Vous êtes sur la page 1sur 17

STANDARD TECHNICAL SPECIFICATIONS FOR ELECTRIC WORKS

GENERAL REQUIREMENTS
( SPECIFICATION )

CIVIL DESIGN FUNDAMENTALS

ADDC/AADC STANDARD : S-AA-GEN-CDF (REV.0-2009)

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 1 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

CONTENTS STANDARD TECHNICAL SPECIFICATIONS FOR ELECTRIC WORKS...........................1 1 2 3 4 4.1 4.1.1 4.2 4.3 4.4 5 5.1 5.2 5.3 6 6.1 6.2 6.3 6.4 6.5 6.6 7 8 9 INTRODUCTION .......................................................................................................3 STANDARDS CODES AND REFERENCES FOR CIVIL WORK..........................3 MATERIALS...............................................................................................................5 GENERAL DESIGN GUIDELINES ..........................................................................6 Substations above 11 kV................................................................................................6 HSE Requirements ........................................................................................................9 Substations 22 kV and below .........................................................................................9 Distribution Lines........................................................................................................10 Underground Cables ....................................................................................................10 DESIGN CRITERIA.................................................................................................11 Substations ..................................................................................................................11 Distribution Lines........................................................................................................12 Underground Cables ....................................................................................................13 LOAD AND DESIGN ASSUMPTIONS ...................................................................14 General Assumptions...................................................................................................14 Seismic Load...............................................................................................................14 Crane load ...................................................................................................................14 Wind Load ..................................................................................................................15 Increase in Soil Bearing Capacity/ Pile Capacity..........................................................15 Under-Ground Water Retaining Structures...................................................................16 PARTICULAR SPACE REQUIREMENTS ............................................................16 ROADS, PAVEMENTS AND PARKING AREAS ..................................................16 BOUNDARY WALLS & PERIMETER FENCING ................................................16

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 2 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

CIVIL WORKS FUNDAMENTALS


The general information given hereunder applies to all civil works in addition to the General Design Fundamentals, and unless specified in greater detail in sections on special conditions or specific installations. 1 INTRODUCTION

The civil works are governed by the conditions of the electromechanical part, and as far as they are not supplemented by data, by the conditions or specifications stipulated hereafter. However, any local laws and regulations shall prevail, such as the "Abu Dhabi Municipality Building Regulation and Guide Lines for Structural Design (1994)". Detailed execution features of the civil work are described in the relevant sections of the Specifications. This document shall represent the basic specification and information for calculating the lump sum price of the works concerned, but they should not be considered to be a complete description in every respect. Tender drawings indicate the intended layout of the works, but are not to be taken as a complete and dimensional reference. The price offered shall be understood as the total sum for the complete civil and finishing works to suit the requirements and the functions of the Works concerned. Design and choice of construction materials shall consider and ensure the reduction of future maintenance works, and therefore, all civil elements shall be designed to minimise maintenance and to result in a durable construction with a minimum design life of 40 years. The Bidder/Contractor shall prepare all necessary design and detail drawings in accordance with the Project requirements. However, the following guidelines design criteria shall be strictly followed and applied in view of the proposed equipment, and are having priority over the Tender drawing details. 2 STANDARDS CODES AND REFERENCES FOR CIVIL WORK

Except where otherwise stipulated, all civil works materials, tests of works, investigations on Site, installation and construction methods, and also manufacturing procedures shall comply as a minimum with the following codes and standards:

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 3 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

EUROCODE

CEN European Committee for Standardisation Central Secretariat Rue de Stassart 36 B - 1050 Brussels Belgium Deutsches Informationszentrum fr Technische Regeln (DITR) in DIN Deutsches Institut fr Normung e.V. Burggrafenstr. 4 10 10787 Berlin Tel. +49 (0)30 2601-0 / Fax 2601-1260 American Concrete Institute P.O. Box 4754, Redford Station Detroit, Michigan 28219, U.S.A. American Society of Testing Materials 1916 Race Street, Philadelphia Pennsylvania 19103, U.S.A. American Institute of Steel Construction 101 Park Avenue, New York N.Y. 10017, U.S.A.
American Society of Heating, Refrigeration and Air-conditioning Engineers Inc. 1791 Tullie Circle, N.E., Atlanta, GA 30329 USA

