Spring 2007
Project Statement Develop an action plan and timeline for ERP system transformation that includes the scope of a future system and establishes processes to identify the new system requirements.
Table of Contents
Executive Summary ..........................................................................................................2 Section 1: Section 2: Section 3: Overview...................................................................................................4 Current Process .........................................................................................8 Analysis.....................................................................................................9 Cause and Effect Diagram ..........................................................11 Current System Relational Diagram ...........................................12 Comparison of ERP Implementations ........................................13 ERP System Comparisons ..........................................................16
Section 4:
Improvement Theory and Implementation Plan .....................................19 Future System Relational Diagram.............................................21 Relational Diagram Definitions ..................................................22 GANTT Chart .............................................................................25 Action Plan..................................................................................26 Process Mapping Process Map ...................................................27
Recommendations...................................................................................28 Assessment Plan......................................................................................29 Presentation Materials.............................................................................31 Steering Committee Recommendations...................................................... Follow-up Reports to Steering Committee ................................................. TracDat Assessment Impact Report............................................................ Project Retirement Documentation.............................................................
As a result of these numerous recommendations and incentives, an ERP Action Team was formed and the following Project Statement formed the basis of the teams actions.
Project Statement Develop an action plan and timeline for ERP system transformation that includes the scope of a future system and establishes processes to identify the new system requirements.
Project Description This project will develop a comprehensive, multi-year action plan to guide activities related to the implementation of new ERP technologies. This plan will include: A general description of the scope for this project to be used in defining system requirements, A timeline to define the major phases of the long term ERP project, including estimated timeframes and responsible parties for completion, Potential resources and vendors to include software developers as well as independent consulting firms that may assist with the long term project, and A procedure to identify current system processes and capabilities, including strengths and weaknesses .
In order to assure adequate progress towards meeting the above objectives, the following process measures are recommended:
1) Develop project plan 2) Recommend an ERP Migration Committee organization structure 3) Receive positive feedback from College auditors regarding proposed ERP system transformation process and timeline 4) Receive approval from Executive Council and Board of Trustees to move forward with project plan 5) Complete business process re-engineering 6) Complete all user training 7) Go live with new ERP system July 1, 2009 8) Document improvements in business procedures in new ERP system versus current system.
There will be a successful implementation of the new ERP system. From an external perspective, the College will receive a clean audit opinion from its auditors and no significant comments regarding the new system in the Management Letter for FY 10. Internally, a survey of user satisfaction with the new system will be taken twelve months after implementation and at least 75% of users will rate the new system as an improvement.
Action Project Title: ERP System implementation action plan and timeline development
Date: May 2, 2007
Team Members: Jim Batson, Associate Director of Computing Services Sherry Hodnik, Business Analyst Gwen Koehler, Dean of Corporate and Continuing Education Todd McDonald, Assistant Vice President of Finance Laura McGee, Coordinator of Financial Aid & Veterans Services Sandra Moll, Director of Employment Services/Affirmative Action Coordinator Donald Quirk, Director of Institutional Research and Planning Marilyn Weniger, Director of Student Development Missy Spengel, Secretary for Department Chairs of Humanities
Steering Committee Sponsors: Ronald Ally, Vice President for Administration and Treasurer Walter Packard, President
Action Project Statement Develop an action plan and timeline for ERP system transformation that includes the scope of a future system and establishes processes to identify the new system requirements.
