Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.

Mueangnakornrajsrima Nakornrajsrima 30310, Thailand Tel : 038-774149-50, 081-7254231 Fax : 038-774150

Report of LPG pump inspection Rong Poh Plant

MACHINE TYPE : SERVICE :

MODEL HEAD

: :

SERIAL No. : FLOWRATE :

DRIVER TYPE POWER

: :

MODEL SPEED

: :

SERIAL No. :

TRANSMISSION TYPE :

MODEL

SERIAL No. :

PTT Public Company Limited Sriracha Petroleum Terminal

Date : 5 Sep 2010 Report No. : Reporter : Geerasak Thepdhwach, Rotating Engineering & Service Co.,Ltd.

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

PART INSPECTION REPORT


ITEM PART IDENTIFICATION 1 P-331C Mechanical seal Lubrication Coupling P-311A Mechanical seal Lubrication Coupling P-311B Mechanical seal Lubrication Coupling P-311C Mechanical seal Lubrication Coupling P-311D Mechanical seal Lubrication Coupling P-311E Mechanical seal Lubrication Coupling PART No.
QTY

GOOD x x x x x x x x x x x x x x x x x x

PART CONDITION AS FOUND CONDITION


RUST SCRATCH CRACK DAMAGE(SPECIFY)

PART EVALUATION
RE-USE REJECT RECONDITION (SPECIFY)

REMARKS

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

PART INSPECTION REPORT


ITEM PART IDENTIFICATION P-311F Mechanical seal Lubrication Coupling 8 P-311R Mechanical seal Lubrication Coupling 9 P-341A Mechanical seal Lubrication Coupling 10 P-341B Mechanical seal Lubrication Coupling 11 P-341C Mechanical seal Lubrication Coupling 12 P-341D Mechanical seal Lubrication Coupling 7 PART No.
QTY

GOOD x x x x x x x x x x x x x x x x x x

PART CONDITION AS FOUND CONDITION


RUST SCRATCH CRACK DAMAGE(SPECIFY)

PART EVALUATION
RE-USE REJECT RECONDITION (SPECIFY)

REMARKS

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

PART INSPECTION REPORT


ITEM PART IDENTIFICATION 13 P-341R Mechanical seal Lubrication Coupling PART No.
QTY

GOOD x x x

PART CONDITION AS FOUND CONDITION


RUST SCRATCH CRACK DAMAGE(SPECIFY)

PART EVALUATION
RE-USE REJECT RECONDITION (SPECIFY)

REMARKS

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill

PUMP INSPECTION REPORT


Client : PTT Sriracha,Chonburi
Pump No. Plant P-311C Rong Poh Area Test date Pump rail loading Sep-10

PUMP DESCRIPTION Manufacturer Serial No. Type NIIGATA Worthington 3HNN1S-122 Capacity Power Speed 50 15 2920 m3/hr HP rpm

1. Pressure Suction : 5.8 barg Discharge : 10.2 barg 4. Vibration and temperature measurement Unit 1 2 Position 0.8 0.8 mm/s Vertical mm/s 1.8 0.8 Horizontal mm/s 0.9 0.8 Axial gE Accerelation Temperature C 45.4 36.8 Condition Alert Good

RUNNING TEST 2. Speed test n/a rpm Speed : 3 0.8 1.5 2.0 39.0
Alert

3. Noise test Position : 4 0.8 0.8 0.8 43.0


Good

n/a Seal

dBc 6

35.0

3 2 1

Description Visual inspection Suction pressure Discharge pressure Speed test Noise test Bearing, vibration test Temperature Mechanical seal Lubrication Coupling Alignment Suction strainer Piping system

Test and Inspection result Result Comment Good Good Good n/a Normal Good Good Good Good Good Good Good Good

PUMP INSPECTION REPORT


Client : PTT Sriracha,Chonburi
Pump No. Plant P-311D Rong Poh Area Test date Pump rail loading Sep-10

PUMP DESCRIPTION Manufacturer Serial No. Type NIIGATA Worthington 3HNN1S-122 Capacity Power Speed 50 15 2920 m3/hr HP rpm

1. Pressure Suction : 5.8 barg Discharge : 10.2 barg 4. Vibration and temperature measurement Position 1 2 Unit Vertical 0.8 1.1 mm/s Horizontal 0.9 0.8 mm/s 0.8 1.1 mm/s Axial gE Accerelation 41.6 39.4 Temperature C Condition Good Satisfactory