DIN

ACI

ASTM

AISC

ASHRAE

Phone: (404)636-8400, ASHTO

Fax: (404)321-5478

American Association of State Highway and Transportation Officials, 444 North Capitol Street, Suite 249, Washington, D.C. 20001, USA, Tel: +1 202 624-5800 National Fire Protection Agency 1 Batterymarch Park P. O. Box 9101, Quincy, Massachusetts, USA Tel: +1 617 770-3000, Fax: +1 617 770-0700 British Standard Construction Industry Research and Information Association Abu Dhabi Municipality Building Regulation and Guide Lines for

NFPA

BS CIRIA Abu Dhabi

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 4 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

Municipality

Structural Design (1994)

The Bidder/Contractor shall clearly identify in his offer which of the acceptable Standards shall be applied during design and execution for each part of his works. Standards for one type of materials shall be of the same grouping, i.e. only BS, DIN or ASTM. Only if the selected group of Standards does not offer guidelines for specific parts of design or execution, alternative standards may be proposed. The Bidder/Contractor shall ensure that the design and execution of civil works adheres at least to the minimum requirements based on BS. Execution of concrete works shall normally either follow BS or DIN Standards. All concrete works shall further be executed in line with the CIRIA publication Guide to the construction of reinforced concrete in the Arabian Peninsular. Structural Steel works shall normally be designed and executed according to EUROCODES 3 and 4. Other Standards may only be applied after explicit approval through ADDC/AADC. The Bidder/Contractor shall provide all required drawings for Town Planning Department, Civil Defence, ADDC/AADC, Municipality and other Authorities, which are mandatory to obtain required (building) permits. In addition to the basic tendered design to be offered, the Bidder/Contractor may propose alternative type(s) of building and structures to be applied within the Project. It is the Bidders/Contractors obligation to carry out complete Geotechnical Investigations to determine all relevant soil conditions and parameters required for a sound and durable structural design, including the bearing capacity of the ground to determine type and size of foundations and to determine the chemical soil and groundwater aggressiveness. 3 MATERIALS

All materials proposed and their colours selected to be used within the Project shall be subject to ADDC/AADCs approval and shall comply with the Technical Specification and the defined Standards. Application of materials shall be in line with this Specification, but Manufacturers specific instructions for the use and application of his material shall be complied with. All work shall be executed by skilled workers in a workmanlike manner. Prior to the start of execution the Bidder/Contractor shall verify that all conditions are suitable for the timely and effective carrying out of his work. Specified or requested testing of material shall only be carried out by a licensed office or institute or an approved laboratory, conforming to accepted standards in accordance with the technical data and approved by ADDC/AADC. Selection of samples for testing shall be made by ADDC/AADC at Site.

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 5 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