Action Project Description The current computer system is antiquated and does not interface readily with the multitude of college-wide applications. This project will develop a comprehensive, multi-year action plan to guide activities related to the implementation of new ERP technologies. This plan will include: A general description of the scope for this project to be used in defining system requirements, A timeline to define the major phases of the long term ERP project, including estimated timeframes and responsible parties for completion, Potential resources and vendors to include software developers as well as independent consulting firms that may assist with the long term project, and A procedure to identify current system processes and capabilities, including strengths and weaknesses The plan is not intended to select a software vendor, define detailed user requirements, or evaluate software products. Action Project Relationships Primary AQIP Category Relationship: 6. Supporting Institutional Operations Other Related AQIP Categories (choose up to four):
1. Helping Students Learn 2. Accomplishing Other Distinctive Objectives 3. Understanding Students and Other Stakeholders Needs 4. Valuing People 5. Leading and Communicating 6. Supporting Institutional Operations 7. Measuring Effectiveness 8. Planning Continuous Improvement 9. Building Collaborative Relationships
Key Performance Indicators Professional Development Training General Education Goals Assessment
Spring, 2007 Data for Mailing Labels Purchasing Effective Room Usage Online Courses Graduation Policy ERP Business Continuity Scholarship Processing AQIP Systems Portfolio
Rationale for Action A replacement or enhancement of the present ERP system is proposed in the College Technology Plan. The Colleges current ERP system is outdated and approaching end of life. Annual maintenance costs continue to increase both in terms of expense paid to outside vendors and internal modifications. In order to improve operational efficiencies, data integrity, access, and system reliability it has been suggested by various consultants that the College replace its current system. Areas Affected The entire College will be impacted by ERP system transformation. However, for this specific action team the primary area impacted is Information Technology. Processes Affected The entire College will be impacted by ERP system transformation. The primary processes affected by this action team (and succeeding teams that will continue with the overall ERP project) are: Project Management/Planning Purchasing/RFP Budgeting Networking (IT) Professional Development Reporting
In addition to the above functions, steering committee members from various departments in the College may spend a significant amount of time on the long-term project. Human Resources Learning and Student Support Services
6
Process Measures 1) Develop project plan 2) Recommend an ERP Migration Committee organization structure 3) Receive positive feedback from College auditors regarding proposed ERP system transformation process and timeline 4) Receive approval from Executive Council and Board of Trustees to move forward with project plan 5) Complete business process re-engineering 6) Complete all user training 7) Go live with new ERP system July 1, 2009 8) Document improvements in business procedures in new ERP system versus current system. Outcome Measures There will be a successful implementation of the new ERP system. From an external perspective, the College will receive a clean audit opinion from its auditors and no significant comments regarding the new system in the Management Letter for FY 10. Internally, a survey of user satisfaction with the new system will be taken twelve months after implementation and at least 75% of users will rate the new system as an improvement. Performance Targets Phase 1 Spring 07 action team will develop the overall project plan. Phase 2 ERP project management team will execute the project plan. Phase 3 New ERP system will go live on July 1, 2009. Keeping Focus The project management team will have representation from all areas of the College and the individual members will keep their respective areas informed of project progress. General information regarding progress will also be made available via InsideMCC and/or other appropriate media.
Current Process There currently is no process in place at MCC for ERP system transformation.
Operational Definitions Scope of future system activities, processes, and information within the institution that would be integrated within in the resulting system System requirements specific tasks, abilities, and technical information that will be necessary components in the resulting system and serve as the basis for developing an RFP (Request For Proposal) Transformation modifying or replacing institutional processes and/or systems ERP System - An Enterprise Requirements Planning System for MCC is a comprehensive set of software, automated procedures and institutional processes that form a single automated system to support and integrate activities across all departments throughout the institution
We reviewed the FY 2006 Management Letter from Sikich, the Colleges auditors, the 2006 Organizational Effectiveness Study from Bridger, and the information presented and notes taken from the Colleges FY 2005 meeting with CampusWorks. All three of these recent reports provide external analysis of the current state of MCCs ERP system and recommendations for the future of the ERP system. The Action Team read each report thoroughly and summarized the high level themes that were common between the reports. Common Themes Derived From CampusWorks, Sikich, and Bridger Reports 1) The life cycle of current ERP is over. 2) The institution needs to be able to make appropriate data driven decisions in a timely manner. 3) Users need a more integrated and efficient system. 4) The system should provide for self-service opportunities for stakeholders. 5) The system needs improved data integrity, management, reporting, and ownership. The identification of these themes led the Action Team to brainstorm the weaknesses of the current system at a high level and show the causes of those weaknesses. We identified many weaknesses and determined that all of the weaknesses fit into one of the following categories; methods, people, resources, and technical capabilities. Included in this section is a Cause and Effect Diagram depicting the various causes of weaknesses in the current system. Another important analysis that the Action Team performed was to review the current software and database systems that are in place across the institution. The purpose of this analysis was to document the as-is status of MCCs current ERP system. We categorized these various software and database systems according to three distinct definitions; 1) Mainframe applications 2) Peripheral applications 3) External applications Included in this section is a visual representation of the categorization of these systems. The systems listed in the center circle represent category 1 above, systems in the first ring out from the center represent category 2 above, and systems in the outer ring represent category 3 above. In Section 4 of this report, a similar diagram is shown depicting how the system and database relationships could be with the implementation of an improved ERP system.
