Académique Documents
Professionnel Documents
Culture Documents
out to impart whiteness to textile fabrics by removing natural colouring matter. The process of dyeing is carried out to improve the marketability of textile products and also to suit the customer needs by adding colour. These two processes are generally carried out in open tank, kier machines, jet dyeing machines, jiggers, soft flow dyeing machines etc. For hosiery goods, it is carried out with winch machines, since it imparts very less tension during operation. Viable processing units can be set up as most of the fabric manufacturing units do not have their own processing units. In this report, details are provided for setting up the unit for bleaching and dyeing of cotton knitted fabrics. Market Potential The demand for hosiery garments is increasing due to its popularity in domestic and export market. There are number of units engaged in manufacturing of knitted cloth and most of these units are not having their own captive processing units. Bleaching and dyeing of knitted fabric produced by these units are normally carried out from outside on paying requisite processing charges. It is, therefore, presumed that setting up of textile processing units is economically very much viable. Basis and Presumptions This project is based on single shift basis with 300 working days in a year. Time period for achieving maximum capacity utilisation is considered from 3rd year from the date on which production is started. Rental value of the building is taken at Rs. 2 per sq. ft. Costs of machinery and equipments/materials indicated refer to a particular make and approximately to those prevailing at the time of preparation of this project. Cost of installation and electrification is taken @ 10% of cost of machinery and equipment. Nonrefundable deposits, project report cost, trial production, security deposit with Electricity Board are classified under pre-operative expenses. Depreciation has been considered at 10% on plant and machinery, 15% on office furniture, fixtures, vehicle and 20% on testing equipments. Interest rate on capital loan has been taken @ 12% per annum. Implementation Schedule The implementation period required for executing this project right from selection of site to starting the trial run production will be 6 months. Technical Aspects Process of Manufacture The knitted fabric to be bleached is thoroughly wet in a soap solution of 2% and piled in kier boiling pan containing 1.5% caustic soda, 2% soda ash and 1% lisapol etc. and allowed to boil for 6-8 hours.
The cloth is washed well and taken to SS winches for bleaching using 2% bleaching powder and then washed thoroughly. This bleached cloth is scoured using hydrochloric acid of 1.5% concentration. After sometime, cloth is washed thoroughly to neutralise the traces of acid. In case of only bleaching the cloth is treated with optical whitening agent, thereafter, it is hydro-extracted, dried and calendered as final operations. In case of dyeing, about 15-20% salts, 2% brightol C paste, 2-4% dyes as per shade are mixed and fabric is treated with the solution in winches. The cloth is allowed to run for several times in order to maintain uniform shade, thereafter, washed, hydro-extracted, dried and calendered. Production Capacity (per annum) Quantity (Kg.) 1. Bleaching Charges 2. Dyeing Charges Total Motive Power 50 HP is required to run the unit and proposed to be obtained from State Electricity Board. Pollution Control As this process involves treatment of chemicals, entrepreneurs are required to obtain NOC from State Pollution Control Board. Energy Conservation Energy can be conserved by proper house-keeping i.e. unnecessary running of boilers, heaters and fans are to be monitored in order to reduce the excess energy consumption. Technical Aspects A. Fixed Capital (i) Land and Building (i) Land 4000 Mtrs. @ Rs. 3000 per Sq. Mtr Boundary wall and gates Factory shed 400 Sq. Mtr, @ Rs. 6000 / Sq. Mtr Raw Material & finished goods storage 500 Sq. Mtr@ Rs. 6000 / Sq. mtr. Rs.1,20,00,000 Rs. 5,00,000 Rs. 24,00,000 4,50,000 4,50,000 9,00,000 Value (Rs.) 1,15,86,000 1,48,05,000 2,63,91,000
Rs. 30,00,000
Office Building 300 Sq. Mtr @ 750 / Sq. Mtr Workers sitting hall 500 Sq.Mtr @ Rs.6000/Mtr
Utility plants area e.g., bore well, raw water storage, boiler, generator and effluent treatment plant 200 Sq. Rs. 12,00,000 Mtr @ Rs. 6000/Sq. Mtr Total (ii) Machinery and Equipments Sl. Description No. 1. 2. 3. SS Winch m/c of 6-4 86 200kg. SS Winch m/c 6-4' 66 size 150kg. MS Kier wall thick 1/4' bottom 8' Steam callendering m/c roller sizes 51/21 Hydro-extractor 40-45 kg capacity No. Rate (Rs.) Amount (Rs.) Rs 2,43,00,000
1 3 2
4.