For site testing of fresh concrete, at least equipment equivalent to "Set B" of "Der Deutsche Beton Verein e.V." shall be provided and used. If no approved laboratory for the further testing of concrete materials is available, equipment equivalent to that listed as "Set C or Set D" of "Der Deutsche Beton Verein e.V." shall be provided in addition. 4 4.1 1. GENERAL DESIGN GUIDELINES Substations above 11 kV Substations shall normally be designed as concrete skeleton structures. Walls shall be made of insulated block/brick work or concrete panels of adequate insulation. The roof shall normally be designed as flat concrete roof. Foundations shall be designed according to the findings of the soil investigations and shall consider the requirements of the buildings. In weak soils, pile foundations have to be considered. Ground improvement, such as vibro compaction, vibro soil replacement, stone columns, etc., may be proposed for ADDC/AADCs approval. Cable basements shall be considered under all 11 kV, 22 kV, 33 kV switchgear rooms. Raised modular flooring shall at least be foreseen for Control-, Protection-, LDC- & PLC-, Charger -, Telephone - & LV Station Supply Rooms. The station design shall provide adequate provisions for offices, kitchen, toilets and storage facilities, as further detailed within the scope of works. A comprehensive HVAC System shall be provided for station. Station ground level are to be defined according to local laws or to ADDC/AADC's instructions, and unless specified otherwise. The minimum Station level shall be 50 cm above any adjacent (within 250 m) asphalt road. Finish floor level (F.F.L) shall not be less than 50 cm above external ground (station) level. In general, the underside of basement slabs should not be deeper than 2.0 m below final ground (station) level, and should normally also be at least 30 cm above the highest ground water level. Minimum free height (clearance) of basements is to be 2.2 m in traffic areas/escape routes after completion of all installations. An adequate number of doors/emergency exits to comply with means of egress requirements and sufficient loading spaces have to be provided. Switchgear, Control and Auxiliary room walls not bordering transformer bays are to be provided with glass blocks for daylight illumination. Fire rating of the glass blocks panels shall be in accordance with the local regulations or NFPA, at least, however, 90 minutes. Installation of double glazed windows shall be limited to offices, kitchens and toilets.
Page 6 of 17

2.

3. 4. 5. 6. 7.

8. 9.

10. 11. 12.

13.

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

GENERAL REQUIREMENTS Civil Design Fundamentals

14.

All basements/cellars and cable trenches to be executed with at least 1% slope towards drainage points or pump sumps, which shall be provided for each section or at least at both ends of the trench or basement. Concrete roof slabs shall be provided with sufficient slopes (minimum 2 %), and proposals for diagonal roof slopes of (1% towards rain water outlets) made by lean concrete may be provided. Diagonal slopes of 1% are not required if a provision of gutter is adopted in the design. Normally a recessed/flush installation shall be foreseen for all cabinets and panels, e.g. for indoor fire hose reels, breathing apparatus, fire extinguishers, annunciator/repeater panels, CO2 lock off units, alarm/detection equipment, etc. A minimum slope of 1% and Floor Drains/Pits shall be provided in all rooms /areas, where surface water may occur, e.g. the H.V.A.C. Plant Room, Fire Pump Room, Battery Rooms, trenches, bathrooms, kitchens, and Insulator Washing Equipment Room, etc.. SWG/SVC-hall floors and the transformer/shunt reactor basements shall have rigid foundations to minimise differential settlements. If separate basements are provided, the Bidder/Contractor shall provide proof for the maximum settlements, and shall provide sufficiently sized compensators in the Switchgear (GIS). Reference is made to the GIS specification. External block walls, roofs, aluminium or metal clad walls and roofs, as well as all doors and windows of all building shall provide adequate thermal insulation and shall be approved by ADDC/AADC. The thermal transmission coefficient U of walls, including all windows and doors, shall be equal to or less than 1.2 W/(m2 *K). Distances and room partitions shall be designed according to the specified fire protection standards. The design layout shall follow the requirements of preventive measures as outlined in the relevant sections. Unless local regulation require differently, all fire rated doors shall be designed in accordance with NFPA, and all reinforced concrete structure members (slabs, beams, frames, columns, etc) shall be designed in accordance with DIN V 18230, DIN 4102, or NFPA 220 type 1, table 3, and to withstand at least the below listed fire ratings: Structure/concrete External walls Internal fire barrier wall Glass blocks Fire rated steel doors Fire rating 90 min. 180 min. 120 min. 120 min. 90 min.

15.

16.

17.

18.

19.

20.

21.

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 7 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

Integrity/stability of insulation/core Raised floor 22.

20 min. 30 min.