RUNNING TEST 2. Speed test n/a rpm Speed : 3 0.8 2.1 1.4 38.6
Alert

3. Noise test Position : 4 0.8 0.9 0.8 42.6


Good

n/a Seal

dBc 6

40.8

3 2 1

Description Visual inspection Suction pressure Discharge pressure Speed test Noise test Bearing, vibration test Temperature Mechanical seal Lubrication Coupling Alignment Suction strainer Piping system

Test and Inspection result Comment Result Good Good Good n/a Normal Good Good Good Good Good Good Good Good

PUMP INSPECTION REPORT


Client : PTT Sriracha,Chonburi
Pump No. Plant P-311F Rong Poh Area Test date Pump rail loading Sep-10

PUMP DESCRIPTION Manufacturer Serial No. Type NIIGATA Worthington 3HNN1S-122 Capacity Power Speed 50 15 2920 m3/hr HP rpm

1. Pressure Suction : 5.8 barg Discharge : 10.2 barg 4. Vibration and temperature measurement Unit 1 2 Position 0.8 0.8 mm/s Vertical mm/s 0.9 0.9 Horizontal mm/s 0.8 0.9 Axial gE Accerelation Temperature C 52.4 45.8 Condition Good Good

RUNNING TEST 2. Speed test n/a rpm Speed : 3 0.8 1.0 0.8 48.0
Satisfactory

3. Noise test Position : 4 0.8 0.8 0.8 46.0


Good

n/a Seal

dBc 6

33.8

3 2 1

Description Visual inspection Suction pressure Discharge pressure Speed test Noise test Bearing, vibration test Temperature Mechanical seal Lubrication Coupling Alignment Suction strainer Piping system

Test and Inspection result Result Comment Good Good Good n/a Normal Good Good Good Good Good Good Good Good

PUMP INSPECTION REPORT


Client : PTT Sriracha,Chonburi
Pump No. Plant P-311E Rong Poh Area Test date Pump rail loading Sep-10

PUMP DESCRIPTION Manufacturer Serial No. Type NIIGATA Worthington 3HNN1S-122 Capacity Power Speed 50 15 2920 m3/hr HP rpm

1. Pressure Suction : 5.8 barg Discharge : 10.2 barg 4. Vibration and temperature measurement Position 1 2 Unit Vertical 0.8 0.8 mm/s Horizontal 0.9 0.8 mm/s 0.8 0.8 mm/s Axial gE Accerelation 53.0 45.2 Temperature C Condition Good Good

RUNNING TEST 2. Speed test n/a rpm Speed : 3 0.8 1.1 0.8 49.8
Satisfactory

3. Noise test Position : 4 0.8 0.9 0.8 48.2


Good

n/a Seal

dBc 6

34.4

3 2 1

Description Visual inspection Suction pressure Discharge pressure Speed test Noise test Bearing, vibration test Temperature Mechanical seal Lubrication Coupling Alignment Suction strainer Piping system

Test and Inspection result Comment Result Good Good Good n/a Normal Good Good Good Good Good Good Good Good

PUMP INSPECTION REPORT


Client : PTT Sriracha,Chonburi
Pump No. Plant P-311A Rong Poh Area Test date Pump rail loading Sep-10

PUMP DESCRIPTION Manufacturer Serial No. Type NIIGATA Worthington 3HNN1S-122 Capacity Power Speed 50 15 2920 m3/hr HP rpm

1. Pressure Suction : 5.8 barg Discharge : 10.2 barg 4. Vibration and temperature measurement Unit 1 2 Position 0.8 0.8 mm/s Vertical mm/s 1.0 1.3 Horizontal mm/s 0.8 0.9 Axial gE Accerelation Temperature C 56.0 39.2 Condition Satisfactory Satisfactory

RUNNING TEST 2. Speed test n/a rpm Speed : 3 0.9 1.3 1.3 38.6
Satisfactory

3. Noise test Position : 4 1.3 0.8 0.8 38.4


Satisfactory

n/a Seal

dBc 6

35.4

3 2 1

Description Visual inspection Suction pressure Discharge pressure Speed test Noise test Bearing, vibration test Temperature Mechanical seal Lubrication Coupling Alignment Suction strainer Piping system

Test and Inspection result Result Comment Good Good Good n/a Normal Good Good Good Good Good Good Good Good

PUMP INSPECTION REPORT


Client : PTT Sriracha,Chonburi
Pump No. Plant P-331C Rong Poh Area Test date Pump truck loading Sep-10

PUMP DESCRIPTION Manufacturer Serial No. Type NIIGATA Worthington 3HNN1S-122 Capacity Power Speed 50 15 2920 m3/hr HP rpm

