Vous êtes sur la page 1sur 2

MECHANICAL COMMISSIONING STANDARD CHECKLIST SHEET STATION : NTPC - Ramagundam Stage III (1 X 500 MW) 01 OF 02 PLANT ITEM: PIPEWORK

- WATER SERVICES PLANT NOMENCLATURE : SYSTEM: UNIT NO : 7 ITEM 1 STATUS YES/NO General conditions satisfy the site Standing instructions as listed in the "Plant Item Comissioning Essential Pre-requisites". ( SCL MS1/1 ). The nameplate legend agrees with the approved NTPC Plant Nomenclature is clearly visible,securely fixed, durable and correleates with remote leabels. The installation is complete and correct in accordance with the latest drawings and specifications. Access for adjustments maintenance and repairs is satisfactory. Check that all bolts , flanges and tapping points are adequately provided. Check that all pipe falls to draining points satisfactory. Check that all fittings on the pipework comply to the requirements of the relevent Indian Standard for that system. Verify , if appropriate , that compression coupling have been inspected on site to confirm that coupling with drawing showing approved location. Check that all eqipment , fittings , temporary supports , anchors used during construction have been removed. Check that floor collars and wall boxes are of suficient size and the pipe suitably positioned to cater for pipe movement within the system constraints. Check that the pipework system,including supports is free to expand and contract within its constraints. Check that adequate venting and draining facilities have been provided for the pipe system. Check that all hose connections and fittings on fire Hydrant pipework are of the instantaneous coupling pattern. Check that all suppots are undamaged, fixed mounted vertically (except where design requires the support at a specified angle.) Check that all support loadings have been correctly set. ACTIVITY REMARKS

4 5

6 7

10

11

12

13

14

15

MECHANICAL COMMISSIONING STANDARD CHECKLIST SHEET 02 OF 02 STATION : NTPC - Ramagundam Stage III (1 X 500 MW) PLANT ITEM: PIPEWORK - WATER SERVICES PLANT NOMENCLATURE : SYSTEM: UNIT NO : 7 ITEM ACTIVITY STATUS REMARKS YES/NO 16 Confirm where possible, that there is a radial clearance between the pipe and the support clip. 17 18 Check that all temporary supports have been withdrawn. Check that all roller and sliding support are clean ,free to move and so constructed that dirt and water can not accumulate . Check that all thrust/anchor points are correctly installed. Confirm adequate support for small bore,horizontal pipes that may be stood upon (or adequate protection for pipes and support for system not strong enough to withstand additional loads). Verify that all valves in the system have been checked. Particularly NRV for correct direction of flow. Flush pipework through to open drain to ensure cleaniness and lack of debris in the lines . Hydraulic pressure test to the appropriate standard and ensure that system is leak free. Check that all temporary fittings,connections ,pades and blanks used for testing &cleaning have been removed ,and that all blanks still required in the system are adequately identified & recorded in the Blank Scedule. Ensure that ,where applicable ,commissioning strainers/filters have been removed and system strainer / filters fitted. During system Initial Operation /proving trails at full working pressure check for : (a) Leaks (b) System Vibration Check for proper painting of pipe line as per colour codes approved by NTPC. Name Signature Date

19 20

21

22

23

24

25

26

28

Elect. Mech. C&I BHEL Erec. BHEL Comg. NTPC Comg.

NTPC Erec.

Agency Elect. Mech. C&I

Vous aimerez peut-être aussi