Transformer foundations shall be designed as a solid block foundation (not separate beams/walls) and reinforced properly for all straining action including the effects during casting and service life of the transformer. Transformer bays/shunt reactor shall be designed and executed - in view of fire protection and the required oil and water collection capacity - as follows: Double walls shall be used between transformer bays and building walls, whereby both walls shall be designed as fire separation Each transformer bay shall be enclosed by reinforced concrete fire protection walls on three sides. All walls shall be at least 0.5 m higher than the highest transformer part (e.g. top of tank). Design of the Bays, the Fire Walls, the Oil Tanks and the Fire Fighting equipment shall meet NFPA and local regulations The capacity of the oil collection area incorporated in the foundation has to be designed according to the oil capacity of the transformer as well as the maximum expected fire fighting water If specified and approved, joint oil/water separator tanks may be provided for groups of transformer foundations. Reference is made to below listed sample drawing, which is provided in the Drawings Section.
Drawing No. Title DWG AA GEN 01 01 Typical Oil Separator

23.

If specified, transformer bays shall be covered by a light-weight roof construction over the full bay ensuring shading, but not obstructing necessary ventilation and air circulation. Costs for this construction must be clearly indicated in the BOQ/PTS. 24. Access to transformer bays shall be through lattice steel fences and doors/gates, with a maximum spacing of the lattice steel works of 7.5 cm. Fence, doors and frames shall be hot dip galvanised after manufacture and welding, and shall be coated (corrosion protected) as per the General Specifications Part : S-AA-CORR - Corrosion Protection and Painting Color Codes

Alternatively, such gates and fences may be constructed utilising powder coated aluminium sections and profiles. 25. Each substation has to be equipped with fire alarm and fire fighting systems, which meet NFPA regulations.

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 8 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

26.

Wherever the soil investigation indicate a groundwater table within one (1) meter below the lowest slab level, all reinforced concrete structures below ground level (e.g. basement slabs & wall, trenches, etc.) shall be designed as water retaining structure in accordance with BS 8007 and BS 8110. For substations within the City of Abu Dhabi, the ground water level shall generally be considered at the finish ground level. Cable trenches shall be designed and provided for the foreseen future extension of the Station (including consideration of all MV, LV, HVAC, F/F. and control cables). All cable recesses and openings to be provided for foreseen future extension (including MV, LV and control cables) shall be made watertight and fire protected by an approved method. Provisional recesses and openings in floors of Switchgear, Control and Relay Rooms and prepared for the foreseen future extension of the Station shall be covered by heavy duty chequered plates, fire protected and if required thermally insulated. Foundation and floor slab reinforcement shall have projecting galvanised earthing flags to enable connection to the earthing grid of the Station. All substation metalwork including transformer tank, cable screens, feeder pillar, doors and any internal structural steel work shall be securely bonded together so that a firm metallic connection existing between each of them and the substation earthing terminal. External earth points as per requirement for equipment and system earthing shall also be arranged to keep earth resistance to less than two ohms. A/C unit mounted on roof / top roof shall be surrounded by screen walls ( i.e. clustra block, GRP, aluminium sections). External/internal stair to roof/top roof to be provided. HSE Requirements

27. 28.

29.

30. 31.

32. 33. 34. 4.1.1

Specifying emergency response equipment for substation buildings such as, but not limited to: A. B. C. D. Breathing Apparatus First Aid Kits Spillage Control Kits/Products Fire Fighting Equipment, etc.

is a relative phenomenon depending upon the configuration of the substation building. The type/nature of equipment used in the building, the normal/average occupancy of the building, location of the building, etc.

4.2

Substations 22 kV and below

This section refers to additional, deviating specific civil works requirements related to the construction of Substations of the voltage level 22 kV and below.

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 9 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

1. 2.

