 4) Install WiMAX antennas during MDT. 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment. 6) Test Service. 7) Dismantle the existing MW and WiMAX BTS during MDT. Details: For Details on WiMAX Equipment Handling in Scenario C2 , please click here. For Details on MW Equipment Handling in Scenario C2 , please click here.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

11. Scenario C3
Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. Key points: 1) Install WiMAX BTS (excluding antennas) before MDT. 2) Commission WiMAX BTS during MDT by swapping transmission with existing BTS. 3) Install MW during MDT. (Replacing existing MW). 4) Install WiMAX antennas during MDT (Replacing Existing Antennas). 5) Finish LOS during MDT using the existing frequency. 6) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment. 7)Test Service. 8) Dismantle the existing WiMAX BTS during MDT. Details: For Details on WiMAX Equipment Handling in Scenario C3 , please click here. For Details on MW Equipment Handling in Scenario C3 , please click here.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

12. Scenario C4

Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. MW LOS during MDT is not successful. Key points: 1) Install WiMAX BTS (excluding antennas) before MDT. 2) Commission WiMAX BTS during MDT by swapping transmission of existing BTS. 3) Install MW during MDT. (Replacing existing MW) 4) Install WiMAX antennas during MDT. (Replacing existing antennas) 5) Cannot Finish LOS during MDT using the existing frequency or MW Design has been changed due to capacity planning or have losses in the link. Need Re-Routing. 6) Finish Re-Routing. 7) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment. 8) Test Service. 9) Dismantle the existing WiMAX BTS and MW during MDT. Details: For Details on WiMAX Equipment Handling in Scenario C4 , please click here. For Details on MW Equipment Handling in Scenario C4 , please click here.
HUAWEI Confidential

HUAWEI TECHNOLOGIES Co., Ltd.

13. Scenario D1
Definition: There is no extra indoor space to allow Installation of the Huawei DBS3900 parallel to the existing BTS. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. For MW the temp freq is available as well as the space on tower for installation of MW antennas before MDT. Key points: 1) Install WiMAX BTS (outdoor excluding antenna) and MW before MDT. 2) Finish LOS for MW before MDT using Temp frequency. 3) Install WiMAX BTS during MDT by first dismantling existing BTS. 4) Commission WiMAX BTS during MDT by swapping transmission with existing BTS. 5) Install WiMAX antennas during MDT after dismantling existing antennas. 6) Switch off existing MW equipment during MDT and Switch On Huawei Equipment. 7) Test Service. 8) Dismantle the existing MW. Details: For Details on WiMAX Equipment Handling in Scenario D1 , please click here. For Details on MW Equipment Handling in Scenario D1 , please click here.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

14. Scenario D2
Definition: There is not extra space to allow Installation of the Huawei DBS3900 parallel to the existing BTS. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. MW Temp freq is not available but the space on tower for installation of MW antennas is available. Key points: 1) Install WiMAX BTS (outdoor excluding antennas) and MW before MDT. 2) Finish LOS during MDT using the existing frequency. 3) Install WiMAX BTS during MDT by first dismantling existing BTS. 4) Commission WiMAX BTS during MDT by swapping transmission with existing BTS. 5) Install WiMAX antennas during MDT. (Replacing Existing Antennas). 6) Switch off existing MW equipment during MDT and Switch On Huawei Equipment. 7) Test Service. 8) Dismantle the existing MW. Details: For Details on WiMAX Equipment Handling in Scenario D2 , please click here. For Details on MW Equipment Handling in Scenario D2 , please click here.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

15. Scenario D3
Definition: There is no extra space to allow Installation of the Huawei DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. Key points: 1) Install WiMAX BTS (out door excluding antennas) before MDT. 2) Install WiMAX BTS during MDT by dismantling existing equipment. 3) Commission WiMAX BTS during MDT by swapping transmission with existing BTS. 4) Install MW during MDT. (Replacing existing MW). 5) Install WiMAX antennas during MDT (Replacing Existing Antennas). 6) Finish LOS during MDT using the existing frequency. 7) Switch off existing MW equipment during MDT and Switch On Huawei Equipment. 8)Test Service. Details: For Details on WiMAX Equipment Handling in Scenario D3 , please click here. For Details on MW Equipment Handling in Scenario D3 , please click here.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