1. Pressure Suction : 5.8 barg Discharge : 10.2 barg 4. Vibration and temperature measurement Position 1 2 Unit Vertical 0.8 0.8 mm/s Horizontal 0.8 0.9 mm/s 0.8 0.8 mm/s Axial gE Accerelation 56.0 39.2 Temperature C Condition Good Good

RUNNING TEST 2. Speed test n/a rpm Speed : 3 0.8 1.2 0.8 53.4
Satisfactory

3. Noise test Position : 4 0.8 0.8 0.8 46.4


Good

n/a Seal

dBc 6

33.8

3 2 1

Description Visual inspection Suction pressure Discharge pressure Speed test Noise test Bearing, vibration test Temperature Mechanical seal Lubrication Coupling Alignment Suction strainer Piping system

Test and Inspection result Comment Result Good Good Good n/a Normal Good Good Good Good Good Good Good Good

PUMP INSPECTION REPORT


Client : PTT Sriracha,Chonburi
Pump No. Plant P-341C Rong Poh Area Test date Pump rail loading Sep-10

PUMP DESCRIPTION Manufacturer Serial No. Type Siemen&Hinsch 2.972.222 CEHQ 6106/5 AO146.09.4 Capacity Power Speed 17.5 30 1450 m3/hr HP rpm

1. Pressure Suction : 0.5 barg Discharge : 22.2 barg 4. Vibration and temperature measurement Position 1 2 Unit Vertical 0.8 0.8 mm/s Horizontal 0.8 0.8 mm/s 0.8 0.8 mm/s Axial gE Accerelation 38.8 35.8 Temperature C Condition Good Good

RUNNING TEST 2. Speed test n/a rpm Speed : 3 1.3 2.7 1.1 46.6
Satisfactory

3. Noise test Position : 4 0.8 0.8 0.8 35.0


Good

n/a Seal

dBc 6

35.0

3 2 1

Description Visual inspection Suction pressure Discharge pressure Speed test Noise test Bearing, vibration test Temperature Mechanical seal Lubrication Coupling Alignment Suction strainer Piping system

Test and Inspection result Comment Result Good Good Good n/a Normal Good Good Good Good Good Good Good Good

PUMP INSPECTION REPORT


Client : PTT Sriracha,Chonburi
Pump No. Plant P-331C Rong Poh Area Test date Pump truck loading Sep-10

PUMP DESCRIPTION Manufacturer Serial No. Type NIIGATA Worthington 3HNN1S-122 Capacity Power Speed 50 15 2920 m3/hr HP rpm

1. Pressure Suction : 5.8 barg Discharge : 10.2 barg 4. Vibration and temperature measurement Position 1 2 Unit Vertical 0.8 0.8 mm/s Horizontal 0.8 0.9 mm/s 0.8 0.8 mm/s Axial gE Accerelation 56.0 39.2 Temperature C Condition Good Good

RUNNING TEST 2. Speed test n/a rpm Speed : 3 0.8 1.2 0.8 53.4
Satisfactory

3. Noise test Position : 4 0.8 0.8 0.8 46.4


Good

n/a Seal

dBc 6

33.8

3 2 1

Description Visual inspection Suction pressure Discharge pressure Speed test Noise test Bearing, vibration test Temperature Mechanical seal Lubrication Coupling Alignment Suction strainer Piping system

Test and Inspection result Comment Result Good Good Good n/a Normal Good Good Good Good Good Good Good Good

PUMP INSPECTION REPORT


Client : PTT Sriracha,Chonburi
Pump No. Plant P-331B Rong Poh Area Test date Pump truck loading Sep-10

PUMP DESCRIPTION Manufacturer Serial No. Type NIIGATA Worthington 3HNN1S-122 Capacity Power Speed 50 15 2920 m3/hr HP rpm

1. Pressure Suction : 5.8 barg Discharge : 10.2 barg 4. Vibration and temperature measurement Unit 1 2 Position 0.8 1.0 mm/s Vertical mm/s 1.0 1.4 Horizontal mm/s 1.4 0.8 Axial gE Accerelation Temperature C 41.4 38.0 Condition Satisfactory Alert

RUNNING TEST 2. Speed test n/a rpm Speed : 3 0.8 1.0 2.1 42.8
Alert

3. Noise test Position : 4 0.8 1.0 0.8 45.6


Satisfactory

n/a Seal

dBc 6

34.8

3 2 1

Description Visual inspection Suction pressure Discharge pressure Speed test Noise test Bearing, vibration test Temperature Mechanical seal Lubrication Coupling Alignment Suction strainer Piping system

Test and Inspection result Result Comment Good Good Good n/a Normal Good Good Good Good Good Good Good Good