A third analysis project completed by the Action Team was the review of relevant literature and ERP conversion project plans of other institutions and/or governmental agencies. The purpose of this analysis was to determine the common project tasks that an organization goes through when implementing an ERP system. We reviewed articles from Government Finance Review (a monthly publication from the Government Finance Officers Association), Educause, ISIS (Integrated Student Information System) Newsletter, among others, and also project plans from Lucas County, Ohio, the University of Virginia, and Harper Community College. Included in this section is a document titled Comparison of ERP Implementation Stages which lists all of the material reviewed and a summary of each. As a result of this review, the Action Team concluded that the steps listed below would be appropriate to include in the Colleges ERP transformation plan. 1. Project planning 2. Business and operational analysis including gap analysis 3. RFP process and product selection 4. Business process reengineering 5. Installation and configuration 6. Project team training 7. Business requirements mapping to software 8. Module configuration 9. System modification and interfaces 10. Data conversion 11. Custom documentation 12. Conference room pilot 13. Acceptance testing 14. End user training 15. Go Live 16. Post implementation audit and support A fourth analysis project was to review the modules and major functions of current ERP systems. A matrix was created comparing the different vendors and their modules.
10
Technical
Hardware capability
Resources
Lack of skilled support
High cost
Limited expansion
Age of application
Decreased support
Data organization
No relational DB
Data Redundancy
Data integrity
Lack of information
Difficult to use
Lack of time
No training
Non-traditional Keyboard
Not intuitive
Lack of documentation
Many work-arounds
People
Methods
11
2/21/2007
Peripheral Applications
PR GIS Student Recruitment Judicial/Security Application NELNET Fitness Center Graduation
Financial Aid
Mainframe Applications
Admissions
Financial Aid
Nursing
Non-credit Registration
DAIS-I
Special Needs
Course Information
Budgeting
Fixed Assets
Grants Work Keys
E-Syllabus
Accounts Payable
Institutional Research Admissions Library
Faculty Loading
Distance Education Trips Human Resources
Human Resources
12
4/17/2007
http://www.virginia.edu/isp/whatisisp.html, Integrated Systems Project, April 21, 2003 Lucas County, Ohio Planning and Analysis: Scope definition, requirements definition, functional gap analysis, infrastructure analysis, project planning, communicate implementation strategies Design and Development: Infrastructure deployment, define and setup application parameters, data conversion mapping & development, interface specifications & development, report specifications & development, customized features specifications & development, security specifications & development, prototyping to ensure fit, and unit test. Testing and Training: Training, system tests, compile application documentation, and develop deployment plan. Deployment: Produce rollout, final data conversion, finalize deployment plan, initial production support, and post implementation review.
http://www.co.lucas.oh.us/lcis/PeopleSoft/01StrategicImplementationPlan.pdf, Lucas County Strategic Implementation Plan, September 2001 Government Finance Review Project initialization: Lay groundwork for implementation process, identify key project roles and responsibilities.
13
http://www.gfoa.org/services/dfl/trg/Power-to-the-People.pdf, Government Finance Review, December 2001 Lessons Learned Needs Assessment: Evaluate the needs and requirements that will drive the implementation of an ERP system. A needs assessment with a definition of requirements is essential in guiding the start of the project and gauging the success of the project after completion. Software Selection: review the different solutions available and see which system can best fit the identified requirements. As part of the analysis a detailed accounting of gaps should be developed, as well as, an evaluation to compare trade-offs among the various solutions. Process Reengineering: Changes in current business processes that are needed and recommended as a result of an ERP project. Conference Room Pilot: Provides a demonstration of the ERP system that users can test drive before the system configuration is locked down. Training: Determine timing and type of training required. Implementation: Phased implementation or big bang approach.
Education Quarterly Number 2 2001, Dave Swartz and Ken Orgill, pages 20 27. Creating your open source ERP strategy Is ERP for you? Evaluate the current systems functionality and needs and determine if a new ERP system is necessary Define Requirements: Define the functionality required in the new system. Evaluate current processes. Select a Partner: Find a service provider that can help with the process.
14
www.SearchEnterpriseLinus.com Creating your open source ERP strategy, Benard Golden, June 9, 2005.
