Code No: 23MBA

R5-R7
www.prsolutions.in

M.B.A. II Semester Supplimentary Examinations, January 2009 QUANTITATIVE ANALYSIS FOR BUSINESS DECISIONS ---Time: 3 hours Max Marks: 60 Answer any FIVE Questions All Questions carry equal marks

1. Discuss the scope of Operations Research. 2. Describe the various decision making environments. Under what conditions would a majority of one be a satisfactory approach to making decisions? Should a majority of one ever be the basis for action? What kind of decision-making models facilitatehinder decentralization? 3. A manufacturing unit of super Scooters Ltd. Products three components C1 , C2 and C3 that are used in production of scooters. Each component can be produced on either one or two machine M and N. The time required to produce one unit of each component on a machine is presented here: Time in hours Machine M Machine N 0.5 0.6 0.7 0.8 0.9 1.05

Component C1 C2 C3

www.prsolutions.in

The operating cost is Rs. 6 per hour for machine M and Rs. 4 for machine N. the main production centre of the company has sent the requirements for at least 80 units of C1 and C2 each, and not less than 50 units of C3 . Each machine can be operated for 8 hours per day. It has been informed that the machines are due for repairs just after 10 days so that only 80 hours are available on each machine. If the manufacturing unit wishes to minimize the operating cost, your are required to formulate the above problem as an LPP. 4. A company has factories at four dierent places (1,2,3 and 4) which supply items to warehouses A,B,C,D and E. Monthly factory capacities are 200,175,150 and 325, respectively. Monthly warehouse requirements are 110, 90,120,230 and 160 respectively. Unit shipping costs ( in rupees) are given in the following table. From 1 2 3 4 A 13 14 25 10 To B C D - 31 8 9 17 26 11 12 17 21 13 E 20 10 15 17

1 of 2
www.prsolutions.in

Code No: 23MBA

R5-R7

Shipments from 1 to B and from 4 to D are not possible. Determine the optimum distribution plan to minimize the shipping cost. 5. (a) Determine which of the following two person zero sum games are strictly determinable and fair. Give optimum strategies for each player in the case of strictly determinable games:
player B

i. player
B

5 0 0 2

0 2 ii. A 1 4 (b) Determine the range of values of P and Q that will make the pay-o element a2 2 a saddle point for the game whose pay-o matrix (aij) is given below. Player B 2 4 5 Player A 10 7 q 4 q 8 6. (a) State some of the important distributions of arrival intervals and service times. (b) In a car gaurage A, if takes 15 minutes to wash one car. Cars arrive to the gaurage at an average rate of one every 25 minutes and arrival process is Poisson. In Car-gaurage B, it takes 25 minutes to wash one car and cars arrive to this shop at an average rate of one every 45 minutes, the arrival process being Poisson during steady state. Determine: i. At which gaurage you expect the bigger queue. ii. At which gaurage you require more times waiting including the service time. 7. (a) Discuss the general features of the discrete simulation languages. (b) Discuss signicance of validation of Simulation model. 8. (a) What is the dierence between the time estimates of a PERT activity and a CPM activity? (b) Distinguish between an activity and an event. (c) State Fulkersons rule for numbering the nodded in network.