First Article Inspection Report

AS/EN9102 Release Sheet & Checklist

Full FAI Report No:

Complete for all FULL FAIRs when Satair P.O states FAIr IAW AS/EN9102 standard & attach to front page of FAIR

Part Number

Issue

P.O No.

Manufacturer

Drawing Design Authority Manufacturer Approval No: Approval I/D Document. No Supplier Contact Details FAIR queries Name Position E-mail Telephone Satair Approved

Full Tick all Applicable Boxes Change of production location Change of manufacturing process Change of Raw Material Specification or Stockist

Partial First Production Run Change of Special Process or Special Processor Change of Inspection Method or Test Product or FAIR previously Rejected

Partial - Tabulated Drawing Lapse in production of 24 months New Drawing Issue No. Other Change: record reason below

FAIR Pack Required Documents Check List a b This sheet AS/EN 9102 Please indicate document(s) included by ticking shaded boxes, ALL applicable documents are required Form 1 Form 2 Form 3 **PLEASE ENSURE THAT ALL DOCUMENTATION SUPPLIED IS FULLY LEGIBLE** c d e f g h Raw Material Certificate of Conformity record details on Form 2 Special processing Certificate of Conformity - Record details on Form 2 (Plating, NDT etc) Test Reports Record Details on Form 2 Referenced balloon drawing (size A4 where possible) Concession permit (must be included for any non-conformance to specification)

Manufacturers C of C No. Vendor Vendor C i Name of C No. NOTE: If you have not received Satair NTS FAIR: NTS-01-05-10 Document, please request from your Satair Buyer Confirmation FAIR completed to AS/EN 9102 & Satair NTS FAIR:NTS-01-05-10 requirements, all required paperwork included in FAIR pack Signed Date:

AS/EN/SJAC 9102 Rev A First Article Inspection


May 2010 Satair FAIR to AS9102

Sheet 1 off

Form 1: Part Number Accountability


1. Part Number 2. Part Name 3. Serial Number 4. FAI Report Number

5. Part Revision Level

6. Drawing Number

7. Drawing revision level

8. Additional Changes

9. Manufacturing Process

10. Organization Name

11. Supplier Code

12. P.O. Number

13. Tick as applicable Detail FAI Assembly FAI b)

14. Tick as applicable Full FAI Partial FAI

Reason for Partial FAI: Full FAIR Report No. (if Partial)

a) if above part number is a detail part only, go to Field 19 if above part number is an assembly, go to the INDEX section below.

INDEX of part numbers or sub-assembly numbers required to make the assembly noted above.
15. Part Number 16. Part Name 17. Part Serial Number 18. FAI Report Number

1) Signature indicates that all characteristics are accounted for; meet drawing requirements or are properly documented for disposition. 2) Also indicate if the FAI is complete per Section 5.4: 19. Signature: 21. Reviewed By: 23. Customer Approval FAI complete FAI not Complete 20. Date 22. Date 24. Date

Name: Saqib Majeed Butt

AS/EN/SJAC9102 Rev A First Article Inspection

Sheet 2 of

Form 2: Product Accountability


May 2010

Raw Material, Specifications and Special Process(s),


Satair FAIR to AS9102

Functional Testing
1. Part Number 2 Part Name 3. Serial Number 4. FAI Report Number

5. Material or Process Name

6. Specification Number

7. Code

8. Special Process Supplier Code

9. Customer Approval Verification

10. Certificate of Conformance number

11. Functional Test Procedure Number

12. Acceptance report number, if applicable

12a. Test Report No.

13. Comments 14. Prepared By : Saqib Majeed Butt Sign: 15. Date

May 2010

Satair FAIR to AS9102

AS/EN/SJAC9102 Rev A First Article Inspection Form 3: Characteristic Accountability, Verification and Compatibility Evaluation
1. Part Number Characteristic Accountability
5. 6. Ref Char Loc No. 7. Characteristic Designator 8. Requirement 9. Results

Sheet 3 of
3. Serial Number 4. FAI Report No.

2. Part Name Inspection / Test Results


10. Designed Tooling 11. Non-Conformance Number

Drawing Notes
14 Drawing Note Reference Number & result
REF No.

RESULT

The signature indicates that all characteristics are accounted for; meet drawing requirements or are properly documented for disposition. 12. Prepared By: Saqib Majeed Butt Sign: 13. Date

May 2010

Satair FAIR to AS9102