16. Scenario D4

Definition: There is no extra space to allow Installation of the Huawei DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. MW LOS during MDT is not successful. Key points: 1) Install WiMAX BTS (out door excluding antennas) before MDT. 2) Install WiMAX BTS during MDT by dismantling existing equipment. 3) Commission WiMAX BTS during MDT by swapping transmission of existing BTS. 4) Install MW during MDT. (Replacing existing MW) 5) Install WiMAX antennas during MDT. (Replacing existing antennas) 6) Cannot Finish LOS during MDT using the existing frequency or MW Design has been changed due to capacity planning or have losses in the link. Need Re-Routing. 7) Finish Re-Routing. 8) Switch Off existing MW equipment during MDT and Switch On Huawei Equipment. 9)Test Service. Details: For Details on WiMAX Equipment Handling in Scenario D4 , please click here. For Details on MW Equipment Handling in Scenario D4 , please click here.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Contents
1 2 3 4 5 9 Swap Principles and Strategy Swap Scenario analysis Swap Process Rollback Process Risk Analysis Proposed Solution

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 43

End-to-End Swap Work Process


Design Review & Benchmarking Survey & Design Swap Solution Review
Complete end-toend solution Solution Analysis/Review Swap solution and approval

Swap Implementation

Optimization & Acceptance

Develop Swap strategy

Site Survey

Swap preparation

Driver test and Statistical counters Network optimization

Critical Review of existing network design and parameter mapping Performance benchmarking

Site Audit and related design Site RF design approval

Swap Demo & Training (Sub-Urban) Implementation

Customer Acceptance test

100 90 80 70 60 50 40 30 20 10 0 0 3 6 9 12 15 18 21 24 27 30

33

36

39

42

45

Number of Sit es

Network information collection & assessment

Radio network survey & engineering survey

Network swap planning

48

Swap implementation

Network Monitor and Optimization

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 44

End-to-End Swap Work Process for WIMAX


Standard Operation Procedure For WIMAX Swap :
WIMAX SWAP SOP V1.1

Cutover Flowchart For WIMAX Swap :

Cutover Flowchart for SWAP

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Contents
1 2 3 4 5 9 Swap Principles and Strategy Swap Scenario analysis Swap Process Rollback Process Risk Analysis Proposed Solution

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 46

Rollback Principles
WiMAX Rollback criteria: Base on number of sites unsuccessfull in SWAP cluster WiMAX Rollback Actions: Troubleshooting unsuccessfull sites during MDT Request support to rollback to samsung. MW Rollback criteria:

Base on number of sites unsuccessfull in SWAP cluster

MW Rollback Actions: Troubleshooting unsuccessfull sites during MDT Request support from Trx team if required.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 47

Contents
1 2 3 4 5 6 Swap Principles and Strategy Swap Scenario analysis Swap Process Rollback Process Risk Analysis Proposed Solution

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 48

Risks Analysis
WiMAX Risks Involved: On time support required to dismantle existing equipment and incase of rollback. MW Risks Involved: 1. Some Fiber sites are not confirmed. This will affect the LOS &site survey. This still affect our implement design. 2. Swap risk: Customer request use the existing links frequency. It means we will face 2 scenarios: Enough space to install. Can roll back but can not forecast how long the downtime it will be . No space to install: first dismantle existing link, then install new link and alignment. This can not roll back, high risk. And all the work on the tower need to be done in the day time. RNP Risks Involved: In the swap period, everyday the network will have new provisional boundary with Samsung sites. Because of this the HO KPI may be bad.But for that the wimax service is fixed wireless service so there is not some real heavy affection to the users. About the detail performance risk considering and solution preparation, Huawei need to first collect the Samsung current network information then do the analyse and report to Mobily.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Contents
1 2 3 4 5 6 Swap Principles and Strategy Swap Scenario analysis Swap Process Rollback Process Risk Analysis Proposed Solution