For the buildings, preference will be given to a standardised pre-fabricated scheme, ensuring fast completion and maintaining the required high quality of works. It may be noted that experience has proven that in the past in most cases, a bearing capacity of 50 kN/m2 could in the past be assumed in Abu Dhabi, and 100 kN/m2 in Al Ain. For not air-conditioned stations, lattice steel doors ensuring adequate ventilation, shall be provided. The minimum door opening shall be 3.0 m x 2.3 m. For air-conditioned stations, doors for Switchgear rooms shall be double leaf, insulated steel doors. Thermal insulation of all walls, roofs, doors, glass blocks, etc. shall be adequately designed and shall be approved by ADDC/AADC. The thermal transmission coefficient U of walls, including all windows and doors, shall be equal to or less than 1.2 W/(m2 *K). All cables, ducts and conduits entering the Station shall normally be routed horizontally and below ground level, Adequate provision shall be made to seal the cable entries against ingress of water and to prevent animals, etc. from entering. A/C unit mounted on roof / top roof shall be surrounded by screen walls ( i.e. clustra block, GRP, aluminium sections). External/internal stair to roof/top roof to be provided. Distribution Lines OHTL Tower foundations shall normally be designed as single-leg foundation, i.e. one foundation per tower leg. OHTL foundations shall reach at least (50-75) cm above the final ground level at the tower location site. If required, pile foundations shall be provided with permanent casings wherever the ground down to the bearing strata is highly aggressive or cannot support the newly cast pile. Whenever required for the execution of the works, access roads shall be provided by the Bidder/Contractor. Maintenance access roads may be ordered by ADDC/AADC along sections of the line. Underground Cables

3. 4. 5.

6.

7. 8. 4.3 1. 2. 3. 4. 5. 4.4

Civil works shall be carried out in line with the General Specifications Part and shall be subject to approval by ADDC/AADC.

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 10 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

DESIGN CRITERIA

Following fundamental design criteria shall be strictly followed and applied in view of the proposed equipment, and are having priority over the Tender drawing details and dimensions. 5.1 1. Substations Design Criteria to be submitted shall include a description of the following: Soil investigations Codes and standards to be adopted in the design Loading to be adopted for the various elements of the structure Load factors and load combinations Description of the design method and theories to be adopted. 2. 3. Architectural scheme design Base calculation of the structural design and general arrangement drawings shall include the principle framing and loading calculations, as well as the information concerning the expected forces in the relevant elements of the structure. Architectural detail drawings (for Substations only) covering the electrical equipment requirements shall be co-ordinated with Mechanical, Electrical and Plumbing (MEP) drawings and shall include the following: Plans, elevations and sections detailed enough to enable construction without difficulties Stair case details Roofing and water proofing detail Doors and windows schedules Finishing schedules. 5. Structural detail drawings shall include the following: Detailed structural calculations for the analysis and the design of all members and the full structure General notes and typical detail drawings that are applicable the majority of works. Reference shall be made to the below listed sample drawing, which is provided in the Drawings Section.
Drawing No. DWG AA CIV 00 01 Title General Notes

4.

Load drawings, showing all dead, equipment and live loads, including line loads from walls
S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc Page 11 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

Reinforcement details, bar bending schedules, following ACI simplified methods for detailing, except where seismic/ductile connections are required Concrete protection details Structural steel details of all members, their welds and other connections Coatings and corrosion protection details Detailed lists of steel structure members, plates, bolts Details of sheet metals and claddings for walls and roofs, etc. Details of walls, stairs and other members Formwork drawings/calculations shall be submitted for information. The design procedure for the project shall be as described above, but not necessary limited to the above and shall be approved by ADDC/AADC before proceeding. 5.2 1. Distribution Lines Design criteria to be submitted shall include a description of the following: Soil investigations Codes and standards to be adopted in the design Loading to be adopted for the foundations based on the approved Tower design Load factors/load combinations for foundation and stub angle design Description of the design method and theories to be adopted Foundation tests to be applied and their details. 2. Base calculation of the foundation design and general arrangement drawings shall include the principle loading calculations resulting from the tower design, as well as the information concerning the expected forces in the relevant foundation. Foundation forces along the slope of the tower leg and in the global axes shall be provided in a table format for all types of towers and their extensions. 3. Structural details shall include the following: Detailed structural calculations of all members of the foundation showing that the ultimate earth bearing capacity is not exceeded by the maximum pressure due to loads, acting on the tower, multiplied with the corresponding safety factor, and due to the dead weight of the tower and foundation Prove that the uplift forces on the foundation do not exceed the weight of the fictive anchor body in the soil, assumed to be in the shape of an inverted pyramid/cone starting 25 cm above the toe of the pile. Alternative, methods of design can be adopted subject to ADDC/AADC approval