15
x x x
x x x x x
x x x
x x x x x
x x x x x x x x x x x
x x
x x x x x x x x x x x x x x x x x
x x
x x x
x x x x
x x x
x x
x x x x x x x x x x x x x x x x x x x x x x x
x x
x x x x x x x x
x x x x x x x x
x x x x x x x x
16
x x
x x
x x x
x x x
x x x x x x x x
x x x x x x x x x x x x x x x x x x x x x x x x x
x x
x x
x x
x x x x
x x x x x x x x
x x
x x x x x
17
x x x x x
x x
x x
x x x x x x x x x x x x x x x x x x x x
x x
18
The Trustees and administration of the College requested research into options to upgrade or replace the current ERP system. The purpose of this team was to recommend the process that should be followed in order to implement a new or improved ERP system. A fully integrated ERP system will offer improvements in operational efficiency, data integrity, information access, and system reliability. While it is impossible to predict the amount of time savings, dollar savings, etc. at this stage of plan development, we have depicted the expected overall improvements to the integration of system applications in a relational diagram. These improvements are represented in the Future ERP System Application Relational Diagram included in this section of the report. To help the readers of this report, there is a brief general definition of each system application appearing in this diagram included in this section of the report. As can be seen by comparing this future diagram with the current diagram in Section 3 of this report, there are significant increases in the number of system applications that have moved from being external and peripheral applications to being integrated into and supported by the new ERP system. The benefits of an integrated system are many: Eliminates data redundancy and the need for double keying of information. Provides one source of truth were each data element is stored and maintained in only one place, increasing data accuracy and reducing storage needs. Reduces the number and complexity of interfaces between systems which leads to reduced programming support and maintenance efforts. Decreases the number of potential failure points by eliminating unnecessary separation of systems on multiple computer systems. One consistent application development platform provides increased efficiencies in programming support, server licensing fees and data retrieval. End user training is improved through a consistent user interface (system look and feel) Costs savings are realized through a fewer number of industry standard servers rather than an expensive mainframe in addition to many special purpose servers using several different operating systems. Recovery after a major disaster or system failure is significantly more efficient with a single, integrated database.
While it is impossible to precisely estimate the cost of a new ERP system software, hardware, and associated training and implementation, it is important to note that the College has anticipated this expenditure for several years and has made provisions in the Five Year Financial Plan. The current Five Year Financial Plan allocates $3.0 million in each of fiscal years 2009 and 2010 to support an anticipated ERP system replacement or upgrade. This represents a total commitment of $6.0 million for this project. This amount was developed as the College has gained an understanding of what other community colleges have expended on system replacements and preliminary discussions with technology vendors.
19
This Action Team developed both a Gantt Chart and a Systematic Diagram to document the recommended tasks that must take place for successful ERP system transformation. The Team also created a process map of the process mapping procedure that will be used to document business practices during the ERP implementation. Successful business process engineering and re-engineering requires that a consistent methodology be followed across the College. Business process re-engineering is one of the key process measures that this team has identified as part of an ERP system transformation. The Gantt Chart, Systematic Diagram, and Process Map are all included in this section of the report. The next step to be taken is gaining the approval and support of Executive Council for the implementation that this Team has developed. After that, this Team would like to make a presentation to the Board of Trustees and ask for their approval and support of the implementation plan. After approvals from these two key groups, an ERP Implementation Project Committee would be formed consisting of the following key stakeholders in the implementation process: Assistant Vice President of Information Technology Assistant Vice President of Finance Assistant Vice President of Human Resources Assistant Vice President of Learning and Student Support Services Executive Dean of an Academic Division (one to be selected) Executive Dean of Corporate and Community Education Associate Director of Computing Services Director of Institutional Research and Planning This committee will be charged with executing the ERP system transformation plan as outlined by this Action Team and will oversee the processes outlined in the Gantt Chart. This Action Team will monitor the achievement of the process and outcome measures that have been established.
