CONTRACTOR'S CLAIM PROCESS UNDER ITB VOL. I OF 3, CLAUSE 1.

21

42 days

28 days
Contractor gives notice to the Owner describing the event or circumstance giving rise to the claim *

42 days
Contractor submits fullydetailed claim with supporting details & EOT and/or additional payment claim Owner shall respond with approval or disapproval & detailed comments

Contractor becomes aware of item to claim

NOTE:

- If the contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment, and the Owner shall be discharged from all liability in connection with the claim (ITB Vol.1 of 3, SubClause 1.21.1, 2nd paragraph).