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 12 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

Calculations and drawings showing the bearing capacity and stresses at each critical section of the concrete and the steel reinforcement Type of foundation selected for each tower location Reinforcement details, bar bending schedules Concrete protection details Structural steel details of stubs and cleats Detailed lists of steel structure members, plates, bolts, etc. for the stubs Coatings and corrosion protection details for the stubs. The design procedure for the project shall be as described above, but not necessary limited to the above and shall be approved by ADDC/AADC before proceeding. 5.3 1. Underground Cables Design criteria to be submitted shall include a description of the following: Soil investigations Codes and standards to be adopted in the design Loading to be adopted for structure Load factors and load combinations Description of the design method and theories to be adopted. 2. Structural details shall include the following: Detailed structural calculations of all members and structures Type of foundation to be applied Reinforcement details, bar bending schedules, prepared in line with ACI simplified methods for detailing, except where seismic/ductile connections are required. These have to be elaborated and presented in more detail. Concrete protection details Structural steel details of all elements Detailed lists of structural steel elements, welds, plates, bolts, and other connections Coatings and corrosion protection details The design procedure for the project shall be as described above, but not necessary limited to the above and shall be approved by ADDC/AADC before proceeding.

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 13 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

6 6.1

LOAD AND DESIGN ASSUMPTIONS General Assumptions

Further to the data given in the Section on General Design Fundamentals, the minimum requirements for loads to be applied for the static analysis of both sub-and superstructure works shall be as follows, whereby equipment and installation loads always shall be considered additionally: 6.2 Live load for building roofs (A/C equipment and foundations to be considered additionally) Battery rooms, stores Control Rooms Switchgear Rooms Offices Kitchens, corridors, staircases, etc. Plant Rooms Additional dead load for suspended ceiling, pipes, AC system, etc Roads and pavements, gutters Water tanks, septic tanks, etc. in road areas Seismic Load 1.5 10.0 5.0 10.0 5.0 5.0 10.0 1.0 kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m
2

2 2 2 2 2 2 2

SLW 60, DIN 1072 SLW 60, DIN 1072

Static analysis shall be carried out for seismic loads calculated as static shear forces based on seismic coefficient of 0.075 in accordance with Zone 1 of Uniform Building Code (latest Version). The Seismic Importance Factor shall be considered as 1.0. All other parameters must be determined in accordance with UBC and highlighted in design criteria. Structural analysis and design shall be started after approval of such parameters. The buildings and structures shall meet the serviceability requirements of UBC. 6.3 Crane load

Vertical load will be considered for a maximum approach of crane hook towards the building columns. An impact factor of 25% of wheel load shall be considered for design of crane girder. Longitudinal surge forces parallel to the crane runaway girder shall be 5% of wheel load shared equally on both sides.

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 14 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

Lateral surge force (perpendicular to crane runaway girder) shall be 10% of lifted weight + trolley weight. 6.4 Wind Load

Wind loads shall be calculated in line with BS-6399 Part-2. The maximum wind speed shall be taken from the specification as defined under S-AA-GEN-GDF - General Requirements: General Design Fundamentals

The site wind speed (Vs, as defined in BS-6399- Part2) shall be taken equal to the maximum wind speed as mentioned above. Other parameters shall be considered in line with above mentioned standard for calculation of Effective Wind Speed and Wind Pressure. Load Combinations Following basic load combinations shall be considered in the analysis of framed structures for buildings:
a) b) c) d) e) f) g) DL + LL + EL DL+ LL+ EL+ CL.( Working condition)
DL+ 50%LL+ EL SL.x/z+ CL. (50% lift capacity + self weight of crane)

Any bay may have crane.

DL + EL SL x/z
DL+ 50%LL+ EL + WL.x/z + CL. (50% lift capacity + self weight of crane)

Any bay may have crane.