20
Peripheral Applications
Data Warehouse
Bookstore Trips
System Applications
Registration Financial Aid Course Information
DAIS-I
Kids on Campus
Advising
Judicial/Security Application
Fixed Assets Facilities Scheduling Donor Management (Foundation) Human Resources Payroll
General Ledger
Enterprise Reporting
Human Resources Supplemental Insurance tracking Work Keys
Adult Education
21
4/17/2007
ERP Action Team Future ERP System Application Relational Diagram Definitions
Mainframe Applications/ERP Applications a comprehensive set of software, automated procedures and institutional processes that form a single automated system to support activities across all departments throughout the institution Peripheral Applications software applications which share data with and are used to enhance the mainframe/ERP applications External Applications software applications and/or other data which are not connected to the mainframe/ERP applications but are used to support the operations of the College Application: Accounts Payable Accounts Receivable Admissions Definition: used to process all non-payroll related payments and issue annual 1099 forms used to issue invoices and credits and apply payment to nonstudent accounts used to track paperwork and process coordination associated with processing and tracking applications received and admitting students to the College; including high school transcript evaluation and international student admittance used to track activities related to assisting students with academic and/or career planning used to track student and volunteer activity used to track and manage alumni relationships point of sale system and inventory management for bookstore operations used to plan and prepare the Colleges financial planning documents web based interface to provide a single point of entry for student related automated services used to identify, track, and manage all course offerings (both credit and non-credit) used to integrate data from the various operational systems to provide efficient data analysis and reporting used to evaluate student progress towards degree or certificate completion used to track registered student orientation used by the Foundation to track and manage relationships with current and potential donors facilitates information retrieval and delivery used to maintain consistent syllabi across course offerings used for tracking of work orders and facility maintenance activities used to track usage of room and other usable space throughout
Advising Adult Literacy/GED/ESL Alumni Development Bookstore Budgeting Campus Portal Course Information Data Warehouse Degree Audit Distance Education Donor Management Enterprise Reporting E-Syllabus Facilities Management Facilities Scheduling
22
ERP Action Team Future ERP System Application Relational Diagram Definitions
(Main campus, Shah Center, University Center) Nelnet Faculty Loading Financial Aid the College campus
Fitness Center Fixed Assets Food Service General Ledger Grading & Transcripts Graduation Grants Human Resources Judicial/Security Applications Institutional Research Kids on Campus Library Non-credit Registration Payroll PR-GIS Corporate and Continuing Education Purchasing Registration STAIRS/DAIS-I Student Accounts Student Demographics Student Recruitment
third party payment plan processor that the College transmits to and receives information from used to track and manage the assignments of all faculty used to package federal & state grants, loans, scholarships, etc. and award and disburse financial aid & perform various processes to assure compliance with regulations membership tracking used to track and manage both capital and non-capital equipment owned by the College point of sale system and inventory management for food service operations used to record and summarize all financial transactions of the College used for grade management (including grade entering and change) and evaluation of transcripts and credentials used for graduation evaluation and related activities used to track grant information (application, reporting, etc.) used to track and maintain employee and applicant information used to track all security incident information and student judicial/disciplinary actions various databases used to track a variety of information and report to internal and external stakeholders Used to track qualifications and fee schedules used to maintain library collection and check out materials to cardholders used for non-credit hour generating course scheduling and registration for programs, workshops, seminars, etc. used to process employee payroll mapping software used by marketing department Used to track program participants (past and future) for marketing purposes used to generate purchase orders for the procurement of goods and services used to register, withdraw, and evaluate fulfillment of prerequisites for both credit and non-credit classes used to report adult education grant information to the state used to accept payment from students and manage student account balances Used to track and monitor student information related to tutoring, special needs, student clubs, etc. used to track activity related to identifying potential students
23
ERP Action Team Future ERP System Application Relational Diagram Definitions
Trips Web-based Course Delivery Work Keys and marketing appropriate program offerings Tracking additional information related to trip and tours not maintained in student information used to manage delivery of course materials via the web testing services provided for students and customers
24
ID
Task Name
Duration
Resource Names AQIP Team Steering Comm. Proj Team Proj Team Board/ Admin All Areas IT/ CS Depts. Proj Team All Areas
Proj Team, Key Users
2006 Sep Oct Nov Dec Jan Feb Mar Apr May
2007 Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2008 Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
1 2 3 4 5 6 7 8 9 10 11 12
Project planning AQIP Steering Team Approval Business and operational analysis including gap analysis RFP process and product selection Board Approval Business process reengineering Test Installation and configuration Project team training Business requirements mapping to software Module configuration System modification and interfaces Data conversion Interface Development for external systems Custom documentation Conference room pilot Acceptance testing End User Training Go Live Post implementation audit and support
90d 0d 20d 35d 0d 144d 34d 39d 160d 74d 90d 109d
13
101d
14
48d
15
180d
16
80d
17
44d
Everyone
18
27d
19
85d
25
Updated 03/14/07
Evaluate needs & requirements that will drive the ERP implementation.
Evaluate needs & requirements that will drive the ERP implementation.
Deployment
26
3/9/2007
Notify department administrator that mapping is required and ask for okay and contact person.