3,00,000
3,00,000
5.
2,50,000
5,00,000
6.
4 cylinder drier with motor and gear 1 box S.S. Conveyors with ball bearing Baby boiler with storage tank chimney, water softening plant Water softening plant (cap. 6kl/hr), with storage tank pumps and S.S. piping 4
7,00,000
7,00,000
7.
50,000
2,00,000
8.
8,00,000
8,00,000
9.
7,00,000
7,00,000
1 LS
5,00,000 3,00,000
500,000 300,000
accessories Deep tube well with submersible 12. pump with storage tank, pumping and distribution system 13. Mini transport vehicle (3 Wheelers) 14. Fire extinguisher 5 kg capacity 15. Testing equipments Computer colour matching equipment (optional)
5,00,00
5,00,000
1 2 LS
3,00,000 20,000
16.
25,00,000
25,00,000
Total
88,40,000
(iii) Other Fixed Assets (a) Erection and installation (b) Office furniture (c) Pre-operative expenses Total Total Fixed Capital (i) + (ii) + (iii) B. Working Capital (i) Staff and Labour Wages Sl. Designation No. 1. 2. 3. G. Manager Finance and Accountant Computer Operator Nos.
1 2 1
20,000 20,000
4. 5. 6.
6 2 4 3500 3500
Total (i) (ii) Production Staff Dyeing Master 01 no. and shift supervisors 03 nos. Skilled Workers Semi-skilled Workers Lab. Chemists and Attendant Boiler Attendant Electrician 12 15 6 4 3 4000 4000 5,000 3,000
7.
36,000
Total (i) + (ii) Perquisites@ 22% G. Total (iii) Raw Material (per month) Sl. Description No. Rate/ unit (Rs.) 35 20 10
Unit
Qty.
Amount (Rs.)
1. 2. 3.
4. 5. 6. 7. 8. 9.
Lisopal Bleaching Powder Hydrochloric acid Glabour's salt Common salt Optical whitening agent
Kgs. Kgs. Kgs. Kgs. Kgs. Lit. Lit. Lit. Lit. Kgs. Lumpsum
750 3,000 8,000 800 1000 225 1200 2500 750 750
1,13,000 60,000 64,000 8,000 3,000 32,000 24,000 25,000 56,000 1,13,000
10. Hydrogen peroxide 11. Sulphuric acid 12. Acetic acid 13. Dye fixing agent
1,00,000
Total
7,86,000
(iv) Utilities Electricity bill 37.5 x 25 x 4 x 0.8 x 24 Water charges Fuel Coal/furnace oil Fuel for vehicle Total
(Rs.)
(a) Rent (b) Postage/stationery (c) Repair and maintenance (d) Transport/travelling charges (e) Insurance (f) Telephone bills (g) Miscellaneous Total (vi) Total Recurring Expenses (per month) (vii) Total Working Capital for 3 months C. Total Capital Investment (i) Machinery and equipment (ii) Working capital for 3 months Total Machinery Utilisation Capacity utilisation is considered as 75% of installed capacity. Financial Analysis (1) Cost of Production (per year) Recurring expenses Depreciation on machinery @ 10% Depreciation on office furniture, computor and testing equipments @ 20% Depreciation on civil construction @ 5%
6,40,000
5,90,000
Interest on total investment @ 12% Total (2) Turnover (per year) Processing Charges Bleaching Charges Dyeing charges Total Qty. Kgs. 4,50,000 4,50,000 Rate/Kg. 25.75 32.90
57,78,000 2,03,02,000
(3) Net Profit (per year) (4) Net profit ratio (Net profit/Turnover (per year) (5) Rate of return on investment (Net profit/Total capital investment) (6) Break-even Point Fixed Cost Depreciation Rent Interest on capital investment 40% of wages of staff and labour 40% of other expenses Insurance Total (Rs.) 18,44,000 57,78,000 19,05,000 6,43,000 2,28,000
60,89,000 23.07%
12.64%
1,03,98,000
B.E.P.
= 63.07%