Académique Documents
Professionnel Documents
Culture Documents
Objectives
AQP Process SAQE Responsibilities Construction Of SAQP Workbook Update & Review Procedure
X
Concept SAQE Responsibility 0 Defects ? Product / Process Maturity
PPA P
APQ
Contents Page
01 Design Records 02 Engineering Change Documents 03 Customer Engineering Approval 04 Design FMEA 05 Process Flow Diagrams 06 Process FMEA 07 Control Plan 08 Measurement System Studies 09 Dimensional Results 10 Material & Performance Test 11 Initial Process Studies 12 Qualified Laboratory Documents 13 Appearance Approval 14 Sample Product 15 Master Sample 16 Checking Aids 17 Customer Specific 18 Part Submission Warrant
PPA P
1 2 3 4 5 6 7 8 9 10 11 12 13
SSOW (supplier statement of work) / DSKO (directed supplier kick off) LON (letter of Nomination) AQP kick-off meeting & contacts list Drawing & specification review & quality objectives DVP&R (design verification plan & report) Team feasibility commitment Capacity plan Design FMEA (failure mode & effects analysis) Tool & equipment design & feasibility Gauge design & feasibility Tooling kick-off & purchase order cover Pre-production build plan & purchase order cover Process flow chart & manufacturing floor plan Process FMEA Control plan & control plan special characteristics Pre-launch containment plan Subcontractor PPAP status Packaging specifications & shipping plan 1st Off Tool Parts & dim report Drawing Release for PPAP (Design Freeze) IMDS data base acceptance Production trial run Gauge functionality, certification, & R&R (reliability and repeatability) Process capability study & Status Dimensional Report AAR (appearance approval report) Material certification Product Validation Testing SPSO (supplier process sign-off) - Capacity Verification PPAP Interim PPAP submission approval & master samples
APQ
14
15 16 17 18 19 20 21 22 23 24 25
26 27 28 29 30 31
It is not the Intention of the workbook to be the method to communicate issues to the SDT
SDT Review
Target
To ensure that the supplier has the correct information to develop the product to achieve cost and quality objectives over the product life.
What to Keep
Meeting minutes DSKO Sample of SSOW Sample of the Letter of Nomination
Note The SSOW must be signed by both Supplier and JCA at beginning of project, and failure to comply must be a RED issue.
Target
Workbook is updated with planned dates for each element and these remain fixed target for the duration of the project.
Supplier Development APQP 4. Drawing & specification review & quality objectives
A team review to facilitate a thorough understanding of the product material and performance specifications is necessary. A comprehensive review helps the team identity the functional, durability and appearance requirements of the component and/or assembly. The product characteristics and process parameters required to effect or control the functional, durability, and appearance requirements are to be determined by the supplier.
Target
Supplier understands design completely and potential control characteristics are identified. Potential improvements and cost reduction opportunities are identified Agreement of all special characteristics
Target
All design defined material and functional tests are compliant
The DVP&R is a summary of all development testing required to ensure the product conforms to defined customer needs and requirements. Testing results are incorporated into the document as they become available.
What to Keep
DVP Report FER_DVP
Target
Supplier agrees requirements can be manufactured to required quality in serial conditions to the planned volume All Important characteristics to be measured and monitored appropriately
What to Keep
Feasibility report FER_Feasibility
Note
Feasibility confirmation is needed after each engineering change
Target
To ensure that the supplier has the capacity to produce product at the quoted values + 20% peak volume
What to Keep
1.A 1.B Master Capacity Plan OEE data sheet
Target
Unless the supplier is design responsible. The salient points from the customer DFMEA affecting customer satisfaction are available.
! What to Keep
Where possible a copy of the DFMEA should be retained, minimum is copy of the FER_DFMEA
Note - Safety
All CC identified in DFMEA must be included in Drawing.
Target
Tooling manufactured is designed to produce expected quality parts for product life.
Target
The gauges and fixtures used to determine quality, should be available for 1st off tool parts. SC & CC should be measurable from the gauges and used in the capability studies.
What to Keep
Gauge plan
Note
All SC & CC must be gauged preferably with variable result. Ongoing SPC should be done off gauge.