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Page 50

Recommended Proposal:
1. Proposal One: First Swap Wimax Sites

2. Proposal Two: (Recommended) 3. Proposal Three:

Then Swap MW transmission Start Swap Wimax in Region A and SWAP MW in Region B simultaneously . Precondition: Match RF cluster with MW link design

3.A: First Swap WiMAX according to RF clusters, Once all Wimax sites are Swapped in a particular MW link, then Swap MW for that Link. (Some sites might be require two or even more MDTs depending on MW link design)

3.B: Swap Both MW and WiMAX Simultaneously in same RF cluster.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Benefits Of Recommended Proposal:

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

2011-5-3

Security Level:

Part - III Installation Key Point

www.huawei.com

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

INDOOR EQUIPMENT [Key points]


Types of indoor equipment include: DCDU [DC-Power Distribution Unit] BBU [Base Band Unit for WiMAX] Transmission Rack in Block-8 Should be utilized for installation unless specified otherwise. [Block 8 is the right most 60cm*60cm block when entering the shelter ] 63A fuses should be used to connect DCDU with existing DCDistribution BOX [DCDB] installed usually on wall in block 7 of the shelter. If DCDB is full then the direct connection with rectifier can be made but power team approval is required from Mobily. DCDB uses round fuses while rectifier uses fuse with pins on top and bottom.
Page 54

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

DCDU

Has 9 power outputs = Load 0- Load 5 for RRU , Load 6,7 for BBU power1&2 Leave the last one blank Should leave 1U gap between Equipments for cable routing and heat dissipation Proper Labeling required as shown in picture
Page 55

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

BBU 1/2

Slot0 BBBI F A N Slot1 Slot2 BBBI Slot3

Slot4 USCU UPEU0 Slot5 Slot6 reserved UPEU1 Slot7 BMPT

BMPT = Main Processing and transmitting Unit BBBI = Base Band Processing and Radio interface Unit UPEU = Universal power and Environmental Interface Unit

Page 56

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

BBU 2/2

BMPT
FE/GE0 for transmission [Mw IDU or Cisco Switch] GPS for GPS signal cable ETH for Local commissioning

BBBI
CPRI0 for fiber connections to RRU

UPEU PWR for power connection with DCDU MON1/2 Input and output of environment alarm signals. EXT-ALM Boolean-value signals and monitoring the ext environment.
Page 57

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

OUTDOOR EQUIPMENT [Key points]


Outdoor Equipments Include: RRU GPS Antenna Antenna RF Combiner GPS should be connected to BBU through antenna arrestor. Color Coding for feeder Antenna Combiner , and CPRI for RRU BBU is extremely important to get rid of any cross connections. Swap Sites = RF Antenna azimuth for Existing [Samsung] Antennas should be noted before installation of Huawei RF antennas. Three RRU power cables should be routed in one PVC pipe. Three RRU CPRI cables should be routed in one PVC pipe. Its important to note RRU type Wimax/LTE , before installing on pole/rack.

Page 58

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

RRU

WiMAX RRU: 2614MHz~2624 MHz TD-LTE RRU: 2582MHz~2602


Page 59

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

MHz

1.RRU Rack overview - 1

Page 60

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

1.RRU Rack overview - 2

Page 61

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

RRU Installation 1/3


Wimax RRU

Auxiliary bracket Auxiliary bracket Main bracket 2

Main bracket

LTE RRU

Main bracket 1
Page 62

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

RRU Installation 2/3


WiMAX TDD RRU WiMAX TDD RRU LTE TDD RRU

Same direction
Page 63

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

RRU Installation 3/3

Page 64

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Combiner

Page 65

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

RRU- Combiner Connection


WiMAX RRU LTE TDD RRU Bottom View of WiMAX RRU

ANTA_TX/RX

C D

Bottom View of LTE RRU

CB

D A
ANTB_TX/RX ANTA_TX/RX

Top View of Combiner

C NOTE : COMBINER ALWAYS TO BE INSTALLED ON LTE SIDE OF THE POLE !!!


HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Top View of Combiner

Page 66

Antenna

Bottom View of Antenna and Combiner

Page 67

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Antenna Installation [Color Coding]

Sector 1 Red Sector 2 Yellow Sector 3 Blue Sector 1 Red Sector 2 Yellow Sector 3 Blue

Page 68

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

GPS Antenna Installation


The location requirements for installing the GPS antenna are as follows: Install the GPS antenna in open air. The installation place should have no obstacles at the angle of 10 above the horizon. Keep the antenna away from high buildings and accessory construction on the roof. Install the GPS antenna on a platform as large as possible. The antenna must have an upright visual angle greater than 90.

Note :In phase 1 we just leave this cable there because we dont insert the LTE board yet. In Technologies do can Huaweiphase 2 we Co., Ltd. the HUAWEI Confidential HUAWEI TECHNOLOGIES connection

LTE BMPT WIAMX BMPT

RRU-BBU Connection 1/2


1) Total RRUs = 6 [3 for Wimax, 3 for LTE ] 2) Total CPRIs required = 9 [3 for Wimax , 6 for LTE ] which means each WiMAX RRU will use only 1 CPRI and each LTE RRU will use 2 CPRIs. 3) For Project Phase 1 [Wimax 30MHZ] RRU CPRI connection will be as follows: Phase-1 Wimax Wimax Wimax LTE LTE LTE WiMAX RRU Sector 0 : no connection [Wimax 30 Sector Sector Sector Sector Sector Sector MHZ] 0 1 2 0 1 2 WiMAX RRU Sector 1 : no connection BBBI CPRI 0 X X X Yes X X WiMAX RRU Sector 2 : Connection BBBI CPRI 1 X X X X Yes X LTE RRU Sector 0 : Connection [CPRI 0 only] BBBI CPRI 2 X X Yes X X X LTE RRU Sector 1 : Connection [CPRI 0 only] BBU Slot 3 LTE RRU Sector 2 : no Connection 4) For Project Phase 2 [Wimax 10MHZ, LTE 20 MHZ] WiMAX RRU Sector 0 : Connection WiMAX RRU Sector 1 : Connection WiMAX RRU: WiMAX RRU Sector 2 : Connection 2614MHz~2624MHz LTE RRU Sector 0 : Connection TD-LTE RRU: LTE RRU Sector 1 : Connection 2582MHz~2602MHz LTE RRU Sector 2 : Connection

Page 70

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

RRU-BBU Connection 2/2


From LTE CPRI_0From LTE CPRI_1 From WiMAX CPRI_0

Please put the remaining cable under BBU rack orderly!

Page 71

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

RRU-BBU Connection Phase-1[Wimax 30MHz]

Page 72

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

RRU-BBU Connection Final

Page 73

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Optical Cables CPRI color coding


LTE CPRI fiber sector1(0,1) sector 2(0,1) sector 3(0,1) CPRI_1 CPRI_0 1 0 WiMAX CPRI fiber sector1, sector 2, sector 3

Page 74

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Connect the TX cable to MW IDU


WiMAX BMPT Board:

Nera MW IDU:

Note :The reserved IDU port will be finalized after confirm with Mobily Huawei MW IDU Service Board:

Optical-Port

ETH-Port

Page 75

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Inserting LTE boards to BBU

Page 76

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Changing Cable Connection for LTE


Original connection:

Target connection:

LTE CPRI_0 LTE CPRI_1

Page 77

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

3 May 2011

Thank You