DL WL.x/z DL + EL WL.x/z DL LL EL SL.x/z WL.x/z CL = = = = = = Dead Load Live Load Equipment Load Seismic load in X or Z direction Wind Load in X or Z direction Crane Load

For the design of buildings with crane, the longitudinal frame shall suitably consider surge loads in longitudinal direction, from crane. 6.5 Increase in Soil Bearing Capacity/ Pile Capacity

For load combinations with wind and seismic loads, soil bearing capacity can be increased by 25% over the values mentioned in the Soil investigation report. For load combinations with wind and seismic loads, pile capacity can be increased by 25% as per pile design.

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 15 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

6.6

Under-Ground Water Retaining Structures

Water retaining structures below ground shall be analysed considering earth outside with ground water up to the maximum assumed level, but no water inside. Additionally, a surcharge load of 2000 kg/m2 shall be considered for structures located very near to roads, or else a surcharge load of 1000 kg/m2 shall be considered. In case the structure has compartments, the structure must be analysed for the condition that water is present in one compartment only. Earth pressure for under ground structures will be calculated using coefficient of active earth pressure (Ka) or earth pressure at rest (K0) depending on boundary condition. Reinforced concrete members shall be designed with a crack width not more than 0.2 mm in accordance with BS 8007. 7 PARTICULAR SPACE REQUIREMENTS

Dimension of Switchgear rooms, and control rooms shall be determined under full consideration of the equipment requirements and listed in the relevant part of the Specification. Pipes, lighting installations, air conditioning ducts and glass block panels have to be located in a way that sufficient (shadow-free) lighting is provided after completion of all installations. 8 ROADS, PAVEMENTS AND PARKING AREAS

Roads within the substation limit shall be either concrete or asphalt roads of at least 6.0 m width with kerbstones on both sides. Around all buildings, curb-stones and walkways in interlocking tiles shall be provided. Road radii in relation to the outer curb shall not be less than 21.00 m. sufficient slopes for surface water drainage of all paved areas shall be provided. For paved and marked parking areas, suitable passage and kerbstone shall be arranged with at least 1.00 m distance to the nearest building. The construction of an asphalt access road from the end of internal roads inside the station boundary to the nearest external road and as detailed in the scope of works shall be included in the scope of works, unless explicitly stated otherwise in the scope of work. Road widths here shall be at least 7.5 m. The road section shall be as per Municipality/Town Planning approval, with kerbstones, shoulders and/or 1.5 m wide walkways on both sides. The roads are to be designed for loads of SLW 60 (DIN 1072). 9 BOUNDARY WALLS & PERIMETER FENCING

Where specified, Boundary Walls shall be arranged at the perimeter of the plot. The boundary walls shall be at least of 2.75 m high, and made of pre-fabricated concrete panels of approximately four (4) meter length painted from both sides . At the top of the boundary wall, 100 mm height of spikes option shall be fixed of metal strip encased/fixed on top the panel. Boundary walls shall normally be arranged at a distance of not less than 1.5 m from the plot limits unless specified differently in the scope of works.

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 16 of 17

GENERAL REQUIREMENTS Civil Design Fundamentals

On filled plots (or plots to be filled) the boundary wall shall keep a distance of at least 3 m from the edge of fill, where it has reached the final fill level. Alternatively, ADDC/AADC may specify security fencing around the plot. Such fence shall be at least 3.00 m high chain link or if approved or specified within the scope of works - mesh fence, with additional arms for four strands of barbed wire at the top. The bottom of the fence mesh shall be encased in a ground beam. For every plot, at least two entrance gates have to be arranged within the boundary wall or security perimeter fence. Each gate shall be a double winged road gate of at least 6.0 m clear opening, with a separate pedestrian gate of 1.2 m width each. Transportation requirements for the equipment may require larger openings and have to be considered. Boundary wall shall be provided with external type of light fitting For details, reference shall be made to the below listed drawing and specifications, provided in the Civil Drawings Section:
Drawing No. DWG AA CIV 13-03 Specification S-AA-CIVIL-FENCE Title Details of Pre-Cast Boundary Wall Title Security Fencing

S-AA-GEN-CDF (Civ Design Fundamental) (Rev.0-2009).doc

Page 17 of 17

Vous aimerez peut-être aussi