Is there documentation?
No
Yes
Yes
Meet with contact to go over process map to correct omissions, additions and/or mapping errors.
No
Yes
No
1
27
Section 5 - Action Team Recommendations and Steering Committee Feedback Form Action Team Recommendations 1. Create an ERP Project Management Team to include the following employees: AVP of Human Resources AVP of Finance AVP of Information Technology AVP of Learning and Student Support Services Associate Director of Computing Services Executive Dean (one to be selected) Executive Dean of Corporate and Continuing Education Director of Institutional Research and Planning 2. Accept the project plan as developed by this Action Team 3. Board presentation of project plan 4. After approvals, charge project management team to move forward with project plan Steering Committee Feedback Comments Action Team Updates Comment
Date
28
McHenry County College - Assessment Impact By Department, Program, Committee Obj... Page 1 of 2
Assessment Impact
McHenry County College ACT 20076 ERP
Objective: Start Date: End Date: Status: Assessment Plan Review Process: Method
Approval
Approval - Approval from Board of Trustees to move forward with project plan. [ v t c j b O e d i H ] l a D
Open
Assessment Methods Being Used Criterion How often will you collect / analyze data?
Objective: Start Date: End Date: Status: Assessment Plan Review Process: Method
Completion
Business Process Re-Engineering - 100% of ERP system processes documented and revised v t c j b O e d i H ] l a D where necessary. [
Open
Assessment Methods Being Used Criterion How often will you collect / analyze data?
100% completion prior to July 1, 2009.
Objective: Start Date: End Date: Status: Assessment Plan Review Process: Method
Completion
Open
Assessment Methods Being Used Criterion How often will you collect / analyze data?
Objective: Start Date: End Date: Status: Assessment Plan Review Process:
Open
29
http://tracdat.mchenry.edu:8080/TracDat/tracdat/reports/reportAssessImpact_DeptObj_Deta... 5/1/2007
McHenry County College - Assessment Impact By Department, Program, Committee Obj... Page 2 of 2
Method
Auditor's Management Letter Comments Survey of user satisfaction
Assessment Methods Being Used Criterion How often will you collect / analyze data?
Clean opinion and no significant At the end of the fiscal year. comments. At least 75% of users will rate the new system as an improvement. 12 months after implementation
Observations Observation
03/20/2007 -- SP - ERP DESCRIPTION: Current ERP system is outdated and inefficient. TYPE: Problem / Limitation
Proposed Transformations
03/20/2007 -- Document and reengineer current processes and develop an employee training program to prepare for the implementation of a fully integrated ERP system.
Follow-Up
Resolved
No
May 1, 2007
30
http://tracdat.mchenry.edu:8080/TracDat/tracdat/reports/reportAssessImpact_DeptObj_Deta... 5/1/2007
ERP
McHenry County College Action Team Final Report May 2, 2007
31
32
Resources
Lack of skilled support Little used technical skills Age (Retired)
People
Methods
Future
Before
33
Gantt Chart
ID Task Name Duration Resource Names AQIP Team Steering Comm. Proj Team Proj Team Board/ Admin All Areas IT/ CS Depts. Proj Team All Areas
Proj Team, Key Users
2006 Sep Oct Nov Dec Jan Feb Mar Apr May 2007 Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May 2008 Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May 2009 Jun Jul Aug Sep Oct Nov Dec
1 2
Project planning
90d 0d 20d 35d 0d 144d 34d 39d 160d 74d 90d 109d
AQIP Steering Team Approval Business and operational analysis 3 including gap analysis
4 5 6 7 8 9 10 11 12
RFP process and product selection Board Approval Business process reengineering Test Installation and configuration Project team training Business requirements mapping to software Module configuration System modification and interfaces Data conversion
101d
Custom documentation Conference room pilot Acceptance testing End User Training Go Live Post implementation audit and support
48d
15
180d
16
80d
17
44d
Everyone
18
27d
19
85d
Recommendations:
Create an ERP Project Management Team Accept the project plan as developed by this Action Team Board presentation of project plan After approvals, charge project management team to move forward with project plan
Outcomes Measures
Successful implementation of new ERP system. External clean audit opinion and no significant comments in FY10 Management Letter. Internal user satisfaction (12 months after implementation) of at least 75% of users.
34
Performance Targets
Spring 2007 Action Team will develop overall action plan. ERP Project Management Team will execute project plan. New ERP System will go live on July 1, 2009.