PUMP INSPECTION REPORT


Client : PTT Sriracha,Chonburi
Pump No. Plant P-331A Rong Poh Area Test date Pump truck loading Sep-10

PUMP DESCRIPTION Manufacturer Serial No. Type NIIGATA Worthington ABB8B-RED00-055 3HNN1S-122 Capacity Power Speed 50 15 2920 m3/hr HP rpm

1. Pressure Suction : 5.8 barg Discharge : 10.2 barg 4. Vibration and temperature measurement Position 1 2 Unit Vertical 1.1 0.8 mm/s Horizontal 1.0 0.8 mm/s 1.0 1.1 mm/s Axial gE Accerelation 42.0 40.2 Temperature C Condition Satisfactory Satisfactory

RUNNING TEST 2. Speed test n/a rpm Speed : 3 0.9 1.0 1.9 39.8
Alert

3. Noise test Position : 4 0.8 0.8 0.8 39.4


Good

n/a Seal

dBc 6

35.2

3 2 1

Description Visual inspection Suction pressure Discharge pressure Speed test Noise test Bearing, vibration test Temperature Mechanical seal Lubrication Coupling Alignment Suction strainer Piping system

Test and Inspection result Comment Result Good Good Good n/a Normal Good Good Good Good Good Good Good Good

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

RECOMMENDATION
Before After

R VIEW MOTOR A LPG PUMP SPEC. R = +0.05 A = +0.05


0

UNIT : mm

-0.06

-0.10

-0.16

-0.06

-0.29

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

RECOMMENDATION
Before After

R VIEW MOTOR A LPG PUMP SPEC. R = +0.05 A = +0.05


0

UNIT : mm

-0.12

-0.10

-0.60

-0.16

-0.23

-0.80

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

RECOMMENDATION
Before After

R VIEW MOTOR A LPG PUMP SPEC. R = +0.05 A = +0.05


0

UNIT : mm

-0.08

-0.13

-0.08

-0.07

-0.26

-0.17

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

RECOMMENDATION
Before After

R VIEW MOTOR A LPG PUMP SPEC. R = +0.05 A = +0.05


0

UNIT : mm

+0.19

-0.23

-0.10

-0.19

-0.31

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

RECOMMENDATION
Before After

R VIEW MOTOR A LPG PUMP SPEC. R = +0.05 A = +0.05


0

UNIT : mm

+0.02

+0.05

-0.05

-0.05

+0.04

+0.05

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

RECOMMENDATION
Before After

R VIEW MOTOR A LPG PUMP SPEC. R = +0.05 A = +0.05


0

UNIT : mm

+0.18

+0.05

+0.20

-0.20

+0.02

+0.20

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

RECOMMENDATION
Before After

R VIEW MOTOR A LPG PUMP SPEC. R = +0.05 A = +0.05


0

UNIT : mm

-0.15

-0.46

-0.60

-0.94

-0.70

-1.60

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

RECOMMENDATION
Before After

R VIEW MOTOR A LPG PUMP SPEC. R = +0.05 A = +0.05


0

UNIT : mm

+0.05

-0.32

-0.25

+0.05

-0.51

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

RECOMMENDATION
Before After

R VIEW MOTOR A LPG PUMP SPEC. R = +0.05 A = +0.05


0

UNIT : mm

+0.05

-0.30

-0.25

-0.06

-0.51

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

RECOMMENDATION
Before After

R VIEW MOTOR A LPG PUMP SPEC. R = +0.05 A = +0.05


0

UNIT : mm

-0.02

+0.07

-0.29

-0.25

+0.07

-0.53

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

RECOMMENDATION
Before After

R VIEW MOTOR A LPG PUMP SPEC. R = +0.05 A = +0.05


0

UNIT : mm

-0.08

-0.30

-0.30

+0.07

-0.55

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill

Rotating Engineering & Service Co.,Ltd. 799 / 167 Moo 13 T. Joho A.Mueangnakornrajsrima Nakornrajsrima Tel : 038-774149-50 Fax : 038-774150

PROJECT PLANT MODEL

: PTT Sriracha,Chonburi : Rong Poh : TAG No. : SERIAL : MANUFACTURE :

EQUIPMENT : LPG pump

RECOMMENDATION
Before After

R VIEW MOTOR A LPG PUMP SPEC. R = +0.05 A = +0.05


0

UNIT : mm

+0.05

+0.03

-0.04

-0.27

+0.04

-0.24

INSPECTED BY Mr.Akkaraphol Areephom

REPORTED BY Mr.Geerasak Thepdhwach

SUBMITTED TO Mr.Charin Grinill