Target
To ensure the tooling Is kicked off in time to achieve time plans
What to Keep
No specific document is used but a matrix of all tooling and equipment with completion dates would be required. Tool Tracker
Target
Supplier has a plan to manufacture parts for key build dates and understands delivery requirements. Purchase orders are in place to cover all pre series and testing parts
A plan of the pre-production build requirements, including parts for testing must be communicated. Purchase order for the parts should have been issued. The project buyer should maintain a list of PO cover
What to Keep
No specific document defined,
Target
To establish the manufacturing route plan and the movement and storage that could have impact on quality and delivery. This forms the structure to develop the PFMEA
What to Keep
Process Flow Chart Sample Floor plan FER_MPFC
! Note Safety
Any part of process that has implications on safety should be clearly identified. ie. Welding Parameters Material Hardening or Conditioning
Target
A formal review of all current quality issues on similar products should be documented and aligned with review of new product. This should be reviewed with the known quality outputs from similar products in production and the lessons learned from them must be completed and
What to Keep
PFMEA FER_PFMEA
! Note - Safety
All processes that effect product safety should be given special attention for control and . Welding Hardening Surface Treatment
Target
In conjunction with the PFMEA all the key RPN issues have controls applied to ensure the failure does not appear in production. This includes all measurement equipment and frequency of checks likely to detect failure.
Target
0 defects during pre-launch period
! What to Keep
Measurement reports Inspection reports
Note
Special Attention is needed for all Welding and heat treatment processes
Target
All parts using in supplied assembly are validated to the same level as the supplied part
! What to Keep
Matrix of all sub-component PPAP Status
Note
All SC & CC, Surface treatment, Heat treatment, welding or conditioning must be traceable through sub component approval.
Target
An agreed method of packaging to ensure all products are received in perfect condition
Supplier Development APQP 19. 1st Off Tool parts & Dim report,
Once tooling is completed it is key to ensure the tooling or equipment can produce a correct part, the manufacturer must provide data to confirm the part produced from the tooling is dimensionally correct before delivery.
Target
To ensure tool or process manufactures a part to the drawing at the earliest opportunity.
What to Keep
Dimensional report
Note
The dimensional report can be from CMM against CAD for this element
Target
The drawing released must be compatible for the part being PPAPd. No changes to the design are acceptable from this point unless with specific demand from Customer with declared timing implications Or Changes are needed to correct functionality.
What to Keep
Copy of drawing to be included in PPAP Feasibility form
Note
Any changes not agreed in the PPAP release cannot be implemented until 90 days after Job 1
Target
To ensure that the component data is accepted by JCA in the data base. The IMDS registration number is recorded on the PSW The Number should also be Recorded on the Workbook in the comments for that element
What to Keep
Copy of IMDS acceptance report Sample screen shot
Note
The element is only complete when the part is accepted on the data base
Target
Process runs under serial production conditions to approved control plan
What to Keep
R&R Study results
Note
ALL gauges should be measured using R&R including attribute gauges
Target
Validation that each of the SC & CC applied to dimensions is capable of achieving its intended tolerance for product life
! What to Keep
Control chart (Analysed for special causes) Histograms for distribution List of all SC and Cpk PIPC (from CRT agreement)
Note
SPC is a long term process and needs to be continued on key characteristics
Target
To confirm that the produced part conforms to the drawing. 6 parts are measured and the master samples should be taken from these. Remaining parts to be available for testing.
What to Keep
Dimensional report Material Test report
Note
The dimensional results for all 6 parts must be recorded separately
Target
Customer approval of all defined surface parts for PPAP submission
What to Keep
AAR Sample
Note
Each part and colour should be measured and the values on AAR must be within design tolerances or Master plaque whichever is agreed
Target
Validation that the material used performs to the expectation of the design
Target
Component passes all test capability and dimensional requirements Process achieves all throughput and delivery requirements
What to Keep
Records of compliance not retained in PPAP
Target
Validate the process can produce 0 defect production and planned production speed . All checking and control documentation is in place and operators are trained.
Target
The target should always be to not need Interim PPAP but if there is no alternative, then a mechanism must be introduced to ensure that the issues are followed up and full PPAP introduced.
Supplier Development APQP 31. PPAP Submission Approval & Master Samples
PPAP is developed to AIAG 4th Edition PPAPs purpose continues to be to provide the evidence that all customer engineering design record and specification requirements are properly understood by the organization and that the manufacturing process has the potential to produce product consistently meeting these requirements during an actual production run at the quoted production rate.
Target
The purpose of PPAP is to determine if all customer engineering design record and specification requirements are properly understood by the organization and that the manufacturing process has the potential to produce product consistently meeting these requirements during an actual production run at the quoted production rate.
Task 1
From the provided documents create an AQP folder
Task 2 Create a SAQP Workbook from the folder and set status and comments for each element