Académique Documents
Professionnel Documents
Culture Documents
FEATURES
PEER-REVIEWED PAPERS
MANAGEMENT IN ENGINEERING
NOVEMBER/DECEMBER 1995 VOLUME 11 NUMBER 6
FEATURES
THINK VALUE ENGINEERING Depending on how it is exe-
cuted, value engineering has the potential to be the first
step to success—or disaster.
By Prakash Acharya, Charles Pfrommer
and Charles Zirbel ............................................................13
'
DON T BURN THAT BRIDGE! Team effort by all parties
to a contract—owner, architect, construction manager,
PEER-REVIEWED PAPERS
contractor and subcontractors—is a crucial ingredient for
the successful completion of a project. MEASURING EFFECTIVENESS OF MATERIALS MANAGEMENT
By Hassan Al-Qudsi .................................................... 22 PROCESS A recently completed research project has
identified key measures of materials-management
effectiveness for industrial construction.
............
By James K. Plemmons and Lansford C. Bell 2 6
DEPARTMENTS
The construction industry is becoming, dard details for retrofit projects. They may not
more and more, a repeat business. Owners pre- realize an architect's intentions for the project.
fer dealing with the same organizations, provid- • Get specialists involved early on in the de-
ed that previous experiences were pleasant. sign stage and before going out for tendering.
These days the biggest bridge burners among Certain areas of specifications (hardware, spe-
contract parties are claims and lawsuits. cialties and other items) typically get modified
Team effort by all parties to a contract— during the construction phase.
owner, architect, construction manager, con- • Consider performing value engineering for
tractor and subcontractors—is a crucial ingre- projects at certain intervals of the design stages
dient for the successful completion of a project. (50%, 75% and 100%). Such a service could be
There is no need to antagonize any of the other instrumental in reducing cost and preempting
parties; the old saying that "you can attract construction problems.
more bees with honey than woth vinegar" still • Perform constructability reviews of projects
holds. Moreover, it is important to keep in at completion of design to eliminate any gray
mind that failure of any party is failure of all. areas that would otherwise result in change or-
Since an engineer plays a number of roles in ders and claims.
a project, he or she should look for ways to re- • Watch out for architects and contractors with
duce, if not eliminate, misunderstandings and large egos, which should be left aside as much
subsequent lawsuits from the jobsite. This may as possible.
not always be possible, but these guidelines
should help parties anticipate disagreements Bidding stage
and find ways to resolve such disputes. It is safe to assume that misinterpretations
of the scope of work start at the point of incep-
Design stage tion—the bidding stage—and get carried
Designers and/or architects are key players through the rest of the project. Some items to
in projects, especially in the case of an in-house keep in mind are:
design-build project. Some things designers • To clarify ambiguities in scope of work to the
should do to fully orchestrate a team are: fullest possible extent.
• Visualize the project, planning for complicat- • To remember that landing the right job is
ed details and unique requirements. more important than landing just any job. The
• Visit the project during construction. Visits bottom line is profit realized at the end of the
can be scheduled to coincide with construction projects and not the total value of projects be-
stages or installation activities associated with ing executed.
items pertinent to each professional's particular • To understand that the contractor's scope of
trade. the work needs to be communicated to the own-
• Ask about methods and techniques for con- er as soon as practical after signing the contract
structing certain items and whether alternate A memo to the owner/architect, using assertive
or simpler methods can sometimes be adopted. request for information (RFI) formats is highly
• Accept for use typical manufacturer's details, recommended. Judges look favorably at docu-
which are available in catalogs. They need not mented facts outlining contractual obligations
be redrawn. The recommended manufacturer's that have been established in the early stages of
name and material particulars should be clearly the construction phase.
given on the drawings. • To define the sCOP e of the work during the
• Leave out special design items for the spe- bidding stage of retrofit jobs. This may be ac-
cialized trade contractor to design. This may complished by asking general and specific ques-
not necessarily be true in case of safety-related tions concerning perceived hidden conditions.
Hassan Al-Qudsi is project
manager for Baker Mellon
components. • To ask the owner and/or architect, on retro-
Stuart Inc., Pittsburgh. • Make contractors aware of hidden, nonstan fit jobs, who has as-built drawings. Note if the
2 2 / JOURNAL OF MANAGEMENT IN ENGINEERING / NOVEMBER/DECEMBER 1995
architect has shown all concealed items on the Construction stage
drawings. At this point every team member has en-
• To ask the owner/architect to clarify general tered the game, so extra care should be taken
statements such as "work necessary for the in- to maintain those fragile relationships among
stallation of' and "whether or not shown on all parties of the contract. Remember that:
drawings." Clarifying such statements will de- • Owners appreciate a chance to reduce some
fine the sCOP e of work better, make the owner of the construction cost. Accordingly, if at all
more comfortable and remove gray areas. In possible, contractors should consider perform-
case the owner and/or architect fails to reply, ing value engineering for the project to allow
the contractor will still be in a better position to the owner to reduce out-of-pocket cost. This
demonstrate in a court of law that he did at- has the added advantage of giving the contrac-
tempt to clarify ambiguities. tor a chance to come up with simpler and more
• To allow for adequate staff ing of the job. Un- efficient ways to execute the same work. Own-
derstaffed organizations cannot produce the re- ers will, most probably, remember this service
sults they are expected to, nor can they properly when considering change-orders implications.
safeguard the contractor's own interest. This service likely will also be considered when
• To keep a copy of a project ' s estimate with choosing team players for future work.
the project 's site staff during the construction • A mobilization period is an excellent opportu-
stage. This helps them determine what kinds of nity to send RFIs concerning items that, through
assumptions were made and improves their review and actual preparation of shop drawings,
ability to anticipate the project's direction. are considered deficient or unclear. Again, it is a
• To update and review the subcontractors' good idea to ask positive questions and suggest
prequalification statements every so often. Sub- possible solutions.
contractors' financial status and their level of • You should always try to reach a win-win situ-
services might be affected by their own in- ation with owners. The site staff needs to give
house workload. Consequently, the construc- alternative solutions to the owner/architect
tion department needs to send periodical evalu- that would satisfy the perceived intent of de-
ation of subcontractor and vendor performance sign. This is true even if there is nothing wrong
to the estimating department, who in turn with the design. The bottom line is if the con-
should take such information into considera- tractor's staff can save the owner money, they
tion during pricing of future jobs. should do it.